GOVERNMENT OF ASSAM

WATER RESOURCES DEPARTMENT

SCHEDULE OF RATES
WATER RESOURCES DEPARTMENT, ASSAM
2022 – 23

Prepared by:

Office of the Chief Engineer


Water Resources Department
Assam Water Centre
5th Floor, Basistha Chariali, Guwahati-29
Schedule of Rate 2022 - 23

[i]
Schedule of Rate 2022 - 23

[ii]
Schedule of Rate 2022 - 23

FOREWORD

The Schedule of rates of the Department was last published in the year 2018-19.
The existing SOR of 2018 - 19 has been revised considering the present market rate of
various materials used in the flood & erosion management works, construction materials,
increase in the price of Fuel & Lubricant, Hire Charges, etc. including the current / latest
circular regarding Labour Wages.

Moreover, a few new item of works has been included in the Schedule of Rate for
2022-23 including the items of Ready-Made Embankment (RME) to cope up with the
changing technology adopted by the Department for flood and erosion management works
and some obsolete items have been omitted from the Schedule of Rate.

The Schedule of Rates for 2022-23 is applicable for all funding Agencies like World
Bank, ADB, NABARD, NEC & NESIDS (under DoNER), NLCPR, NDMF, NDRF, FMBAP, etc in
addition to State Funded works.

Although, all care has been taken to prepare the Schedule in the best possible
manner, there might be undetected error and scope for its further improvement. Further,
if any error/omission is noticed the same may kindly be brought to the notice of the
undersigned for appropriate evaluation & necessary rectification. All Field Engineers of the
Department may therefore feel free to point out any error or give their suggestion for
further improvement and feedback on reasonability of Rates. Moreover, new item of
works, which may be required in future best practices of the Department can be added in
the subsequent updating of this SoR of 2022-23 or may be circulated as Addendum to this
Schedule of Rate.

[iii]
Schedule of Rate 2022 - 23

[iv]
Schedule of Rate 2022 - 23

GENERAL INFORMATION ON THE SCHEDULE OF RATE OF WATER


RESOURCES DEPARTMENT 2022-23

 The rates of items in the Revised Schedule of Rates for 2022-23 are only the Basic
rates and does not include Contractors’ Profit, Forest Royalty, GST, Labour Cess, etc.
or any other Taxes.
 In preparation of estimate for any scheme, 10% Contractors’ Profit is to be added
to the Basic Rates of the items of work.
 Labour rates are considered as per the Notification of the Labour Commissioner,
Govt. of Assam vide Notification No. ACL/41/2004/3173-3241, Dated: -
20.04.2022.
 G.S.T. is to be applied as per the relevant Notification.
 Forest Royalty is applicable as per the Notification No. PEM.130/2021/40 Dtd.
07.10.2021 by the Department of Mines & Minerals, Govt. of Assam.
 Labour Cess at 1% is applicable as per Govt. rule.

[v]
Schedule of Rate 2022 - 23

[vi]
Schedule of Rate 2022 - 23

PREFACE

The Schedule of Rates for all Divisions under Water Resources Department, Assam
was last revised in the year 2018 - 19. Since then, the cost of all materials used in flood and
erosion management works under this Department have increased considerably making
the schedule of rate practically obsolete & unworkable. As such, the revision of the
Schedule of Rates for 2018-19 has become necessary to make the S.o.R. workable at the
present stage.
Accordingly, the revision of S.o.R. was carried out considering the present price of
all materials used in flood and erosion management work including construction materials.
The wages of skilled & unskilled labours are based on the rates fixed by Labour
Commissioner, Govt. of Assam vide Notification No. ACL/41/2004/3173-3241, Dated: -
20.04.2022
The detailed analysis of rate for all items covered by this schedule of rates has been
carried out on the basis been prepared on the basis of the Guidelines laid by CWC, New
Delhi, the IS Codes relating to Flood Management works, River Training Works, Building
Works, etc.
The items in this S.o.R. will cover both original & repair works involved in
Embankment works and are likely to cover almost all aspects of work, which may arise.
A number of new items have been incorporated in this S.o.R. (2022 - 23) taking into
consideration the present demand and requirements of modern construction materials
that have been introduced in the market.
Every endeavor has been made to make this S.o.R. comprehensive and expressive
in all respect. If, however, there is any error or omission, the same may kindly be brought
to the notice of The Chief Engineer, Water Resources Department, Assam.
The S.o.R. (2022 - 23) will be effective for all Divisions under Water Resources
Department, Assam, from the date of its publication.
In this context, the valuable contribution and support extended by the following
officers deserve special thanks. I convey my thanks to: -
a) Er. Bipul Bhatta, Superintending Engineer, Northern Assam Water Resources
Circle, Water Resources Department, Chandmari, Ghy. - 03

[vii]
Schedule of Rate 2022 - 23

b) Er. Nayan Saikia, Superintending Engineer, Nagaghuli Maijan Protection Circle,


Water Resources Department, Jalasampad Bhawan, 1st Floor, Paltan Bazar, Maijan
Road, Jalan Nagar, Dibrugarh - 05
c) Er. Radheswar Langthasa, Superintending Engineer, Silchar Water Resources
Circle, Water Resources Department, Dak Bunglow Road, Near D.C. Office, Silchar
- 01
d) Er. Deep Pegu. Director Design, O/o the Chief Engineer, Water Resources
Department, Assam Water Centre, 5th Floor, Basistha Chariali, Ghy. - 29
e) Dr. Rajib Kumar Goswami, Deputy Chief Engineer, O/o the Chief Engineer, Water
Resources Department, Assam Water Centre, 5th Floor, Basistha Chariali, Ghy. - 29

I would like to express my hurtfulness to the Secretary to the Govt. of Assam, Water
Resources Department, Assam, for his valuable advices and guidance during the
preparation of the SoR 2022-23. Further, I express my sincere gratitude to the Chief
Engineer (Quality Control), W.R. Department for his valuable advice and suggestion in
restructuring the SOR for 2022-23. I would also like to take this opportunity to thank the
Director Design, Water Resources Department and the Dy. - Chief Engineer, Water
Resources Department in finalizing the SoR for 2022 - 23.
At last, I wish to record my deep appreciation to All Additional Chief Engineers,
Superintending Engineers, Technical Staffs of Director Design, Design Division and EDRT
Branch of Water Resources Department for their dedication and sincere effort for
preparation of this Schedule of Rates of Water Resources Department for 2022 - 23

[viii]
Schedule of Rate 2022 - 23

SCHEDULE OF RATE PREPARATION COMMITTEE


Vide Office Order no.: - WR(ED)Tech/279/77/Pt. – II/44, Dated: - 07/04/2022

1. Schedule of Rate Approval Committee: -


a) Chief Engineer, Water Resources Department
b) Chief Engineer (QC), Water Resources Department
c) Deputy Secretary (I), W. R. Deptt.
d) Addl. Chief Engineer, Upper Assam Zone, W. R. Deptt.
e) Addl. Chief Engineer, Lower Assam Zone, W. R. Deptt.
f) Addl. Chief Engineer, Cachar & Hills Zone, W. R. Deptt.
g) Addl. Chief Engineer, AWRMI, W. R. Deptt.
h) Addl. Chief Engineer, Mechanical Zone, W. R. Deptt.
i) Addl. Chief Engineer, Diphu Zone, W. R. Deptt.
j) Addl. Chief Engineer, Kokrajhar Zone, W. R. Deptt.
k) Director Design, W. R. Deptt.
l) Director Planning, W. R. Deptt.
m) Superintending Engineer, Northern Assam W. R. Circle
n) Superintending Engineer, Nagaghuli Maijan W. R. Circle
o) Superintending Engineer, Silchar W. R. Circle

2. Working member for monitoring the overall progress of preparation


of Schedule of Rate: -
a) Overall-In-charge: - Deputy Chief Engineer, W. R. Deptt.
b) Asstt.-In-charge: - Executive Engineer, Construction Cell, W. R. Deptt.
c) Conveyor: - Executive Engineer, Design Division, W. R. Deptt.
d) Asstt. Conveyor: - Asstt. Executive Engineer, Design Division, W. R. Deptt.

2.1. Collection of basic rates for materials and labour: -


a) Asstt. Executive Engineer, Southern Assam W. R. Circle.
b) Sri Samir Dutta, Asstt. Engineer, EDRT, W. R. Deptt.
c) Smt. Dorodi Gogoi, Asstt. Engineer, EDRT, W. R. Deptt.
d) Smt. Violina Basumatary, Asstt. Engineer, EDRT, W. R. Deptt.

[ix]
Schedule of Rate 2022 - 23

2.2. Preparation of Schedule of Rates: -


a) Asstt. Executive Engineer, Guwahati Inv. W. R. Circle, W. R. Deptt.
b) Smt. Jumi Baishya, Asstt. Engineer, EDRT, W. R. Deptt.
c) Sri Jaydeep Goswami, Asstt. Engineer, Design Division, W. R. Deptt.
d) Sri Abhinandan Kashyap, Asstt. Engineer, Design Directorate, W. R.
Deptt.
e) Smt. Ankita Gogoi, Asstt. Engineer, Design Directorate, W. R. Deptt.
f) Smt. Tanushree Kumari Deka, Asstt. Engineer, Design Division, W. R.
Deptt.

2.3. Printing-In-charge: -
a) Asstt. Chief Engineer, W. R. Deptt.
b) Smt. Bidyutmati Barman, Asstt. Engineer, Design Division, W. R. Deptt.
c) Smt Jumi Kalita, Asstt. Engineer, Design Directorate, W. R. Deptt.

[x]
Schedule of Rate 2022 - 23

CONTENT
Chapter Description Page no.

A General notes on Schedule of Rates 1


B Labour Wages & Cost of materials 3
C Hire charges 5
1 Site clearance 7
2 Earth work 9
3 Carriage charges 15
4 Collection of Boulder, Metal, Gravel, Stone, Sand etc. 19
5 Boulder Protection work 21
6 Temporary protection work 23
7 P. S. C. porcupine 35
8 Geo - synthetic works 37
9 Ready-Made Embankment (RME) 43
10 Supply of geo textile materials 45
11 Miscellaneous 61
12 Maintenance of drainage channel 65
13 Mechanical Works 67
14 Dredging 73

[xi]
Schedule of Rate 2022 - 23

SCHEDULE OF WATER RESOURCES DEPARTMENT 2022-23

A. GENERAL NOTES ON SCHEDULE OF RATES

1 These general notes are applicable to all sections of Schedule of Rates to the extent
they are relevant.
2 All materials to be used in work shall conform to relevant specifications of Bureau of
Indian standards (BIS Codes).
3 The rates are inclusive of cost of all materials including finishing, wastage, machinery,
labour, enabling works, small tools & plants, etc.
4 The rates mentioned here in the Schedule of Rates shall be applicable for all the flood
& erosion management works as well as river training works, drainage works & other
allied works within the jurisdiction of Water Resources Department, Govt. of Assam.
5 The basic rates of materials have been considered as per cost involved up to delivery
at site.
6 The rates of items in the Revised Schedule of Rates for 2022-23 are only the
Basic rates and does not include Contractors’ Profit, Forest Royalty, GST,
Labour Cess, etc. or any other Taxes.
7 Unless & otherwise specified, the basic lead and lift of all items of work are 30 m and
1.50m respectively.
8 Unless & otherwise specified, lead charges for Earth / Sand / Gravel / Aggregates and
stones are for compacted or in-situ volume.
9 In the rate analyses of earthwork, compacted volume of earth has been considered.

10 Unless & otherwise specified, the rates are exclusive of cost of de-watering, working
under watery situation, de-silting, river diversion arrangements etc., wherever
applicable.
11 The hire charges of vehicles / machineries / boats / carts etc. have been considered
as per prevailing market rates for deployment at work sites in river side areas.
12 The concrete items like P.S.C. Porcupine members / Concrete slabs are to be cured
properly before supply of the same.
13 The rates for concrete items are inclusive of standard finishing to surfaces.

[1]
Schedule of Rate 2022 - 23

14 The wages of labour has been considered as per Notification No. –


ACL/41/2004/3173-3241 dated 20.04.2022, issued by the Labour Commissioner,
Assam.
15 Most of the flood management works are executed in remote areas in the river side
where the working conditions differ from general areas. Carriage of construction
materials to the work site also involves extra effort for want of defined approach
roads. These aspects have been taken into account while arriving at workable rates
for concerned items of work.
16 For the items not incorporated in this Schedule of Rates., the rates as provided in the
latest schedule of rates of PWD, Assam, may be adopted.
18 The basic rates of labour wages, hire charges, cost of materials, P.O.L. etc. are annexed
herewith in the following pages.
19 All works are to be carried out in accordance with the current Water Resources
Department Govt. of Assam general specifications.

20 The Schedule of Rates of W.R. Department for 2022-23 is effective from


1st September, 2022.

21 The Geo-materials are to be procured only from the listed Contractors empaneled by
the Department vide Circulated No. WR(ED)Tech/7711/2021/Pt-I/13 Dtd.
28.01.2022 and Approval No. WR(G)120/2013/Vol/274 Dtd. 23.06.2022.

