CLIENT GHIAL
SIGNATURE
1
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
INDEX
PAGE NO
SL NO DESCRIPTION FROM TO
1.0 Scope of work 3 3
2.0 Technical specification references 3 4
3.0 Organization charts 4 4
4.0 Tools & Tackle Required 4 5
5.0 Roles & Responsibilities 5 7
6.0 Work Procedure 8 12
7.0 Environment, Health & Safety 12 12
8.0 Annexure
8.1 Annexure – C Risk Assessment 13 15
8.2 Annexure – D (Inspection Formats) 16 17
2
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
4
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
c. Cutting Plier
d. Screw Driver
e. Sprit level.
f. Plumb bob.
g. Hammer.
h. Ladders & scaffolding.
i. Measurement tape
j. Hammering drill Machine
k. Hand Drill machine
l. Line Tester
m. Box Spanner /Ring Spanner / Double end Spanner Set
n. Millimeter
o. 500V Megger
p. 1000V Megger
q. 11000V HIPOT
r. Electrical Tool Kit
s. Mobile/Tower crane
t. Sling &Shackles
u. Thickness measurement gauge
5
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
a. Ensure all required submittals are made and required plant / tools / material
and manpower are available in a timely manner.
b. Ensure execution of all works are carried out according to approvals, contract
specifications, Mock up approvals, approved shop drawings, Project Quality
Plan, Method Statement and that safety measures are implemented.
c. Ensure necessary coordination with GC Management / PMC Representatives
and other Agencies for timely completion of works.
5.3. Site Engineer :
6
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
8
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
Take adequate care to ensure that panels are not damaged during movement
and also ensure safety of the personnel handling the Panels.
Take necessary permits to install the Panels.
If the foundation frame consists of several parts, bolt/ weld together at the
Prepared joints in the specified sequence, so as to obtain a flush and level top
Surface.
Place the foundation frame accurately in the specified position on the concrete
floor.
Couple the panel with side coupling bolt and nuts.
Fix the Bus bars as manufacture recommended procedure.
Align the foundation frame with the aid of a leveling instrument.
Use Fabricated MS Supports, if required, Install as required on the floor or trench.
Drill holes if the Panel is to be installed on the Floor.
The switch boards shall be properly aligned and bolted to the base channel by at
least 4 bolts.
Check the horizontal and vertical levels using spirit level.
Tighten the nuts & bolts or anchor bolts on the panel with help of Torque
Wrenches.
Equipment's short names to be pasted inside DB's at possible nearest location
Check listed to be furnished.
Tighten the fastening bolts at busbar section; the rated torque is reached as given
below:
Earth the Panel using correct size of strips as per the approved drawings.
Shift the panels from lower level to upper levels by using mobile crane & place
them upon pallet.
Pull the pallet to exact location as per drawings.
9
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
Earthing connection shall be done by two separate and dilettante connection with
earth.
Panel bus bar section shall have the following minimum clearances:
Between phases - 25mm
Between phases & neutral - 25mm
Between phases & earth - 25mm
Between neutral & earth - 19mm
Electro – static powder coating of approved color as per site / Clients requirement
and the thickness shall be 80 microns +/_ 10%.
Wiring shall be neatly bunched, adequately supported and properly routed to
allow for easy access and maintenance.
All control wiring shall be carried out with 1100 / 660 volts grade single core PVC
FRLS cable having stranded copper conductors with minimum cross section of
1.5sqmm for potential circuits and 2.5sqmm for current circuits.
10
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
11
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
All the Panels Spare Gland Holes and other openings on sealed properly after
completion of cable terminations. Ensure cable entries to the panels for adequate
protection against the increase of vermin and insets
Continuity of the bus bars & phase indication at the terminated cable.
Phase rotation test shall be conducted.
Give Inspection call for Testing and Commissioning after Client Approval of the
installation
Record the readings in the Test Formats and get the Approval of the concerned
Engineers.
. If any changing in weather condition i.e- rain, cyclone, stop lifting activity and
wait for clearance
12
EXPANSION of PTB &
METHOD STATEMENT OF LT AIRSIDE at RGIA
PANELS (SITC)
GHIAL/LNT/PTB/E/MS/006
13