[2]
Schedule of Rate 2022 - 23

B. LABOUR WAGE & COST OF MATERIALS


Sl. no. Item Unit Rate
1 Ordinary / unskilled labour Manday ₹ 337.58
2 Semi-skilled labour Manday ₹ 391.54
3 Skilled (other than ITI certificate holder) Manday ₹ 475.29
Skilled (ITI certificate holder or equivalent /
4 Manday ₹ 499.64
clerical)
5 Highly skilled / account or equivalent to accountant Manday ₹ 621.18
6 Petrol Litre ₹ 96.01
7 Diesel Litre ₹ 84.75
8 Lubricant Litre ₹ 350.00
Matured Jati Bamboo 60 mm to 75 mm dia. and 5 m
6 Each ₹ 120.00
to 6m long
Matured Jati Bamboo 75 mm to 100 mm dia. and 6
7 Each ₹ 140.00
m to 7 m long
Matured Bholuka Bamboo 75 mm to 100 mm dia.
8 Each ₹ 240.00
and 6m to 7 m long
Matured Bholuka Bamboo 100 mm to 150 mm dia.
9 Each ₹ 260.00
and 7 m to 8 m long
Barua Bamboo 75 mm to 100 mm dia. 6 m to 7 m
10 Each ₹ 270.00
long
Bethua Bamboo 60 mm to 75 mm dia. 8 m to 9 m
11 Each ₹ 230.00
long
12 Muli Bamboo top Each ₹ 35.00
Hard Jungle Wood post/pole, 100 mm to 150 mm
13 Each ₹ 120.00
dia.
14 Tree branches (dia. minimum 10 cm) Each ₹ 260.00
15 Bamboo top with green foliage 2.50 m to 3.00 m
Each ₹ 60.00
long
16 Jute Sutli Kg ₹ 95.00
17 Coir Sutli Kg ₹ 110.00
18 Galvanized wire
(a) 8 G. Wire Kg ₹ 110.00
(b) 12 G. Wire Kg ₹ 112.00
(c) 16 G. Wire Kg ₹ 115.00
(d) 18 G. Wire Kg ₹ 115.00
19 Iron bolts and nuts of different size Kg ₹ 107.00
20 Iron Patent Nails of different size Kg ₹ 110.00
21 Serviceable empty cement bags Each ₹ 7.00

[3]
Schedule of Rate 2022 - 23

Sl. no. Item Unit Rate


22 Timber Planks (2nd class) Cum ₹ 25,000.00
23 O.P.C. Cement (ISI Mark) Bag ₹ 450.00
24 Coarse Sand Cum ₹ 1,800.00
25 Stone Aggregate 20mm down Cum ₹ 1,900.00
26 M.S. Rod Kg ₹ 104.00
27 Tor Steel (TMT Bar) Kg ₹ 85.00
28 6mm High tensile steel wires/strands Kg ₹ 90.00
29 Polythene Sheet (40 micron) Sqm ₹ 16.00
30 P.V.C. Pipe, 20 mm (Non I.S.I) Rm ₹ 35.00
31 P.V.C. Pipe 100 mm (Ordinary quality) Rm ₹ 125.00
32 Black Wire Kg ₹ 85.00
33 Brick (1st class) Each ₹ 11.00
34 U' shaped bolt 19.00 mm Each ₹ 75.00
35 Steel shuttering (considering use of 50 times) Sqm ₹ 39.00

[4]
Schedule of Rate 2022 - 23

C. HIRE CHARGES

Sl. no. Item Unit Rate


1 Hire charges of diesel trucks with driver and helper
but excluding fuel and lubricant.
(a) 2 Ton Capacity Day ₹ 1,600.00
(b) 6 Ton Capacity Day ₹ 2,500.00
(c) 10 Ton Capacity Day ₹ 3,200.00
2 Hire Charge of hydraulic Excavator with bucket
capacity of 0.60 Cum to 0.90 Cum along with Hour ₹ 1,300.00
operator excluding fuel and lubricant.
3 Hire charge of Tripper of 10 ton capacity along with
Hour ₹ 650.00
operator excluding fuel and lubricant.
4 Hire charge of Tractor with minimum 40 HP engine
capacity along with trailer of 2.50 Cum capacity Day ₹ 1,800.00
including operator and excluding fuel and lubricant.
5 Hire charge of engine boat with minimum 10 HP
engine and load carrying capacity of not less than
Day ₹ 3,100.00
3.00 ton along with operator and helpers excluding
cost of P.O.L.
6 Hire charge of mar boat (twin boat) along with
dumping platform and with a minimum load
carrying capacity of 5.00 Ton. Day ₹ 1,200.00
(Without boat man)
7 Hire charge of country boat up to 20 quintal capacity
Day ₹ 625.00
(Without boatman)
8 Hire charge of country boat with capacity of 20 to 40
quintal. Day ₹ 1,200.00
(Without boatman).
9 Hire charge of bullock/buffalo cart with tyre wheel
Day ₹ 1,000.00
along with cart man.
10 Hire charge of hand cart with cart man. Day ₹ 900.00
11 Hire charge of 5 HP water pump with operator and
Day ₹ 1,100.00
excluding P.O.L.
12 Hire charge of 25 KVA Diesel Generating Set. with
Day ₹ 2,000.00
operator and P.O.L.
13 Hire charge of Hydraulic equipment comprising of
pump with 10 HP engine, necessary Jets, pipes etc.
Day ₹ 1,700.00
including cost of operator and excluding fuel and
lubricant complete.
14 Hire charge of Crane with capacity 80 ton with
Hour ₹ 1,350.00
operator excluding fuel & lubricant.

[5]
Schedule of Rate 2022 - 23

Sl. no. Item Unit Rate


15 Hire charge of Crane with capacity 35 ton with
Hour ₹ 950.00
operator excluding fuel & lubricant.
16 Hire charge of Crane with capacity 3 ton with
Hour ₹ 400.00
operator excluding fuel & lubricant.
17 Hire charge of Crane with capacity 8 ton with
Hour ₹ 850.00
operator excluding fuel & lubricant.
18 Hire charge of Barge of size 405 × 110 × 25 Ft. with
launching jacket weight up 6000 MT and having
minimum clear deck area of 3300 Sqm with Day ₹ 17,000.00
operator excluding fuel & lubricant.
19 Hire Charge (excluding fuel) of Bitumen emulsion
Hour ₹ 1,274.00
pressure distributor
20 Hire Charge (excluding fuel) of Concrete pump of 45
Hour ₹ 200.00
& 30 Cum capacity
21 Hire Charge (excluding fuel) of Concrete bucket Hour
22 Hire Charge (excluding fuel) of Dozer D 50 Hour ₹ 2,096.00
23 Hire Charge (excluding fuel) of Needle vibrator Hour ₹ 101.00
24 Hire Charge (excluding fuel) of Pre stressing Jack
Hour ₹ 113.00
with access.
25 Hire Charge (excluding fuel) of Smooth wheeled 80 -
Hour ₹ 1,039.00
100 kN tandem roller
26 Hire Charge (excluding fuel) of Three wheel 80 - 100
Hour ₹ 652.00
kN Static Roller
27 Hire Charge (excluding fuel) of Tractor with trolley Hour ₹ 409.00

[6]
Schedule of Rate 2022 - 23

CHAPTER – 1 :: SITE CLEARANCE

Sl. no. Description Unit Basic rate


Light Jungles: Clearing light jungles and trees up to
15 cm. girth including cutting, uprooting roots and
stumps, removing them from the site of the work
1.01 Sqm ₹ 7.72
up to a distance of 30 m, etc. complete as directed.
(When 30% of the area is covered by shrubs, trees
etc.)
Medium Jungles: Clearing medium jungles and
trees up to 15 cm. girth including cutting, uprooting
roots and stumps, removing them from the site of
1.02 Sqm ₹ 11.92
the work, etc. complete as directed.
(When 30% to 60 % of the area is covered by
shrubs, trees etc.)
Thick Jungles: Clearing thick jungles and trees up to
15 cm girth including cutting, uprooting roots and
stumps, removing them from the site of the work
1.03 Sqm ₹ 23.84
up to a distance of 30 m, etc. complete as directed.
(When more than 60 % of the area is covered by
shrubs, trees etc.)
Felling trees including uprooting roots and stumps
up to 50 cm. below ground, cutting into pieces and
1.04
removing the same from the site of work etc.
complete as directed.
1.04.1 Trees above 0.50 m and up to 1 m girth: Each ₹ 170.79
1.04.2 Trees above 1.0 m and up to 2.0 m girth: Each ₹ 423.98
Cutting bamboo, uprooting roots & stumps
1.05 including removing them from the site of work, etc. Sqm ₹ 463.44
complete as directed.
Uprooting bamboo clumps where bamboo already
1.06 removed including removing stumps to a minimum Sqm ₹ 238.39
distance of 30 m etc., complete as directed.
Cutting banana trees, uprooting roots & stumps
1.07 including removing them from the site of work up Sqm ₹ 178.79
to a distance of 30 m etc. complete as directed.

[7]
Schedule of Rate 2022 - 23

[8]
Schedule of Rate 2022 - 23

CHAPTER - 2 :: EARTH WORK


NOTE: - Manual means will be adopted where machineries cannot be deployed
due to site condition and the same is to be certified by the concerned EE
& SE.

Sl. no. Description Unit Basic rate


Earth work in embankment and other structures by
head load free from roots & vegetation and filling in
uniform layers not exceeding 25 cm. thick including
ploughing or roughening or benching the seat, dug
belling, profiling, breaking clods up to 4.0 cm. cube,
2.01 watering if necessary dressing as per design section;
for normal soil and for initial lift up to 1.5 m and initial
lead up to 30 m, complete as directed.
(10% deduction will be made from the section
measured quantities of the completed and compacted
sections on account of shrinkage).
Normal Soil :
2.01.1 For initial lift up to 1.5 m and initial lead up to 30 m Cum ₹ 178.91
Extra lead for every 30 m or part thereof beyond the
2.01.2 Cum ₹ 25.75
initial lead of 30 m
Extra lift for every 1.50 m or part thereof beyond the
2.01.3 Cum ₹ 13.24
initial lift of 1.50 m
Earth work in embankment by head load free from
roots & vegetation and filling in uniform layers not
exceeding 25 cm. thick including ploughing or
roughening or benching the seat, dug belling,
profiling, breaking clods up to 4.0 cm. cube, and
2.02 watering if necessary dressing as per design section,
for wet and sticky soil and for initial lift up to 1.5 m
and initial lead up to 30 m, etc. complete as directed.
(10% deduction will be made from the section
measured quantities of the completed and compacted
sections on account of shrinkage).
Wet & Sticky Soil:
For initial lead up to 30 m and lift of 1.5 m Cum ₹ 207.04
Collection and supply of Earth by head load free from
roots & vegetation and stacking in regular measurable
stacks at suitable places including clearing and
2.03 levelling the stacking seats, breaking clods up to 4.0
cm cube, etc. complete as directed.
(12.5% deduction will be made from measured
quantity on account of shrinkage)
For initial lead up to 30 m and lift of 1.5 m Cum ₹ 200.09

[9]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


Earth work in embankment by manual means by
truck carriage in ordinary/normal soil excluding
sandy and rocky soil free from roots & vegetation and
filling in uniform layers not exceeding 25 cm thick
including ploughing or roughening or benching the
2.04 seats, removing all debris, breaking clods up to 4cm
cube, dressing as per design section, etc. complete as
directed.
(10% deduction will be made from the section
measured quantities of the completed and compacted
on account of shrinkage)
2.04.1 For initial lead up to 1 Km and for all lifts. Cum ₹ 211.88
For every Km extra lead beyond initial lead of 1 Km &
2.04.2 Cum/Km ₹ 18.41
up to 10 Km.
For every Km extra lead beyond initial lead of 10 Km
2.04.3 Cum/Km ₹ 14.43
& up to 20 Km.
Earth work in embankment by manual means by
truck carriage in ordinary/normal soil excluding
sandy and rocky soil free from roots & vegetation and
stacking in regular measurable stacks at suitable
2.05 places including clearing debris, breaking clods up to
4 cm cube, etc. complete as directed.
(12.50 % deduction will be made from measured
quantities on account of shrinkage)
2.05.1 For initial lead up to 1 Km and for all lifts Cum ₹ 226.07
For every Km extra lead beyond initial lead of 1 Km &
2.05.2 Cum/Km ₹ 19.73
up to 10 Km.
For every Km extra lead beyond initial lead of 10 Km
2.05.3 Cum/Km ₹ 14.75
& up to 20 Km.
Earth work in embankment by mechanical means by
truck carriage in ordinary/normal soil excluding
sandy and rocky soil free from roots & vegetation and
stacking in regular measurable stacks at suitable
2.06 places including clearing debris, breaking clods up to
4 cm cube, excluding payment of forest royalty if any,
etc.
(12.50 % deduction will be made from measured
quantities on account of shrinkage).
2.06.1 For initial lead up to 1 Km and for all lifts. Cum ₹ 225.52
For every Km extra lead beyond initial lead of 1 Km &
2.06.2 Cum/Km ₹17.05
up to 10 Km.
2.06.3 For every Km extra lead beyond initial lead of 10 Km Cum/Km ₹14.52

2.07 Earth work in excavation of drainage channel to the


proper grade and slopes as required including
[10]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


disposing the excavated debris/soil to a safe distance
of minimum 50 m distance, etc. complete as directed.
For lead up to 50 m and all lifts
2.07.1 Normal Soil Cum ₹ 113.19
2.07.2 Wet & Sticky Soil Cum ₹ 136.03
Earth work in excavation of drainage channel by
mechanical means to the proper grade and slopes as
required including disposing the excavated
2.08 debris/soil to a safe distance of minimum 50 m
distance, etc. complete as directed.
For lead up to 50 m and all lifts
2.08.1 Normal Soil Cum ₹ 87.24
Earth work in excavation of drainage channel by
mechanical means to the proper grade and slopes as
required including disposing the excavated
2.09 debris/soil to a safe distance of minimum 50 m
distance, etc. complete as directed.
For lead up to 50 m and all lifts
2.09.1 Wet & Sticky Soil Cum ₹ 128.63
Earthwork in bank trimming to the designed section
/slope by manual means including removing the
2.10 Cum ₹ 107.57
trimmed soils to a minimum distance of 30 m,
complete as directed.
Earthwork in bank trimming to the designed section
/slope by mechanical means including removing the
2.11 Cum ₹ 87.68
trimmed soils to a minimum distance of 30 m,
complete as directed.
Earthwork in grabbing the seat of the embankment
up-to 0.3 m depth by mechanical means and
2.12 Hec ₹ 22,489.60
depositing the soils outside the country side toe of the
proposed structures, etc. complete as directed.
Spreading of earth stacks over the crest and slope of
embankment and places as directed in uniform layer
of 22 cm. thick including breaking clods, dressing,
2.13 Cum ₹ 93.50
ramming etc. complete where necessary including
dressing of the embankment, etc. complete as
directed.
Labour for ramming with cast iron rammer to proper
2.14 compaction including watering if necessary, etc.
complete as directed.
2.14.1 Ordinary soil: Cum ₹ 16.37
2.14.2 Soil mixed with murrum: Cum ₹ 19.50

2.15 Turfing with grass sods of largest possible rectangles Sqm ₹ 20.78
of 12 cm. minimum thickness placed closely including
[11]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


dressing earth pegging with Jati bamboo split,
watering till the grass grows for a lead up to 90 m and
all lifts, etc. complete as directed.
Earth work in excavation by hydraulic excavator, to
proper grade and slopes as required including
utilizing the spoils for filling works in the vicinity
2.16 including removing roots & vegetation, dressing to Cum ₹ 89.80
design section etc. complete as directed.
Ordinary Soil, For depth up to 3.00 m
Earth work in filling by mechanical means by
deploying hydraulic excavator and trippers etc.
including ramming with locally available ordinary soil
excluding rocky soil with all lead and lift, transporting
to site, spreading, dressing as per design section
2.17 including ploughing or roughening or benching the
seats, removing all debris, breaking clods up to 2.5 cm
cube, etc. complete as directed.
(12.5 % deduction will be made from the section
measured quantities of the completed and compacted
earth work on account of shrinkage)
2.17.1 For initial lead up to 1 Km and for all lifts Cum ₹ 272.71
For every Km extra lead beyond initial lead of 1 Km &
2.17.2 Cum/Km ₹ 23.66
up to 10 Km.
For every Km extra lead beyond initial lead of 10 Km
2.17.3 Cum/Km ₹ 19.63
& up to 20 Km.
Earth work in embankment by Tractor-trailer
carriage in locally available ordinary soil excluding
rocky soil free from roots & vegetation and filling in
uniform layers not exceeding 22 cm. thick including
ploughing or roughening or benching the seats,
2.18 removing all debris, breaking clods up to 2.5 cm cube,
dressing as per design section, etc. complete as
directed.
(10% deduction will be made from the section
measured quantities of the completed and compacted
earth work on account of shrinkage).
2.18.01 For initial lead up to 1 Km and for all lifts Cum ₹ 219.46
For every Km extra lead beyond initial lead of 1 Km &
2.18.02 Cum/Km ₹ 17.25
up to 10 Km.
2.18.03 For beyond initial 10 Km & for all lifts. Cum/Km ₹ 16.80
Earth work in embankment by Tractor-trailer
carriage by mechanical means with locally available
2.19 ordinary soil excluding rocky soil free from roots &
vegetation and filling in uniform layers not exceeding
22 cm. thick including ploughing or roughening or
[12]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


benching the seats, removing all debris, breaking
clods up to 2.5 cm cube, dressing as per design
section, etc. complete as directed.
(10% deduction will be made from the section
measured quantities of the completed and compacted
earth work on account of shrinkage).
2.19.01 For initial lead up to 1 Km and for all lifts Cum ₹ 195.00
For every Km extra lead beyond initial lead of 1 Km &
2.19.02 Cum/Km ₹ 14.54
up to 10 Km.
2.19.03 For beyond initial 10 Km & for all lifts. Cum/Km ₹ 15.47
Earth work in embankment by Tractor-trailer
carriage by manual means in locally available
ordinary soil excluding rocky soil free from roots &
vegetation and stacking in regular measurable stacks
2.20 at suitable places including clearing debries, breaking
clods up to 4 cm cube, etc. complete as directed.
(12.50 % deduction will be made from measured
quantities on account of shrinkage)
2.20.1 For initial lead up to 1 Km and for all lifts Cum ₹ 231.20
For every Km extra lead beyond initial lead of 1 Km &
2.20.2 Cum/Km ₹ 19.03
up to 10 Km.
2.20.3 For every Km extra lead beyond initial lead 10 Km. Cum/Km ₹ 17.10
Earth work in embankment by Tractor-trailer
carriage by mechanical means in locally available
ordinary soil excluding rocky soil free from roots &
vegetation and stacking in regular measurable stacks
2.21
at suitable places including clearing debries, breaking
clods up to 4 cm cube, etc. complete as directed.
(12.50 % deduction will be made from measured
quantities on account of shrinkage)
2.21.1 For initial lead up to 1 Km and for all lifts Cum ₹ 213.81
For every Km extra lead beyond initial lead of 1 Km &
2.21.2 Cum/Km ₹ 15.71
up to 10 Km.
2.21.3 For every Km extra lead beyond initial lead 10 Km. Cum/Km ₹ 15.08
Collection and supply of River silt by truck carriage
free from debries and other foreign material, etc.
2.22 complete as directed.
By manual Means
2.22.01 For initial up to 1.00 Km & for all lifts. Cum ₹ 228.61
2.22.02 For beyond initial 1 Km & up to 10.00 Km & for all lifts. Cum/Km ₹ 15.47
2.22.03 For beyond initial 10 Km & for all lifts. Cum/Km ₹ 12.68

[13]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


Collection and supply of River silt by truck carriage
free from debries and other foreign material, etc.
2.23 complete as directed.
By mechanical Means
2.23.01 For initial up to 1.00 Km & for all lifts. Cum ₹ 204.07
2.23.02 For beyond initial 1 Km & up to 10.00 Km & for all lifts. Cum/Km ₹ 17.41
2.23.03 For beyond initial 10 Km & for all lifts. Cum/Km ₹ 13.95
Earth work in embankment by Mechanical means by
truck carriage with locally available ordinary/normal
soil excluding sandy and rocky soil free from roots &
vegetation and filling in uniform layers not exceeding
25 cm thick including ploughing or roughening or
2.24
benching the seats, removing all debries, breaking
clods up to 4 cm cube, dressing as per design section
and compaction in layers not exceeding 30 cm in
thickness and core cutter soil test at every layer and
every 500 m distance, etc. complete as directed.
A. Compaction with three wheel static roller of 80-100 kN capacity
2.24.1 For initial Lead up to 1.00 Km for all lifts. Cum ₹ 214.42
2.24.2 For beyond initial 1 Km & up to 10.00 Km & for all lifts. Cum/Km ₹ 16.20
2.24.3 For beyond initial 10 Km & for all lifts. Cum/Km ₹ 14.07
A. Compaction with vibratory roller of 80-100 kN capacity
2.24.1 For initial Lead up to 1.00 Km for all lifts. Cum ₹ 242.81
2.24.2 For beyond initial 1 Km & up to 10.00 Km & for all lifts. Cum/Km ₹ 16.39
2.24.3 For beyond initial 10 Km & for all lifts. Cum/Km ₹ 14.44
Earth work in embankment by tractor trailer carriage
by Mechanical means with locally available
ordinary/normal soil excluding sandy and rocky soil
free from roots & vegetation and filling in uniform
layers not exceeding 25 cm thick including ploughing
or roughening or benching the seats, removing all
2.25
debries, breaking clods up to 4cm cube, dressing as
per design section and compaction with three wheel
static roller of 80-100 KN capacity in layers not
exceeding 30 cm in thickness and core cutter soil test
at every layer and every 500m distance, etc. complete
as directed.
2.25.1 For initial Lead up to 1.00 Km for all lifts. Cum ₹ 191.06
2.25.2 For beyond initial 1 Km & up to 10.00 Km & for all lifts. Cum/Km ₹ 16.19
2.25.3 For beyond initial 10 Km & for all lifts. Cum/Km ₹ 13.95

[14]
Schedule of Rate 2022 - 23

CHAPTER - 3 :: CARRIAGE CHARGES

Sl. no. Description Unit Basic rate


Carriage of boulder/metal /sand /gravel, etc.
including loading & unloading cost of P.O.L. etc.
3.01 complete and including hire charge of truck with
driver and handyman etc., complete as directed.
On kutcha road/ embankment./ quarry road (Road
maintained by contractor)
3.01.1 For 1st Km: Cum ₹ 267.68
For every Km extra lead beyond initial lead of 1 Km
3.01.2 Cum/Km ₹ 23.03
& up to 10 Km.
For every Km extra lead beyond 10 Km & up to 20
3.01.3 Cum/Km ₹ 22.42
Km.
3.01.4 For every Km extra lead beyond 20 Km. Cum/Km ₹ 19.89
Carriage of boulder/metal /sand /gravel, etc.
including loading & unloading cost of P.O.L. etc.
complete and including hire charge of truck with
3.02 driver and handyman etc., complete as directed.
On kutcha road/ embankment/ quarry road (road
not maintained by contractor)
3.02.1 For 1st Km: Cum ₹ 254.04
For every Km extra lead beyond initial lead of 1 Km
3.02.2 Cum/Km ₹ 14.32
& up to 10 Km.
For every Km extra lead beyond 10 Km & up to 20
3.02.3 Cum/Km ₹ 13.01
Km.
3.02.4 For every Km extra lead beyond 20 Km. Cum/Km ₹ 12.69
Carriage of boulder/metal /sand /gravel, etc.
including loading & unloading cost of P.O.L. etc.
3.03 complete and including hire charge of truck with
driver and handyman etc., complete as directed.
Gravel Road
3.03.1 For 1st Km: Cum ₹ 212.07
For every Km extra lead beyond initial lead of 1 Km
3.03.2 Cum/Km ₹ 14.19
& up to 10 Km.
For every Km extra lead beyond 10 Km & up to 20
3.03.3 Cum/Km ₹ 11.76
Km.
3.03.4 For every Km extra lead beyond 20 Km. Cum/Km ₹ 10.63
Carriage of boulder/metal /sand /gravel, etc.
including loading & unloading cost of P.O.L. etc.
3.04 complete and including hire charge of truck with
driver and handyman etc., complete as directed.
Pucca Road

[15]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


3.04.1 For 1st Km: Cum ₹ 201.54
For every Km extra lead beyond initial lead of 1 Km
3.04.2 Cum/Km ₹ 10.51
& up to 10 Km.
For every Km extra lead beyond 10 Km & up to 20
3.04.3 Cum/Km ₹ 9.50
Km.
3.04.4 For every Km extra lead beyond 20 Km. Cum/Km ₹ 8.20
Local carriage of boulder, metal, gravel/sand etc.
from the approachable site beyond 150 m and up to
3.00 Km from the work site including loading from
3.05 Cum ₹ 210.08
stack and unloading at work site with 10 (Ten) ton
capacity truck, supplying P.O.L. etc. complete as
directed.
Carriage of wire netting sheets of size 2.57 × 1.67 m
made of 8 G wire of 152 mm Sq. mesh including
loading & unloading, stacking cost of P.O.L. etc.
3.06 complete and including hire charge of truck with Sheet/Km ₹ 0.29
driver and handyman, etc. completed as directed.
(Distance to be calculated from divisional store)
Carriage of Geo Bags of size 2.00 × 1.50 m including
loading & unloading, stacking cost of P.O.L. etc.
3.07 complete and including hire charge of truck with Bag/Km ₹ 0.096
driver and handyman, etc. completed as directed.
(Distance to be calculated from Guwahati)
Carriage of Geo Bags of size 1.03 × 0.70 m / 1.0 x
0.7m including loading & unloading, stacking, etc.
3.08 complete and including hire charge of truck with Bag/Km ₹ 0.014
driver and handyman cost of POL etc. completed as
directed. (Distance to be calculated from Guwahati)
Carriage of 300 gsm Geo sheet of including loading
& unloading, stacking cost of P.O.L. etc. complete
3.09 and including hire charge of truck with driver and Sqm/Km ₹ 0.013
handyman, etc. completed as directed.
(Distance to be calculated from Guwahati)
Carriage of Geo Mat of including loading &
unloading, stacking cost of P.O.L., etc. complete and
3.10 including hire charge of truck with driver and Sqm/Km ₹ 0.023
handyman, etc. completed as directed.
(Distance to be calculated from Guwahati)
Carriage of Gabion box of size 2.0 m × 2.0 m × 0.45
m including loading & unloading, cost of P.O.L. etc.
3.11 complete and including hire charge of truck with Each/Km ₹ 0.115
driver and handyman, etc. completed as directed.
(Distance to be calculated from Guwahati)

[16]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


Analysis of rate for Carriage of Geo Bags type-C of
size 1.5x 1.0 m including loading & unloading,
3.12 Stacking, etc. complete and including hire charge of Each/Km ₹ 0.038
truck with driver and handyman cost of POL etc.
completed as directed.

[17]
Schedule of Rate 2022 - 23

[18]
Schedule of Rate 2022 - 23

CHAPTER - 4 :: COLLECTION OF BOULDER

Sl. no. Description Unit Basic rate


Collection of blasted boulder of size 23 cm. to 30 cm in
average and minimum weight 30 Kg having
i. Specific gravity not less than 2.65,
ii. Aggregate Chrushing < 30% (Wearing) & < 45%
(Non - wearing)
iii. Impact Value (%) max < 30% (Wearing) & < 45%
(Non - wearing) and
iv. Abrasion Value (%) < 30% (Wearing) & < 50%
(Non - wearing)
4.01 (Materials conforming to IS 2386 part III & IV 1963) Cum ₹ 1,105.28
and free from dust, dirt and other foreign materials
including local carriage and stacking in regular
measurable stacks of approximate 1 (One) m. height at
site, etc. complete as directed.
(10% under sized (minimum 10 cm) boulder is
allowable for packing/filling the gaps occurred during
execution of works).
(15% deduction will be made from the stack measured
quantities on account of void)
Collection of river boulder of size 23 cm to 30 cm in
average and minimum weight 30 Kg having
i. Specific gravity not less than 2.65,
ii. Aggregate Chrushing < 30% (Wearing) & < 45%
(Non - wearing)
iii. Impact Value (%) max < 30% (Wearing) & < 45%
(Non - wearing) and
iv. Abrasion Value (%) < 30% (Wearing) & < 50%
(Non - wearing)
4.02 (Materials conforming to IS 2386 part III & IV 1963) Cum ₹ 1,041.90
free from dust, dirt and other foreign materials
including necessary carriage and stacking in regular
measurable stacks at site, monopoly, etc. complete as
directed.
(10% under sized (not less than 10 cm) boulder is
allowable for packing/filling the gaps occurred during
execution of works) Complete as directed.
(15% deduction will be made from the stack measured
quantities on account of void).
Collection of river gravel & shingles of size 20 mm to
40 mm in average free from dust, dirt and other foreign
4.03 materials including necessary carriage and stacking in Cum ₹ 966.43
regular measurable stacks at quarry site, monopoly
etc. complete as directed.

[19]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(7.5% deduction will be made from the stack
measured quantities on account of void).
Collection of broken stone metal of size 20 mm to 40 m
in average from blasted rock free from dust, dirt and
other foreign materials screening properly, stacking in
4.04 suitable stacks at quarry site, etc. complete as directed. Cum ₹ 1,307.62
(7.5% deduction will be made from the stack
measured quantities on account of void).
Collection of sand gravel from approved quarry
containing 60% sand and 40% gravel free from
disintegrated and flaky pieces of vegetation and other
4.05 Cum ₹ 685.16
deleterious matters, adherent coating etc. including
stacking in suitable stacks at quarry site etc. complete
as directed.
Collection and supply of hand chiselled broken stone
boulder of size 23 cm to 30 cm in average having
i. Specific gravity not less than 2.65,
ii. Aggregate Chrushing < 30% (Wearing) & < 45%
(Non - wearing)
iii. Impact Value (%) max < 30% (Wearing) & < 45%
(Non - wearing) and
iv. Abrasion Value (%) < 30% (Wearing) & < 50%
4.06 (Non - wearing) Cum ₹ 951.11
(Materials conforming to IS 2386 part III & IV 1963)
and free from dust, dirt and other foreign materials
including local carriage and stacking in regular
measurable stacks of approximate 1 (One) m. height at
quarry site, etc. complete as directed.
(15% deduction will be made from the stack measured
quantities on account of void).
Collection of stacking river pea - gravel of size 6 mm to
20 mm in average free from dust, dirt and other foreign
4.07 materials including necessary carriage and stacking in Cum ₹ 1,022.74
regular measurable stacks at quarry site, monopoly,
etc. Complete as directed.
Collection and supply of sand from approved quarry of
specified grade for construction work free from
4.08 Cum ₹ 516.37
debries and other foreign material etc. complete as
directed.
Collection of broken stone metal of size 13 mm. to
38 mm in average free from dust, dirt and other foreign
4.09 materials including local carriage and stacking in Cum ₹ 1,208.74
regular measurable stacks of approximate 1 (One) m.
height at quarry site, etc. complete as directed.

[20]
Schedule of Rate 2022 - 23

CHAPTER - 5 :: PROTECTION WORKS

Sl. no. Description Unit Basic rate


Labour charge for dumping boulder in cage made of
wire netting sheets of size 2.57 × 1.66 m of 8 G
galvanized wire making the cage from 2 nos. of wire
netting sheet by tying the projected wires, filling
boulder inside in cage, launching the same in position,
5.01
including all handling charges and including site
carriage of boulder from stack yard/ dump site within
a distance of 150 m. etc. complete as directed.
(Wire netting sheets to be supplied by the Department
free of cost)
5.01.1 Without boat Cage ₹ 396.52
5.01.2 With Mar Boat Cage ₹ 630.22
5.01.03 With Engine Boat Cage ₹ 800.86
Labour charge for loose dumping boulder of 23 cm. to
30 cm. size in loose in eroded portion of river bank/
5.02 bed including handling charge and including site
carriage of boulder from stack yard/ dump site within
a distance of 150 m etc. complete as directed.
5.02.1 Without boat Cum ₹ 357.58
5.02.2 With Mar Boat Cum ₹ 591.28
5.02.3 With Engine Boat Cum ₹ 761.92
Labour charge for dumping boulder in sausage made
of hexagonal wire netting rolls of size (15.24 × 3.66) m
cutting the netting as required making the sausage by
tying the projected ends with 8 G wire including
supplying & tying the wire at every joint after filling the
5.03 sausage with boulders properly and launching in
places handling charges including site carriage of
boulder from stack yard/ dump site within a distance
of 150 m. etc. complete as directed.
(Wire netting sheets to be supplied by the Department
free of cost)
5.03.1 Without boat Cum ₹ 382.13
Labour charge for construction of dead - man with one
- man size boulder in cage of wire netting sheets of size
(2.57 m × 1.66) m and launching the same in river
bed/slope including site carriage of boulder either
5.04
manually or by boat as the case may be and passing the
wire rope round the dead - man including tying the end
of the wire rope by ‘u’ bolt as necessary, etc. complete
as directed.

[21]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(Wire netting sheets, boulders, ‘U’ bolt will be supplied
by the Department free of cost)
5.04.1 Without boat Each ₹ 214.12
5.04.2 With boat Each ₹ 336.56
Labour charge for laying and pitching boulder of 23 cm
to 30 cm size (man size) including dressing the seat,
5.05 ramming to proper size & slope, properly hand packed
including site carriage of boulder from stacks within a
distance of 150 m etc. complete as directed.
5.05.1 Without boat Cum ₹ 305.43
Labour charge for making filter bed of required
thickness with stone metal of size 13 mm to 38 mm
5.06 over the trimmed surface of river bank/embankment,
slope, including site carriage of metal within a distance
of 150 m etc. complete as directed.
5.06.1 Without boat Cum ₹ 256.31

[22]
Schedule of Rate 2022 - 23

CHAPTER - 6 :: TEMPORARY PROTECTION WORKS

Sl. no. Description Unit Basic rate


Construction of single ‘A’ type spur with whole
Bhaluka bamboo of size 7.5 cm to 10 cm dia. placed
close to each other, driven 1.00 m to 1.20 m below
ground keeping 1.2 m to 1.8m above ground and tied
with cane or 16 G wire and horizontal double half Jati
6.01 Rm ₹ 1,265.39
bamboo kamies not more than 50cm apart providing
whole Bhaluka bamboo runner at the apex including
cost of all material etc. Complete as directed.
(Using Bhaluka Bamboo at the rate of 4.125 nos./Rm
& Jati Bamboo at the rate of 0.53 nos./Rm)
Construction of single ‘A’ type spur with whole
Bhaluka bamboo of size 7.5 cm to 10 cm dia. placed
close to each other, driven 1.20 m to 1.80 m below
ground keeping 2 m to 3 m above ground and tied
with cane or 16G wire double half Jati bamboo
6.02 horizontal kamies at not less than 50 cm apart and Rm ₹ 1,801.79
providing double whole Jati bamboo horizontal
runners at the apex including cost of all material etc.
Complete as directed.
(Using Bhaluka Bamboo at the rate of 6.125 nos./Rm
& Jati Bamboo at the rate of 1.00 no/Rm)
Construction of whole bamboo single palisading with
matured Bhaluka bamboo posts 7.5 cm to 10 cm dia.,
15 cm clear apart 1.50 m to 1.80 m above ground and
1.00 m to 1.20 m below ground with Bhaluka bamboo
6.03 inclined struts placed at 1.5 m a part tied with three Rm ₹ 605.26
rows of horizontal half Jati bamboo kamies etc.
complete as directed.
(Using Bhaluka Bamboo at the rate of 10.14 nos./Rm
& Jati Bamboo at the rate of 2.40 nos./Rm)
Construction of whole bamboo single palisading with
matured Jati bamboo stacks 7.5 cm to 100 mm dia., 15
cm clear apart 1.20 m to 1.80 m above ground and
1.00 m to 1.20 m below ground with Jati bamboo
6.04 inclined struts fixed 1.2 m to 1.5 m apart tied with Rm ₹ 934.95
three rows of horizontal half Jati bamboo kamies with
cane/wire of 16 G to 18 G etc. complete as directed.
(Using Bhaluka Bamboo at the rate of 8.67 nos./Rm &
Jati Bamboo at the rate of 2.40 nos./Rm)
Construction of whole bamboo double palisading of
1.5 m width with matured Jati bamboo stacks 7.5 cm
6.05 to 10 cm dia., 15 cm clear apart 1.20 m to 1.80 m Rm ₹ 987.18
above ground and 1.00 m to 1.20 m below ground,
providing horizontal half Jati bamboo at not more
[23]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


than 0.45 m apart kamies and strengthened with
whole Jati bamboo inclined struts at 1.5 m apart and
cross struts tied with 16 G. galvd. wire/cane etc.
complete as directed.
(Using Bhaluka Bamboo at the rate of 13.00 nos./Rm
& Jati Bamboo at the rate of 2.40 nos./Rm)
Construction of whole bamboo double palisading of
1.5 m width with matured Bhaluka bamboo 7.5 cm to
10 cm dia., 15 cm clear apart, 1.5 m to 2.5 m above and
1.2 m to 1.5 m below ground tied with cane/wire 16
G. and horizontal half Jati bamboo kamies at not more
than 0.45 m apart including fixing whole Bhaluka
6.06 bamboo cross struts at 1.50 m apart tied together Rm ₹ 2,815.97
with Bhaluka bamboo posts, including inside lining
with straight woven bamboo chattai and laying
properly including fitting fixing, etc. complete as
directed.
(Using Bhaluka Bamboo at the rate of 27.18 nos./Rm
& Jati Bamboo at the rate of 8.00 nos./Rm)
Construction of whole bamboo double palisading of
1.5 m width with matured Bhaluka bamboo 10 cm to
15 cm dia., closely packed 3.00 m to 3.50 m above G.L.
by hand shaking and hammering by the 10 Kg.
hammer from 15 to 20 Qtl. capacity country boat
below G.L. tied with 16 G./18 G. wire and Bhaluka
6.07 Rm ₹ 2,876.14
bamboo cross struts 1.50 m apart tied together with
two rows of half Jati bamboo kamies and Bhaluka
inclined struts at 1.50 m interval on C/S, etc. complete
as directed.
(Using Bhaluka Bamboo at the rate of 52.00 nos./Rm
& Jati Bamboo at the rate of 1.60 nos./Rm)
Construction of leets fencing with 75 mm to 100 mm
dia. matured Jati bamboo stacks placed 150 mm clear
6.08 a part and 1.2 m to 1.8 m above ground and 1.00 m to Rm ₹ 490.79
1.2 m below ground level, etc. complete as directed.
(Using Jati Bamboo at the rate of 8.67 nos./Rm)
Providing bamboo raft made of matured Jati bamboo
75 mm to 100 mm dia. at 0.90 m c/c both ways and
whole Jati bamboo diagonal and all crossing points
being securely tied with 16 G/18 G wire or cane and
6.09 tying tree branches of minimum length of 2.5 m with Rm ₹ 394.61
green foliage downwards from every crossing points
of the bamboos, weighing with 6 nos. of earth filled
cement bags and anchoring to bank with 3 nos. of 8G
wire of minimum length of 15 m each including

[24]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


supplying all materials handling & launching in water,
etc. complete as directed.
(Using Jati Bamboo at the rate of 14 nos./Rm)
Supplying and launching whole trees 1 m to 2 m girth
and 6.0 m minimum length at eroded river bank with
spreaded branches and green beams anchoring the
same on the river bank with 8 G wire 3 nos. tied to
pieces of 15 cm.to 20 cm. dia., 1.50 m long hard
6.10 jungles wood post buried at bank 0.9 m to 1.20 m Per tree ₹ 434.48
below ground to a safe distance of 15 m from the
eroded bank including supplying of all material and
carriage of trees to the site of with elephant or by any
other means as necessary, etc. as necessary for the
trees etc. and complete as directed.
Construction and launching of bamboo porcupine
made of 12 nos. 2 m long whole matured Bhaluka
bamboo of size 7.5 cm. to 10 cm. making 0.50 × 0.50 ×
0.50 m size cube at the middle and fitting fixing cross
whole Bhaluka bamboo 2 m long 8 nos. on 4 sides of
the cube as directed and nailing with patent nails of
30 cm long total 36 nos. each point and joint as
directed including bending sharp edge of the patent
nails tying each point and joint with 12 G. wire closely
to the side of the cube with Bhaluka bamboo 15 cm Per
6.11 ₹ 2,623.83
apart placed from the inside of the main members of Porcupine
all sides including nailing with nails and bending the
protruding edge tying every joint with 12G wire
making holes in each internodes of bamboo with
chisel, filling the cube with boulder including local
carriage to the site and launching properly etc.
including cost of material and complete as directed.
(Using Bhaluka Bamboo at the rate of 5.79 nos./Rm)
(Boulder is to be supplied by the Department free of
cost in the vicinity of work site.)
Supplying fitting and fixing Jati bamboo chattai fitted
with split Jati bamboo kamies at 0.5 m C/C and edge
6.12
tied with 24 G. galvd. tying wire, etc. Complete as
directed.
Straight woven: (Using Jati Bamboo at the rate of
6.12.1 Sqm ₹ 247.66
23.00 nos./Rm)
Diagonally woven: (Using Jati Bamboo at the rate of
6.12.2 Sqm ₹ 279.59
26.00 nos./Rm)
Supplying and launching of tree branches of 5 cm to
6.13 7.5 cm dia. 2.5 m to 3.5 m long with green foliage tied Bundle ₹ 1,242.38
in bundle (4 nos. in a bundle) with coir sutli securely
anchored to stout Jati bamboo post of 7.5 to 10 cm
[25]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


dia., hard jungles wood peg driven at least 1.00 m
below ground and 0.50 m above at a minimum safe
distance of 7.50 m from the river bank with 8 G. galvd.
tying wire, weighing the bundle with two nos. of earth
filled cement bags tied with coir sutli etc. complete as
directed.
(Using Jati Bamboo at the rate of 21.43 nos./Rm)
Supplying and launching of tree branches of 7.5 cm to
10 cm dia. 3.5 m to 4.0 m long with green foliage tied
in bundle 3 nos. in a bundle with coir sutli securely
anchored to stout Jati bamboo post of 7.5 to 10 cm
dia., hard jungles wood peg driven at least 1.00 m
6.14 below ground and 0.50 m above at a minimum safe Bundle ₹ 1,018.22
distance of 7.50 m from the river bank with 8 G. galvd.
tying wire, weighing the bundle with two nos. of earth
filled cement bags tied with coir sutli etc. complete as
directed.
(Using Jati Bamboo at the rate of 21.43 nos./Rm)
Supplying and launching bamboo tops of 3.0 m to 3.50
m long with green foliage tied to the post of ‘A’ type of
6.15 Each ₹ 118.69
spur, lets fencing palisading etc., with coir sutli, etc.
complete as directed.
Filling and laying of Geo bags made of polyester fibre
of size 1.0 m × 0.70 m excluding excavation of
sand/silt from flood plain or adjacent chars within a
distance of 90 m of the work site, filling geo bags with
sand/silt having minimum weighing 122.00 Kg and
minimum volume 0.081 Cum after filling, double
locking chain stitching the mouth of the filled bags
with polypropylene thread by power driven double
needle double stitched machine, stacking the same in
6.16 batches of 100, carrying the same to the dumping site
including all handling charges and local carriage
within a distance of 150 m and laying properly as
directed.
(Sand/silt, Polyester Geo Bag and Polypropylene
thread will be supplied by the department free of
cost)
(To be used only as emergency flood fighting material
during flood season)
6.16.01 Without Boat Bag ₹ 34.82
6.16.02 With Engine Boat Bag ₹ 55.73
6.16.03 With Mar Boat Bag ₹ 47.80

6.17 Filling and laying of Geo bags made of polyester fibre


of size 1.0 m × 0.70 m including excavation of
[26]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


sand/silt from flood plain or adjacent chars within a
distance of 90 m of the work site, filling geo bags with
sand/silt having minimum weighing 122.00 Kg and
minimum volume 0.081 Cum after filling, double
locking chain stitching the mouth of the filled bags
with polypropylene thread by power driven double
needle double stitched machine, stacking the same in
batches of 100, carrying the same to the dumping site
including all handling charges and local carriage
within a distance of 150 m and laying properly as
directed.
(Sand/silt, Polyester Geo Bag and polypropylene
thread will be supplied by the Department free of
cost)
(To be used only as emergency flood fighting material
during flood season)
6.17.01 Without Boat Bag ₹ 44.61
6.17.02 With Engine Boat Bag ₹ 65.52
6.17.03 With Mar Boat Bag ₹ 57.59
Labour charge for filling of empty cement bags to
attain minimum filled up volume of 0.028 Cum with
filled up size of 0.7 m × 0.40 m × 0.10 m, laying and
pitching of the earth filled cement bags including
6.18 excavation and borrowing earth, breaking clods,
filling in bags and supplying and stitching the mouth
with jute sutli, etc. complete as directed.
(Cement bags will be supplied by the department free
of cost).
6.18.01 For borrowing earth from a distance up to 30 m. Bag ₹ 9.70
For borrowing earth from a distance beyond 30 m. &
6.18.02 Bag ₹ 12.68
up to 60 m.
Labour charge for filling of empty cement bags to
attain minimum filled up volume of 0.03 Cum with
filled up size of 0.75 m × 0.40 m × 0.10 m, laying and
pitching of the earth filled cement bags including
excavation and borrowing earth, breaking clods,
6.19 filling in bags and supplying and stitching the mouth
with jute sutli, etc. complete as directed.
(Cement bags will be supplied by the department free
of cost).
(To be used only as emergency flood fighting material
during flood season)
6.19.01 For borrowing earth from a distance up to 30 m. Bag ₹ 10.43

[27]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


For borrowing earth from a distance beyond 30 m. &
6.19.02 Bag ₹ 13.52
up to 60 m.
Labour charge for filling of sand bags of size 0.90 m ×
0.50 m to attain minimum filled up volume of 0.038
Cum with filled up size of 0.80 m × 0.40 m × 0.12 m,
laying and pitching of the earth filled sand bags
including excavation and borrowing earth, breaking
6.20 clods, filling in bags and supplying and stitching the
mouth with jute sutli, etc. complete as directed.
(Sand bags will be supplied by the department free of
cost).
(To be used only as emergency flood fighting material
during flood season)
6.20.01 For borrowing earth from a distance up to 30 m. Bag ₹ 12.68
For borrowing earth from a distance beyond 30m. &
6.20.02 Bag ₹ 17.03
up to 60 m.
Labour for laying Gunny/Manure bags filled with
sand/earth (As locally available) including stitching,
6.21
laying, fixing in position as directed complete with
supply of bag, sutli, etc. all complete as directed.
6.21.01 Gunny / Manure bags 37 Kg. Capacity (0.12 Cum) Bag ₹ 36.31
6.21.02 Gunny / Manure bags 75 Kg. Capacity (0.25 Cum) Bag ₹ 72.07

Supplying and Construction of bamboo cribs


fabricated out in pyramid shape out of matured
Bholuka bamboo 75 mm to 100 mm dia. complete
with all the branches and foliages with apex point at
7.00 m from the bottom. At 0.60 m above the base of
1st row of horizontal stiffeners of size 4.00 m × 3.00 m
are to be provided along with 2 nos. of cross struts. A
second set of horizontal stiffeners along with cross
stiffeners similar to the 1st set are provided at height
of 4.00 m from the bottom. One set of cross bracing
6.22 are to be provided in each face in between the 1st and
2nd horizontal stiffeners. All the stiffeners and inclined
members are to be projected 0.30 m beyond the
longitudinal members. All the points are to be pinned
with 22 Cm long patent nails and protruding end is to
be bent properly to have a firm grip and the apex
point is also to be clustered with 8 G. wire. All the
members are to be punched with chisel or auger. The
cribs are to be weighted with 25 nos. of earth filled
polythene empty cement bags in all corners and
middle of 1st and 2nd row of horizontal stiffeners of the

[28]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


cribs, tied firmly with 8 G galvanised wire etc.
including cost of material and complete as directed.
(Using Bhaluka Bamboo at the rate of 14.00 nos./Rm)
6.22.01 Construction of Crib Crib ₹ 6,247.66
6.22.02 Launching of crib with boat Crib ₹ 165.86
6.22.03 Launching of crib without boat Crib ₹ 79.44
Construction of whole Bholuka Bamboo double
Screen with matured Bholuka Bamboo stacks 75 mm
to 100 mm dia., placed at 30 cm clear apart (i.e. 40 cm
C/C) driven 4.00 m to 4.50 m below ground and 3.0 m
to 3.50 m above ground with hydraulic driving
equipment including hire charge of equipment, cost of
6.23 P.O.L. etc. and providing with 1 (One) row of Rm ₹ 984.89
horizontal half Jati bamboo kamies tied with
galvanised wire of 16 G to 18 G etc. complete as
directed.
(Using Bhaluka Bamboo at the rate of 240.00 nos./Rm
& Jati Bamboo at the rate of 9.60 nos./Rm)
Supplying and driving of matured Bholuka bamboo post
of 75 mm to 100 mm dia. placed 3 nos of posts together
tightened by 8 G wire in form of bundle and driven 4.0
m to 4.50 m below ground and 3.0 m to 3.50 m above
6.24 ground by hydraulic driving equipment including hire Each ₹ 836.90
charge of equipment cost of P.O.L etc. complete as
directed.
(Using Bhaluka Bamboo at the rate of 240.00 nos./Rm)
Construction of single ‘A’ type spur with whole Barua
bamboo of size 7.5 cm to 10 cm dia. placed close to
each other, driven 1.00 m to 1.20 m below ground
keeping 1.2 m to 1.8 m above ground and tied with
cane or 16 G wire and horizontal double half Bethua
6.25 Rm ₹ 2,368.79
bamboo kamies not more than 50 cm apart providing
whole Barua bamboo runner at the apex including
cost of all material etc., complete as directed.
(Using Barua Bamboo at the rate of 4.13 nos./Rm &
Bethua Bamboo at the rate of 0.53 nos./Rm)
Construction of single ‘A’ type spur with whole Barua
bamboo of size 7.5 cm to 10 cm dia. placed close to
each other, driven 1.20 m to 1.80 m below ground
keeping 2 m to 3 m above ground and tied with cane
6.26 or 16 G wire double half Bethua bamboo horizontal Rm ₹ 2,129.29
kamies at not less than 50 cm apart and providing
double whole Bethua bamboo horizontal runners at
the apex including cost of all material etc., complete as
directed.

[29]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(Using Barua Bamboo at the rate of 6.25 nos./Rm &
Bethua Bamboo at the rate of 1 nos./Rm)
Construction of whole bamboo single palisading with
matured Barua bamboo stacks of 7.5 cm to 100 mm
dia., 15 cm clear apart driven 1.20 m to 1.50 m above
ground and 1.00 m to 1.20 m below ground with
Barua bamboo inclined struts fixed at 1.50 m apart
6.27 Rm ₹ 701.63
tied with three rows of horizontal half Bethua
bamboo kamies with G.I. wire of 16 G to 18 G etc.,
complete as directed.
(Using Barua Bamboo at the rate of 10.14 nos./Rm &
Bethua Bamboo at the rate of 2.40 nos./Rm)
Construction of whole bamboo single palisading with
matured Barua bamboo stacks of 7.5 cm to 100 mm
dia., 15 cm clear apart driven 1.50 m to 1.80 m above
ground and 1.00 m to 1.20 m below ground with
Barua bamboo inclined struts fixed at 1.50 m apart
6.28 tied with three rows of horizontal half Bethua Rm ₹ 729.76
bamboo kamies with G.I. wire of 16 G to 18 G etc.
complete as directed.
(Using Barua Bamboo at the rate of 10.14 nos./Rm &
Bethua Bamboo at the rate of 2.40 nos./Rm)
Construction of whole bamboo single palisading with
matured Barua bamboo stacks of 7.5 cm to 100 mm
dia., 15 cm clear apart driven 1.80 m to 2.50 m above
ground and 1.20 m to 1.50 m below ground with
Barua bamboo inclined struts fixed at 1.50 m apart
6.29 Rm ₹ 1,009.00
tied with three rows of horizontal half Bethua
bamboo kamies with G.I. wire of 16 G to 18 G etc.
complete as directed.
(Using Barua Bamboo at the rate of 14.47 nos./Rm &
Bethua Bamboo at the rate of 2.40 nos./Rm)
Construction and launching of bamboo porcupine
made of 12 nos. 2.00 m long whole matured Barua
bamboo of size 7.5 cm. to 10 cm. making 0.50 × 0.50 ×
0.50 m size cube at the middle and fitting fixing cross
whole Barua bamboo 2 m long 8 nos. on 4 sides of the
cube as directed and nailing with patent nails of 30
6.30 cm long total 36 nos. each point and joint as directed Each ₹ 2,934.42
including bending sharp edge of the patent nails tying
each point and joint with 12 G. wire closely to the side
of the cube with Barua bamboo 15 cm apart placed
from the inside of the main members of all sides
including nailing with nails and bending the
protruding edge tying every joint with 12G wire
making holes in each internodes of bamboo with

[30]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


chisel, filling the cube with 4 nos. of earth filled
cement bags including local carriage to the site and
launching properly in river bed/slopes etc. including
cost of material and complete as directed.
(Using Barua Bamboo at the rate of 5.79 nos./Rm)
Supply and construction of bamboo cribs fabricated
out in pyramid shape out of matured Barua bamboo
75 mm to 100 mm dia. complete with all the branches
and foliages with apex point at 7.00 m from the
bottom. At 0.60 m above the base of 1st row of
horizontal stiffeners of size 4.00 m × 3.00 m are to be
provided along with to nos. of cross struts. A second
set of horizontal stiffeners along with cross stiffeners
similar to the 1st set are provided at height of 4.00 m
from the bottom. One set of cross bracing are to be
provided in each face in between the 1st and 2nd
horizontal stiffeners. All the stiffeners and inclined
6.31 Crib ₹ 6,557.66
members are to be projected 0.30 m beyond the
longitudinal members. All the points are to be pinned
with 22 Cm long patent nails and protruding end is to
be bent properly to have a firm grip and the apex
point is also to be clustered with 8 G. wire. All the
members are to be punched with chisel or auger. The
cribs are to be weighted with 25 nos. of earth filled
polythene empty cement bags in all corners and
middle of 1st and 2nd row of horizontal stiffeners of the
cribs, tied firmly with galvanised wire including cost
of material and complete as directed.
(Using Barua Bamboo at the rate of 14.00 nos./Rm )
Preparation of Dry mortar (at 1:6) filled jute bags for
pitching including filling in bags and stitching the
6.32 mouth with jute sutli, etc. complete as directed. Bag ₹ 351.99
(Jutebags will be supplied by the department free of
cost).
Preparation of Dry mortar (at 1:6) filled cement bags
for pitching including filling in bags and stitching the
6.33 mouth with jute sutli, etc., complete as directed. Bag ₹ 138.01
(Cement bags will be supplied by the department free
of cost).
Supplying and launching of bamboo bundles of
undresses Jati bamboo 75 to 100 cm dia. with
branches and green foliages containing 4 (Four) nos.
6.34 of bamboo in each bundle tied together with 2 (Two) Bundle ₹ 1,285.41
folds of 8 G wire at 3 (Three) places and loaded with 6
(Six) nos. of earth filled cement bags tied with 16 G
wire launching at site by tying 2 (Two) folds of 8 G
[31]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


wire anchored to bamboo pegs etc., completed as
directed.
Supplying fitting and fixing Muli bamboo chattai fitted
with split Muli bamboo kamies at 0.5 m C/C and edge
6.35
tied with 24 G. galvd. tying wire, etc. Complete as
directed.
Straight woven: (Using Muli Bamboo at the rate of
6.35.01 Sqm ₹ 177.15
34.5 nos./Rm)
Diagonally woven: (Using Muli Bamboo at the rate of
6.35.02 Sqm ₹ 188.82
39.00 nos./Rm)
Providing foot bridge of 1.00 m width with Bhaluka
Bamboo (7.5 cm to 10.0 cm) post of 2.00 nos. in a row
@ 2.4 m apart driven 1.2 m below ground and 1 m
above ground with 2 nos. long beam placed over two
lines of posts and a pair of half Bhaluka Bamboo collar
tied together with the posts including providing
bamboo kamies mat on the bridge way including
6.36 strengthening with half bamboo kamies tied together Rm ₹ 526.50
with long beams with 18 G galvanised wire etc.,
complete as directed for height up to 1.2 m to be used
for movement of labour/staff during execution of
work.
(Using Bhaluka Bamboo at the rate of 7.0 nos./Rm &
Jati Bamboo at the rate of 11.0 nos./Rm)
Providing foot bridge of 1.00 m width with Bhaluka
Bamboo post of 2.00 nos. in a row @ 2.4 m apart
driven 1.2 m below ground and 1m above ground
with 2 nos. long beam placed over two lines of posts
and a pair of half Bhaluka Bamboo collar tied together
with the posts including providing bamboo kamies
6.37 mat on the bridge way including strengthening with Rm ₹ 466.50
half bamboo kamies tied together with long beams
with 18 G galvanised wire etc. complete as directed
(For height up to 1.2 m to be used for movement of
general through fare).
(Using Bhaluka Bamboo at the rate of 7.00 nos./Rm &
Jati Bamboo at the rate of 12.00 nos./Rm)
Providing foot bridge of 1.00 m width with Bhaluka
Bamboo post of 2.00 nos. in a row @ 2.4 m apart
driven 1.2 m below ground and 1 m above ground
with 2 nos. long beam placed over two lines of posts
6.38 and a pair of half Bhaluka Bamboo collar tied together Rm ₹ 574.68
with the posts including providing bamboo kamies
mat on the bridge way including strengthening with
half bamboo kamies tied together with long beams
with 18 G galvanised wire etc. complete as directed
[32]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(For height 1.0 m to 2.0 m to be used for movement of
public through fare).
(Using Bhaluka Bamboo at the rate of 10.00 nos./Rm
& Jati Bamboo at the rate of 9.00 nos./Rm)
Providing foot bridge from bank to bank of 1.50 m
width in deep channel of depth 6 m from bank with
Bhaluka Bamboo post of 3.00 nos. in a row driven 1.30
m to 1.80 m below ground and 6 m above the row of
posts being not more than 3 m apart whole bamboo
collars placed on the top pf the posts and B/bamboo
longitudinal beam over Bhaluka bamboo cross beam
tied properly with 18 G galvd. wire C/C strengthening
the structure by providing/Bhaluka bamboo struts
6.39 Rm ₹ 907.86
and bracing at every alternate row of posts on both
U/S & D/S sides and providing Jati bamboo chattai
mat on the bridge way fixed with half bamboo kamies
properly tied with core sutli C/C supplying all
materials complete with all fittings as directed (For
height 2.0 m to 6 m to be used for crossing the channel
through fare).
(Using Bhaluka Bamboo at the rate of 12.00 nos./Rm
& Jati Bamboo at the rate of 9.00 nos./Rm)
Construction of temporary shed of two roof with mud
plinth of 0.45 m height above ground level with
Bhaluka bamboo post 1.5 m apart, driven at least 0.75
m below ground and height above plinth of 2.5 m.
Split Jatti bamboo/tarza wall 10 cm thick touch
roofing over bamboo rua frame, placing at 0.15 m
6.40 clear apart, fitted with bamboo kamies from binding Sqm ₹ 1,863.78
doors and windows with Bamboo Chattai,
strengthening with Bamboo frame binding with wire,
roofing with TATA Shaktee roofing sheets etc.,
complete as directed.
(Using Bhaluka Bamboo at the rate of 6.00 nos./Rm &
Jati Bamboo at the rate of 61.00 nos./Rm)
Supplying and launching of bamboo bundles of
undresses Bhuluka bamboo with branches and green
foliages containing 4 (Four) nos. of bamboo in each
bundle tied together with 2 (Two) folds of 8 G wire at
6.41 bundle ₹ 1,521.16
3 (Three) places and loaded with 6 (Six) nos. of earth
filled cement bags tied with 16G wire launching at site
by tying 2 (Two) folds of 8 G wire anchored to bamboo
pegs completed as directed.
Preparation of Moist mortar 1:6 filled cement bags for
6.42 pitching including filling in bags and stitching the Bag ₹ 162.36
mouth with jute sutli, etc. complete as directed.
[33]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(cement bags will be supplied by the department free
of cost).
Preparation of Moist mortar 1:8 filled cement bags for
pitching including filling in bags and stitching the
6.43 mouth with jute sutli, etc. complete as directed. Bag ₹ 146.79
(cement bags will be supplied by the department free
of cost).

[34]
Schedule of Rate 2022 - 23

CHAPTER - 7 :: PORCUPINE

Sl. no. Description Unit Basic rate


Supply of Pre stressed Cement Concrete (PSC)
Porcupine members of size 0.10 m × 0.10 m × 3.00 m
with M - 30 grade of cement concrete conforming to IS
1343:2012 using super-plasticizer @1.2 lit/bag of
cement with graded broken coarse aggregates up to 20
mm size down conforming to IS 10262:2009 & IS
456:2000 and reinforced with 4 nos. of 4 mm dia. high
tensile steel wire cable/strand with necessary cover
and 4 mm high tensile stirrups at 250 mm C/C, in Per
7.01 ₹ 838.69
conformity with IS-6403:R2002 and stressed to Member
required strength not exceeding 9.18 N/mm, holes of
16 mm dia. at 50 cm inside from both ends in the same
face and in either face of post another 2 nos. of holes of
size 16 mm dia. at 65 mm inside from both ends
including properly curing for 21 (Twenty one) days and
carriage of porcupine members from factory to the
stack yard within a distance up to 50 Km including
loading, unloading & stacking complete as directed.
Carriage of PSC porcupine members of size 0.10 m × Per
7.02 0.10 m × 3.00 m from Stack yard to Work Site including Member ₹ 2.04
loading, unloading & stacking Per Km
Labour charge for launching of PSC Porcupine
including carriage of PSC porcupine members of size
0.10 m × 0.10 m × 3.00 m from the stack yard to the
place of launching, erection of the Porcupine with 6
7.03
(Six) members properly, supply & fitting/fixing with
12 mm dia. 25 Cm long M.S. Nuts and bolts and
launching the porcupine properly as directed. (Lead up
to 150 m)
7.03.1 Launching without boat Porcupine ₹ 533.17
7.03.2 Launching with boat Porcupine ₹ 952.85
Supply of Pre stressed Cement Concrete (PSC)
Porcupine members of size 0.10 m × 0.10 m × 2.00 m
with M - 30 grade of cement concrete conforming to IS
1343:2012 using super-plasticizer @1.2 lit/bag of
cement with graded broken coarse aggregates up to 20
mm size down conforming to IS 10262:2009 & IS Per
7.04 456:2000 and reinforced with 4 nos. of 4 mm dia. high ₹ 672.64
Member
tensile steel wire cable/strand with necessary cover
and 4 mm high tensile stirrups at 250 mm C/C, in
conformity with IS-6403:R2002 and stressed to
required strength not exceeding 9.18 N/mm, holes of
16 mm dia. at 50 cm inside from both ends in the same
face and in either face of post another 2 nos. of holes of
[35]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


size 16 mm dia. at 65 mm inside from both ends
including properly curing for 21 (Twenty one) days and
carriage of porcupine members from factory to the
stack yard within a distance up to 50 Km including
loading, unloading & stacking complete as directed.

Carriage of PSC porcupine members of size 0.10 m × Per


7.05 0.10 m × 2.00 m from Stack yard to Work Site including Member ₹ 1.26
loading, unloading & stacking (Considering 20 Km) Per km

Labour charge for launching of PSC Porcupine


including carriage of PSC porcupine members of size
0.10 m × 0.10 m × 2.00 m from the stack yard to the
place of launching, erection of the Porcupine with 6
7.06
(Six) members properly, supply & fitting/fixing with
12 mm dia. 25 Cm long M.S. Nuts and bolts and
launching the porcupine properly as directed. (Lead up
to 150 m)
7.06.1 Launching without boat Porcupine ₹ 542.98

7.06.2 Launching with boat Porcupine ₹ 739.07

Providing and laying of PCC slab of size 0.3 m × 0.3 m


× 0.15 m, made in proportion 1:2:4 on trimmed graded
slope of river bank including ramming the seat, curing,
7.07 Cum ₹ 7658.93
carriage of the slab from the place of casting up to a
distance of 200 m to the work site and all handling
charges, etc. and complete as directed.

Providing and laying of PCC block of size 0.3 m × 0.3 m


× 0.3 m, made in proportion 1:2:4 on trimmed graded
slope of river bank including ramming the seat, curing,
7.08 Cum ₹ 8095.77
carriage of the block from the place of casting up to a
distance of 200 m to the work site and all handling
charges, etc. and complete as directed.

[36]
Schedule of Rate 2022 - 23

CHAPTER - 8 :: GEOSYNTHETIC WORKS

Sl. no. Description Unit Basic rate


Filling and laying of Geo bags of size 1.03 m × 0.70 m
excluding excavation of sand/silt from flood plain or
adjacent chars within a distance of 90 m of the work
site, filling geo bags with sand/silt having minimum
weighing 126.00 Kg and minimum volume 0.084 Cum
after filling , double locking chain stitching the mouth
of the filled bags with polypropylene thread by power
8.01A driven double needle double stitched machine,
stacking the same in batches of 100, carrying the same
to the dumping site including all handling charges and
local carriage within a distance of 150 m and laying
properly as directed.
(Sand/silt, Geo Bag and Polypropylene thread will be
supplied by the department free of cost)
8.01A.1 Without Boat Per Bag ₹ 35.83
8.01A.2 With Engine Boat Per Bag ₹ 56.74
8.01A.3 With Mar Boat Per Bag ₹ 48.81
Filling and laying of Geo bags of size 1.03 m × 0.70 m
including excavation of sand/silt of size more than 80
micron from flood plain or adjacent chars within a
distance of 90 m of the work site, filling geo bags with
sand/silt having minimum weighing 126.00 Kg and
minimum volume 0.084 Cum after filling, double
locking chain stitching the mouth of the filled bags with
8.01B polypropylene thread by power driven double needle
double stitched machine, stacking the same in batches
of 100, carrying the same to the dumping site including
all handling charges and local carriage within a
distance of 150 m and laying properly as directed.
(Geo Bag and Polypropylene thread will be supplied by
the department free of cost)
8.01B.1 Without Boat Per Bag ₹ 45.96
8.01B.2 With Engine Boat Per Bag ₹ 66.87
8.01B.3 With Mar Boat Per Bag ₹ 58.94
Filling and laying in cage with sand/silt filled Geo bags
of size 1.03 m × 0.70 m excluding excavation of
specified sand/silt from flood plain or adjacent chars
within a distance of 90 m of the work site, filling geo
8.02A bags with sand having minimum weighing 126.00 Kg
and minimum volume 0.084 Cum after filling, double
locking chain stitching the mouth of the filled bags with
polypropylene thread by power driven double needle
machine, stacking the same in batches of 100, carrying
[37]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


the same to the dumping site including all handling
charges and local carriage within a distance of 150 m
and laying properly. in cages made of wire netting
sheets of size 2.57 × 1.66 m of 8 G galvanized wire
making the cage from 2 nos. of wire netting sheet by
tying the projected wires complete as directed.
(Geo Bag, Wire Netting Sheets and Polypropylene
thread will be supplied by the department free of cost)
8.02A.1 Without Boat Per Bag ₹ 40.84
8.02A.2 With Engine Boat Per Bag ₹ 58.10
8.02A.3 With Mar Boat Per Bag ₹ 53.82
Filling and laying in cage with sand/silt filled Geo bags
of size 1.03 m × 0.70 m including excavation of
sand/silt from flood plain or adjacent chars within a
distance of 90 m of the work site, filling geo bags with
sand/silt having minimum weighing 126.00 Kg and
minimum volume 0.084 Cum after filling, double
locking chain stitching the mouth of the filled bags with
polypropylene thread by power driven double needle
8.02B machine, stacking the same in batches of 100, carrying
the same to the dumping site including all handling
charges and local carriage within a distance of 150 m
and laying properly. in cages made of wire netting
sheets of size 2.57 × 1.66 m of 8 G galvanized wire
making the cage from 2 nos. of wire netting sheet by
tying the projected wires complete as directed.
(Geo Bag, Wire Netting Sheets and Polypropylene
thread will be supplied by the department free of cost)
8.02B.1 Without Boat Per Bag ₹ 44.36
8.02B.2 With Engine Boat Per Bag ₹ 61.62
8.02B.3 With Mar Boat Per Bag ₹ 57.34
Labour charge for laying, fitting and fixing of double
layered Geo textile, fabricated to form a three
dimensional mattresses after filling sand at design
slope, filled up with sand by pump, anchoring by
cutting/ at already excavated trench at the upper and
lower end of slope of depth 1.00 m × 0.75 m placing the
8.03 mat by bending it into the trench, filling the trench by Per Sqm. ₹ 99.86
earth filled cement bags/ sand / silt filled type - A geo-
bags, sides of mattresses in sloping direction stitched
by Polypropylene thread with double locking chain
stitch not less than 3 stitches per 2.50 cm to achieve
minimum stream strength including all handling and
carriage charge complete as directed.

[38]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(Polypropylene thread will be supplied by the
department free of cost)
Filling and laying of nonwoven Geo - textile bag of
dimension 2.00 m × 1.50 m excluding excavation of
specified sand/silt from flood plain or adjacent chars
within a distance of 90 m of the work site, filling geo
bags with sand having minimum volume 0.612 Cum
after filling, double locking chain stitching the mouth
8.04A of the filled bags with polypropylene thread by power
driven double needle machine, laying at proper site
including all handling charges and local carriage
within a distance of 100 m complete as directed.
(Sand/silt, Geo Bag and Polypropylene thread will be
supplied by the department free of cost)
8.04A.1 Without Boat Per Bag ₹ 377.00
8.04A.2 With Engine Boat Per Bag ₹ 515.11
8.04A.3 With Mar Boat Per Bag ₹ 493.85
Filling and laying of nonwoven Geo - textile bag of
dimension 2.00 m × 1.50 m including excavation of
sand/silt from flood plain or adjacent chars within a
distance of 90 m of the work site, filling geo bags with
sand/silt, having minimum volume 0.612 Cum after
filling, double locking chain stitching the mouth of the
8.04B filled bags with polypropylene thread by power driven
double needle machine, laying at proper site including
all handling charges and local carriage within a
distance of 100 m complete as directed.
(Geo Bag and Polypropylene thread will be supplied by
the department free of cost)
8.04B.1 Without Boat Per Bag ₹ 491.78
8.04B.2 With Engine Boat Per Bag ₹ 629.89
8.04B.3 With Mar Boat Per Bag ₹ 574.87
Filling and laying of polypropylene gabion boxes 2.0 m
× 2.0 m × 0.45 m filled with sand filled Geo bags of size
1.03 m × 0.70 m excluding excavation of sand/silt from
flood plain or adjacent chars within a distance of 90 m
of the work site, filling geo bags with sand weighing
126.00 Kg after filling, double locking chain stitching
8.05A:
the mouth of the filled bags with polypropylene thread
by power driven double needle machine, stacking the
same in batches of 100 or part as directed carrying the
same to the dumping site including all handling
charges and local carriage within a distance of 150 m
and laying properly.

[39]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(Geo Bag, gabion box and Polypropylene thread will be
supplied by the department free of cost)
8.05A.1 Without Boat Per Bag ₹ 46.80
8.05A.2 With Engine Boat Per Bag ₹ 57.16
8.05A.3 With Mar Boat Per Bag ₹ 63.13
Filling and laying of polypropylene gabion boxes of
size 2.0 m × 2.0 m × 0.45 m filled with sand/silt filled
Geo bags of size 1.03 m × 0.70 m including excavation
of sand/silt from flood plain or adjacent chars within a
distance of 90 m of the work site, filling geo bags with
sand weighing 126.00 Kg after filling ,double locking
chain stitching the mouth of the filled bags with
8.06 polypropylene thread by power driven double needle
machine, stacking the same in batches of 100 or part as
directed carrying the same to the dumping site
including all handling charges and local carriage
within a distance of 150 m and laying properly.
(Geo Bag, gabion box and Polypropylene thread will be
supplied by the department free of cost)
8.06.1 Without Boat Per Bag ₹ 49.87
8.06.2 With Engine Boat Per Bag ₹ 60.23
8.06.3 With Mar Boat Per Bag ₹ 65.70
Labour charge for laying Geo fabric sheet as filter
8.07 bellow pitching including carrying, lapping, wrapping Per Sqm ₹ 9.58
& stitching as directed by the Engineer-in-Charge.
Filling and laying of Geo bags type-C of size 1.5m X
1.0m excluding excavation of sand/silt from flood
plain or adjacent chars within a distance of 90m of the
work site, filling geo bags with sand/silt having
minimum weighing 330 Kg and minimum volume
0.221 cum after filling , double locking chain stitching
the mouth of the filled bags with polypropylene thread
8.08
by power driven double needle double stitched
machine, stacking the same in batches of 100, carrying
the same to the dumping site including all handling
charges and local carriage within a distance of 150m
and laying properly as directed. (sand/silt, Geo Bag
and Polypropylene thread will be supplied by the
department free of cost)
8.08.1 Without Mar Boat Bag ₹ 72.96

8.08.2 With Mar Boat Bag ₹ 92.43

8.08.3 With Engine Boat Bag ₹ 123.14

[40]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


Filling and laying of Geo bags type-C of size 1.5m X
1.0m including excavation of sand/silt from flood plain
or adjacent chars within a distance of 90m of the work
site, filling geo bags with sand/silt having minimum
weighing 330 Kg and minimum volume 0.221 cum
after filling , double locking chain stitching the mouth
of the filled bags with polypropylene thread by power
8.09
driven double needle double stitched machine,
stacking the same in batches of 100, carrying the same
to the dumping site including all handling charges and
local carriage within a distance of 150m and laying
properly as directed. (sand/silt, Geo Bag and
Polypropylene thread will be supplied by the
department free of cost)
8.09.1 Without Mar Boat Bag ₹ 99.97

8.09.2 With Mar Boat Bag ₹ 119.44

8.09.3 With Engine Boat Bag ₹ 150.15

[41]
Schedule of Rate 2022 - 23

[42]
Schedule of Rate 2022 - 23

CHAPTER - 9 :: READY MADE EMBANKMENT (RME)

Sl. no. Description Unit Basic rate


Supply of 30 m long RME structure of vertical height
1.83 m (6 feet) and bottom width 2.4 m (8 feet),
(having 35 chambers interconnected to make one
chain – 30 m long), interconnected baffle walls and
peripheral surface of HSP, forming one section with all
accessories necessary for connection of chains and
anchors complete as per direction of engineer-in-
charge. With the following specifications RME shall be
made up of HS tape (laminated with min 30µ thick
film) with
i. Ultimate tensile strength of 27 kN/m in CD/MD as
per ASTM D 4595;
ii. Wide width elongation of 12/9%;
iii. Trapezoidal tear of 445 N (ASTM D 533);
iv. MULLEN BURST OF 2,930 KPa (ASTM D 3786);
v. Permittivity of 0.05 S-1 (ASTM D 4491);
vi. *UV of min 70% @500 hrs (ASTM 4355);
All above values as Max ARV except* which is TYP of
9.01 the agreed primary sample lot, and all are established Chain ₹ 1,30,593.42
as per sampling procedures defined in ASTM D 4354
for all 5 levels of testing forming the fundamental part
of RME's QAP.
All chambers of RME shall have 3 × 3' top opening for
filling, be 6' vertically deep in the back tapering off into
a 1:1 slope in front that ends in 1' vertical drop to the
bottom base which shall measure 8' from the rear
point. 35 such chambers/cells shall form one chain
with proper water-proof joining arrangements at its
both ends that shall end in flaps to over the first cell of
the connected adjacent chain. Stitching shall be along
the cellular periphery only with not less than 300
denier PET thread while ensuring the bends are curves
and not rectangles, extending into subsequent stitch-
lines up to a distance sufficient enough to ensure
homogeneous bond joint strength. Stitching shall be as
per ASTM D 4885. All RME shall be provided with due
connection joints.
Labour charges for carrying, transporting, levelling,
Placing & Filling of RME with excavator including
9.02 holding stands etc. complete & as per direction of Chain ₹ 15,082.90
Engineer-In Charge.
(The rate excludes cost of filling materials)
Supply of Bi-axial extruded high modulus
9.03 polypropylene geogrid/Techgrid (20 × 20) confirming Sqm ₹ 88.40
to MORTH SPECIFICATION for base reinforcement in
[43]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


apron having minimum tensile strength 20 kN/m in
the longitudinal & transverse direction with 7.5 kN/m
& 15 kN/m tensile strength at 2% & 5% strain
respectively in the longitudinal & transverse direction,
Junction efficiency not less than 95% with 38 mm × 38
mm mesh opening.
Labour Charges for carrying, transporting & laying of
9.04 20 × 20 Geogrid/Techgrid including wrapping Sqm ₹ 7.23
stitching as per Instruction of Engineering-In-charge.
Supply of HDPE Geocell (Techcell type, CE marked),
200 mm deep, TC330 with USWD-C/C 356, having
density greater than 0.935 g/cm3 with multitude
rhomboidal indentations, textured & perforated with
horizontal rows of maximum 10 mm dia. holes.
9.05 Perforations within each row shall be 19 mm on Sqm ₹ 478.17
centre. The quantity of perforations shall remove +/-
17% of cell wall area having 200 mm cell depth with
minimum sheet thickness of 1.20 mm & having yield
strength of 18 kN/m to complete the job as per
drawing & direction of Engineer-In-Charge.
Labour Charges for carrying, transporting, laying,
fixing & filling of HDPE Geocell 200 mm thick including
9.06 Sqm ₹ 37.77
accessories and equipment as per Instruction of
Engineering-In-charge.

[44]
Schedule of Rate 2022 - 23

CHAPTER - 10 :: SUPPLY OF GEOSYNTHETIC MATERIALS AS PER


QUOTED RATE.

Sl. no. Description Unit Basic rate

Supply of Geo-textile bags of type-A (1.03 × 0.70 m)


inner to inner made of Geo-textile non-woven fabric
sheets of 400 GSM manufactured from 100% virgin
Polypropylene (PP) fibre with minimum properties as
per IS 16653:2017
i. Wide Tensile strength (MD) ≥ 20KN/m & Wide
Tensile strength(CD) ≥20 KN/m
ii. Elongation (MD) ≥50% & Elongation (CD) ≥ 50%
iii. Abrasion ≥ 95%
iv. Trapezoidal Tear Strength (MD) ≥ 450N &
Trapezoidal Tear Strength (CD) ≥ 450N
v. CBR Puncture strength ≥ 4000N
vi. Permittivity ≥ 1.10s – 1
vii. Permeability ≥ 40l/m2/sec
viii. AOS ≤ 75 micron
ix. UV Resistance @ 500 hours retained Tensile
10.1 strength (MD) & (CD) ≥ 80% Each ₹ 159.73
x. Mass ≥ 400 gm/m²
xi. Thickness at 2KPa ≥ 3 mm
xii. Seam strength ≥ 80 % of actual fabric strength.
Stitching of Bags should be Ring Spun Yarn stitches
with 2500-3000 denier double line chain stitch with
overlap with stitches along the edge @ minimum 15
stitches per 100 mm.
(Bags are to be supplied of 100 numbers in a bundle,
properly packed with each bag having proper tag with
name of Manufacturer, Batch Number, the GSM and
type of polymer encrypted and stitched on top corner
and each bag is to be marked with “WRD Govt. of
ASSAM” to be printed distinctly. Test Certificate from
approved NABL accredited and ISO (Certified
Laboratory should invariably be submitted against
each batch of material)

Supply of Geo-textile bags of type-A (1.03 × 0.70 m)


inner to inner made of Geo-textile non-woven fabric
sheets of 300 GSM manufactured from 100% virgin
Polypropylene (PP) fibre with minimum properties as
10.2 per IS 16653:2017 Each ₹ 130.19
i. Wide Tensile strength (MD) ≥ 15KN/m & Wide
Tensile strength (CD) ≥ 15KN/m
ii. Elongation (MD) ≥ 50% & Elongation (CD) ≥ 50%
iii. Abrasion ≥ 95%

[45]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


iv. Trapezoidal Tear Strength (MD) ≥ 340N &
Trapezoidal Tear Strength (CD) ≥ 340N
v. CBR Puncture strength ≥ 3000N
vi. Permittivity ≥ 1.25s – 1
vii. Permeability ≥ 60l/m2/sec
viii. AOS ≤ 75 micron
ix. UV Resistance @ 500 hours retained Tensile
strength (MD) & (CD) ≥ 80%
x. Mass ≥ 300 gm/m²
xi. Thickness at 2 KPa ≥ 3 mm
xii. Seam strength ≥ 80 % of actual fabric strength.
Stitching of Bags should be Ring Spun Yarn stitches
with 2500-3000 denier double line chain stitch with
overlap with stitches along the edge @ minimum 15
stitches per 100 mm.
(Bags are to be supplied of 100 numbers in a bundle,
properly packed with each bag having proper tag with
name of Manufacturer, Batch Number, the GSM and
type of polymer encrypted and stitched on top corner
and each bag is to be marked with “WRD Govt. of
ASSAM” to be printed distinctly. Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material).

Supply of Geo Bags Type-B (Size 2.00 m × 1.50 m inner


to inner) (Pillow Type) made of composite layers of
Polypropylene (PP) fibre as per IS 16653:2017 for
Nonwoven and IS 16654:2017 for Woven:
Woven Geo-textile for the outer cover (300gsm): The
woven geo textile is woven with multifilament woven
fabric manufactured from ultra violet stabilized
polypropylene. Geo-textile used to manufacture geo-
textile bags should have high mechanical properties
for enhanced durability along with enhanced
10.3 puncture, abrasion and U.V. resistance characteristics. Each ₹ 1,004.56
Geo-textile should be inert to biological degradation
and resistant to naturally encountered chemicals,
alkalis, and acids.
Properties
i. Tensile strength (MD) ≥ 80 KN/m & Tensile
strength (CD) ≥ 70 KN/m
ii. Elongation (MD) ≤ 25% & Elongation (CD) ≤ 25%
iii. Abrasion ≥ 75%
iv. Trapezoidal Tear Strength (MD) ≥ 1500N &
Trapezoidal Tear Strength (CD) ≥ 1300N

[46]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


v.CBR Puncture strength ≥ 900N
vi.Permeability ≥ 18 l/m2/sec
vii.AOS ≤ 250 micron
viii.UV Resistance @ 500 hours retained Tensile
strength (MD) & (CD) ≥ 80%
ix. Mass ≥ 300 gm/m²
x. Seam strength ≥ 50 % of actual fabric strength.

Non-Woven Geo-textile for the inner layer


(300gsm): It is needle punched non-woven geo-textile
made of 100% polypropylene staple fibres which are
formed into a random network for dimensional
stability. It should resist UV degradation, rotting and
alkalis.
Properties
i. Wide Tensile strength (MD) ≥ 15 KN/m & Wide
Tensile strength (CD) ≥ 15 KN/m
ii. Elongation (MD) ≥ 50% & Elongation (CD) ≥ 50%
iii. Abrasion ≥ 95%
iv. Trapezoidal Tear Strength (MD) ≥ 340 N &
Trapezoidal Tear Strength (CD) ≥ 340 N
v. CBR Puncture strength ≥ 3000 N
vi. Permittivity ≥ 1.25 s-1
vii. Permeability ≥ 60 l/m2/sec
viii. AOS ≤ 75 micron
ix. UV Resistance @ 500 hours retained Tensile
strength (MD) & (CD) ≥ 80%
x. Mass ≥ 300 gm/m²
xi. Thickness at 2KPa ≥ 3 mm
xii. Seam strength ≥ 80 % of actual fabric strength.
Stitching of Bags should be Ring Spun Yarn stitches
with 2500-3000 denier double line chain stitch with
overlap with stitches along the edge.
(Bags are to be supplied of 15 numbers in a bundle,
properly packed with each bag having proper tag with
name of Manufacturer, Batch Number, the GSM and
type of polymer encrypted and stitched on top corner
and each bag is to be marked with “WRD Govt. of
ASSAM” to be printed distinctly. Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material)

Supply of Geo-textile Bags, Pillow Type of Size 1.20 m


10.4 × 1.00 m, inner dimension made of composite layers of Each ₹ 405.04
geo-textile as per specifications below:

[47]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


Woven Geo-textile for the outer cover. The woven geo
textile is woven with UV resistant slit film tape fibre
with MAVR values of the following properties. Geo-
textile used to manufacture geo-textile bags should
have high mechanical properties for enhanced
durability along with enhanced puncture, abrasion and
U.V. resistance characteristics. Geo-textile should be
inert to biological degradation and resistant to
naturally encountered chemicals, alkalis, and acids.
 Weight (ISO-9864/ASTMD 5261) ≥ 250 Gms/Sqm.
 Tensile strength (MD) (ASTMD 4595) ≥35 kN/m.
 Tensile strength (CD) (ASTMD 4595) ≥ 35 kN/m.
 Tensile Elongation (ASTMD 4595) ≥ 5% & ≤ 30%.
 Grab Elongation (ASTMD 4632) ≥ 5% & ≤ 30%.
 Tensile strength (ASTMD 4632) = 1.5 kN.
 UV resistance (ASTMD 4355) = 70%/500 hrs.
Non-woven Geo-textile for the inner layer. It is needle
punched non-woven geo-textile made of 100%
polypropylene staple fibers which are formed into a
random network for dimensional stability. It should
resist UV degradation, rotting and alkalis.
 Weight (ISO-9864/ASTMD 5261) ≥ 300 Gms/Sqm.
 Tensile strength (MD) (ASTMD 4595) ≥ 12 kN/m
 Tensile strength (CD) (ASTMD 4595) ≥ 12 kN/m
 Tensile Elongation (ASTMD 4595) ≥ 5% & ≤ 30%
 Grab Elongation (ASTMD 4632) ≥ 5% & ≤ 30%
 Tensile strength (ASTMD 4632) = 1.5 KN
 UV resistance (ASTMD 4355) = 70%/500 hrs
(Bags are to be supplied of 100 numbers or part in a
bundle, properly packed with name of Manufacturer
and Batch Number is to be marked on each bag with
“WRD Govt of ASSAM” to be printed on each bag and
mentioning properly the GSM and type of Geo bag
polymer. Test Certificate from approved NABL
accredited and ISO Certified Laboratory should
invariably be submitted against each batch of
material)

Supply of non-woven Geo-textile fabric sheets of 300


GSM manufactured from 100% virgin Polypropylene
(PP) fibre with minimum properties as per IS 16653:
2017
10.5 Sqm ₹ 80.37
 Wide Tensile strength (MD) ≥ 15kN/m & Wide
Tensile strength (CD) ≥ 15kN/m
 Elongation (MD) ≥ 50% & Elongation (CD) ≥ 50%
 Abrasion ≥ 95%
[48]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


 Trapezoidal Tear Strength (MD) ≥ 340 N &
Trapezoidal Tear Strength (CD) ≥ 340 N
 CBR Puncture strength ≥ 3000 N
 Permittivity ≥ 1.25 s-1
 Permeability ≥ 60l/m2/sec
 AOS ≤ 75micron
 UV Resistance @ 500 hours retained Tensile
strength (MD) & (CD) ≥ 80%
 Mass ≥ 300gm/m²
 Thickness at 2KPa ≥ 3 mm.
(Each Roll of Geo Fabric Sheet should be supplied in
properly packed Bundles and should be marked with
the Name of Manufacturer, Batch Number & its
dimensions clearly on each roll with “WRD Govt. of
ASSAM” to be printed on it and mentioning properly
the GSM and type of polymer and Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material).

Supply of G-Mat in double layered composite Geo-


textile fabricated to form a three dimensional
mattresses, the upper layer of the mattress being
heavily woven with polypropylene fabric needle-
punched with a mixture of U.V. stabilized green fibres
and cut tape yarns with
Upper Layer Properties as
i. Mass per unit area > 650 GSM,
ii. Tensile Strength (MD) ≥ 70kN/m,
iii. Tensile Strength (CD) ≥ 70kN/m
iv. Tensile Elongation (MD) ≤ 25%,
v. Tensile Elongation (CD) ≤ 25%, 6) Pore Size <
10.6 0.35 mm, Sqm ₹ 1,245.66
vi. Abrasion Resistance ≥ 35 %,
vii. UV @ 500 hours ≥ 90%
viii. Resistance to Oxidation @ 100°C for 28 days) ≥
80%
and Lower Layer Properties as
i. Mass per unit area > 400 GSM,
ii. Tensile Strength (MD) ≥ 110kN/m,
iii. Tensile Strength (CD) ≥ 90kN/m
iv. Tensile Elongation (MD) ≤ 25%,
v. Tensile Elongation (CD) ≤ 25%,
vi. Pore Size < 0.35mm,
vii. Abrasion Resistance ≥ 60 %,
viii. UV @ 500 hours ≥ 90%
[49]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


ix. Resistance to Oxidation @ 100°C for 28 days) ≥
80%
The sewing thread should be of high tenacity polyester
and parallel stitches are to be continued positioned at
350 mm apart with a stitch length not exceeding 5 mm.
(Each roll of G-Mat should be supplied in properly
packed bundle and should be marked with the Name of
Manufacturer & Batch Number & its dimensions
clearly on each roll with “WRD Govt. of ASSAM” to be
printed on it and mentioning properly the GSM (for
both upper and lower layer) and types of polymer (for
both upper and lower layer) and Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material)
(Inclusive of Custom Duty)

Supply of G-Mat in double layered composite Geo-


textile fabricated to form a three dimensional
mattresses, the upper layer of the mattress being
heavily woven with polypropylene fabric needle-
punched with a mixture of U.V. stabilized green fibres
and cut tape yarns with
Upper Layer Properties as
i. Mass per unit area > 650 GSM,
ii. Tensile Strength (MD) ≥ 70kN/m,
iii. Tensile Strength (CD) ≥ 70kN/m
iv. Tensile Elongation (MD) ≤ 25%,
v. Tensile Elongation (CD) ≤ 25%,
vi. Pore Size < 0.35 mm
vii. Abrasion Resistance ≥ 35 %,
10.7 Sqm ₹ 964.38
viii. UV @ 500 hours ≥ 90%
ix. Resistance to Oxidation @ 100°C for 28 days) ≥
80%
and Lower Layer Properties as
i. Mass per unit area > 400 GSM,
ii. Tensile Strength (MD) ≥ 110kN/m,
iii. Tensile Strength (CD) ≥ 90kN/m
iv. Tensile Elongation (MD) ≤ 25%,
v. Tensile Elongation (CD) ≤ 25%,
vi. Pore Size < 0.35mm,
vii. Abrasion Resistance ≥ 60 %,
viii. UV @ 500 hours ≥ 90%
ix. Resistance to Oxidation @ 100°C for 28 days) ≥
80%

[50]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


The sewing thread should be of high tenacity polyester
and parallel stitches are to be continued positioned at
350 mm apart with a stitch length not exceeding 5 mm.
(Each roll of G-Mat should be supplied in properly
packed bundle and should be marked with the Name of
Manufacturer & Batch Number & its dimensions
clearly on each roll with “WRD Govt. of ASSAM” to be
printed on it and mentioning properly the GSM (for
both upper and lower layer) and types of polymer (for
both upper and lower layer) and Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material)
(Without Custom Duty)

Supply of geo-textile Tube (Mega containers) of fill


height of 2.5 m and 25 m length made of geo-textile
with minimum properties as mentioned below.
i. Tensile strength of geo-textile materials >
200kN/m in both directions for woven geo-
textiles
ii. O95 (pore size) of the geo-textile materials < 180
microns.
iii. Seam strength > 70% of the material tensile
10.8 strength. Each ₹ 1,11,132.67
iv. Elongation of the material at the ultimate tensile
strength should not be more than 20%
v. CBR Burst Strength > 10.5
vi. Abrasion resistance (BAW Rotating Drum) >75%
of strength retained.
vii. UV Resistance (ASTMD4355-500Hrs) > 80% of
strength retained.
viii. The geo-textile mega containers must resist the
pressure created by stacking the tubes in 3:2:1
manner.

Supply of woven Geo-Textile Tube (Mega containers)


of filled height 0.9 m made of Geo-textile with
minimum properties as mentioned below
 Tensile strength of geo-textile materials >
65kN/m in both directions
10.9  O95 (Pore size) of the geo-textile materials < 180 Each ₹ 14,127.59
microns,
 Seam strength > 70% of the materials tensile
strength,
 Elongation of the material at the ultimate tensile
strength should not be 65% for
[51]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


 CBR Burst strength > 10.5,
 Abrasion resistance (BAW Rotating Drum) > 75%
of strength retained,
 UV Resistance (ASTMD 4355-500 Hrs) > 80% of
strength retained.
(Including all taxes) 10 m Length

Supply of geo-textile Tube (Mega containers) with


minimum properties as mentioned below
 Polymer = PP
 Tube Circumference = 4.3 / 8.6 / 12.9 / 14.2 / 16
/ 17.2 / 21.6 + 5% (m)
 Fill Port (diameter) = 30 to 45 cm
10.10 Each
 Tensile Strength (MD) ≥ 175 kN/m
 Tensile Strength (CD) ≥ 175 kN/m
 Elongation – MD ≤ 25%
 AOS ≤ 0.180 mm
 Permittivity ≥ 0.40 S-1
Length = 10 / 15 / 20 / 25 / 30 m

Tube Circumference = 4.3 (m)


10.10.1
a. Length = 10 m Each ₹ 23,756.94

b. Length = 15 m Each ₹ 35,047.19

c. Length = 20 m Each ₹ 46,338.90

d. Length = 25 m Each ₹ 60,518.35

e. Length = 30 m Each ₹ 74,710.85

Tube Circumference = 8.6 (m)


a. Length = 10 m Each ₹ 44,070.35

b. Length = 15 m Each ₹ 63,811.19


10.10.2
c. Length = 20 m Each ₹ 83,434.98

d. Length = 25 m Each ₹ 1,06,015.48

e. Length = 30 m Each ₹ 1,28,595.99

Tube Circumference = 12.9 (m)


a. Length = 10 m Each ₹ 65,387.50
10.10.3
b. Length = 15 m Each ₹ 92,986.66

c. Length = 20 m Each ₹ 1,20,577.71

[52]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate

d. Length = 25 m Each ₹ 1,51,073.57

e. Length = 30 m Each ₹ 1,81,563.16

Tube Circumference = 14.2 (m)


a. Length = 10 m Each ₹ 73,628.30

b. Length = 15 m Each ₹ 1,04,100.74


10.10.4
c. Length = 20 m Each ₹ 1,34,576.65

d. Length = 25 m Each ₹ 1,67,800.44

e. Length = 30 m Each ₹ 2,01,317.91

Tube Circumference = 16.0 (m)


a. Length = 10 m Each ₹ 84,348.30

b. Length = 15 m Each ₹ 1,18,418.41


10.10.5
c. Length = 20 m Each ₹ 1,52,488.52

d. Length = 25 m Each ₹ 1,89,456.25

e. Length = 30 m Each ₹ 2,26,423.97

Supply of geo-textile Tube (Mega containers) with


minimum properties as mentioned below
 Polymer = PP
 Tube Circumference = 4.3 / 8.6 / 12.9 / 14.2 / 16
/ 17.2 / 21.6 + 5% (m)
10.11  Fill Port (diameter) = 30 to 45 CM
 Tensile Strength (MD) ≥ 100 kN/m
 Tensile Strength (CD) ≥ 100 kN/m
 Elongation – MD ≤ 25%
 AOS ≤ 0.180 mm
 Permittivity ≥ 0.40 S-1
 Length = 10 / 15 / 20 / 25 / 30 m

Tube Circumference = 4.3 (m)


a. Length = 10 m Each ₹ 20,091.29

b. Length = 15 m Each ₹ 28,127.81


10.11.1
c. Length = 20 m Each ₹ 36,164.33

d. Length = 25 m Each ₹ 44,200.85

e. Length = 30 m Each ₹ 52,237.37

[53]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate

Tube Circumference = 8.6 (m)


a. Length = 10 m Each ₹ 35,360.68

b. Length = 15 m Each ₹ 48,219.11


10.11.2
c. Length = 20 m Each ₹ 62,684.84

d. Length = 25 m Each ₹ 77,954.22

e. Length = 30 m Each ₹ 90,009.00

Tube Circumference = 12.9 (m)


a. Length = 10 m Each ₹ 47,415.46

b. Length = 15 m Each ₹ 68,310.40


10.11.3
c. Length = 20 m Each ₹ 88,401.70

d. Length = 25 m Each ₹ 1,12,511.25

e. Length = 30 m Each ₹ 1,32,602.55

Tube Circumference = 14.2 (m)


a. Length = 10 m Each ₹ 52,237.37

b. Length = 15 m Each ₹ 76,346.92


10.11.4
c. Length = 20 m Each ₹ 1,00,456.47

d. Length = 25 m Each ₹ 1,24,566.03

e. Length = 30 m Each ₹ 1,44,657.32

Tube Circumference = 16.0 (m)


a. Length = 10 m Each ₹ 59,470.23

b. Length = 15 m Each ₹ 84,383.44


10.11.5
c. Length = 20 m Each ₹ 1,08,492.99

d. Length = 25 m Each ₹ 1,36,620.80

e. Length = 30 m Each ₹ 1,64,748.62

Supply of geo-textile Tube (Mega containers) with


minimum properties as mentioned below
 Polymer = Polyester
10.12  Tube Circumference = 4.3 / 8.6 / 12.9 / 14.2 / 16
/ 17.2 / 21.6 + 5% (m)
 Fill Port (diameter) = 30 to 45 CM
 Tensile Strength (MD) ≥ 175 kN/m

[54]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


 Tensile Strength (CD) ≥ 175 kN/m
 Elongation – MD ≤ 15%
 AOS ≤ 0 .25 mm
 Permeability ≥ 3 × 10-3 m/s
 Length = 10 / 15 / 20 / 25 / 30 m

Tube Circumference = 4.3 (m)


a. Length = 10 m Each ₹ 24,031.63

b. Length = 15 m Each ₹ 35,445.90


10.12.1
c. Length = 20 m Each ₹ 43,992.69

d. Length = 25 m Each ₹ 61,151.18

e. Length = 30 m Each ₹ 75,476.98

Tube Circumference = 8.6 (m)


a. Length = 10 m Each ₹ 44,492.24

b. Length = 15 m Each ₹ 64,413.90


10.12.2
c. Length = 20 m Each ₹ 84,334.39

d. Length = 25 m Each ₹ 1,07,151.34

e. Length = 30 m Each ₹ 1,29,965.97

Tube Circumference = 12.9 (m)


a. Length = 10 m Each ₹ 67,317. 31

b. Length = 15 m Each ₹ 95,755.62


10.12.3
c. Length = 20 m Each ₹ 1,24,192.77

d. Length = 25 m Each ₹ 1,55,526.38

e. Length = 30 m Each ₹ 1,86,858.83

Tube Circumference = 14.2 (m)


a. Length = 10 m Each ₹ 74,732.29

b. Length = 15 m Each ₹ 1,05,740.79


10.12.4
c. Length = 20 m Each ₹ 1,36,748.71

d. Length = 25 m Each ₹ 1,70,657.71

e. Length = 30 m Each ₹ 2,04,563.24

10.12.5 Tube Circumference = 16.0 (m)


Each ₹ 85,473.46
[55]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


a. Length = 10 m

b. Length = 15 m Each ₹ 1,19,841.72

c. Length = 20 m Each ₹ 1,54,409.07

d. Length = 25 m Each ₹ 1,91,880.97

e. Length = 30 m Each ₹ 2,29,354.04

Supply of Rope Polypropylene (PP) Gabion of size 2 m


× 2 m × 0.45 m having the following properties
i.Mesh opening size 150 mm × 150 mm
ii.Rope Diameter of 9.0 mm
10.13 iii.Linear Density of rope ≥ 65.1 gm/m Each ₹ 2,410.96
iv. Tensile Strength ≥ 1900 Kg
v. Abrasion Resistance of rope after 1000 cycles ≥
65%
vi. CBR Puncture Strength ≥ 7000 Kg.;

Construction and supply of Wire -netting box of size


1.50 m × 1.50 m × 0.45 m made with mechanically
woven, double twisted, hexagonal shaped wire mesh
with wire made of low carbon, high ductile MS wire
with heavy class of galvanization with an additional
layer of PVC coating with mesh type of 10 × 12 as per
EN 10223 & ASTM A975, mesh wire of 2.70 mm (I.D)
/3.70 mm (OD) tensile strength of 450-500/mm2, edge
10.14 wire selvedge around it at least 2.5 times, lacing wire Nos. ₹ 1,928.76
(Zinc PVC coated) of 2.20 mm (I.D)/3.20 mm (OD), VC
coating thickness of 0.50 mm nominal, 0.38 mm
minimum, Mesh opening size 150 mm × 150 mm and
with average weight per unit being 12 Kg with
additional 3% of the weight of box for lacing wire
supplied separately, supporting the facing of the box
with zinc coated steel wire of required length as
directed, complying with ASTM and European norms.

Supply of Sand Bag of size (0.50 × 0.90 m) inner to


inner dimension, made of 100 GSM manufactured from
woven polyester fabric of Black with minimum
properties
10.15 i. Strip Tensile strength (warp/weft) as per Each ₹ 30.54
ASTMD5035 ≥ 550N
ii. Tensile Elongation as per ASTMD5035 ≥ 20 %
including multicolour 3 mm dia. polyester rope of
length 0.75 punched 10 cm from the top & 3 cm
from edge, Rope strength 300 lbs.

[56]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


(Bags are to be supplied a bundle of 100 numbers,
properly packed with name of Manufacturer and Batch
Number and each bag to be marked with “WRD Govt.
of ASSAM” to be printed with minimum font size height
of 50 mm on each bag and mentioning properly the
GSM and type of Geo bag polymer. Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material).

Supply of EC Bag of size (0.49 × 0.83 n) inner to inner


dimension, made of 87 GSM manufactured from woven
polyester of white colour with minimum properties
i. Strip Tensile strength(warp/weft) as per ASTMD
5035 ≥ 7kN/m
ii. Tensile Elongation as per ASTMD 5035 ≤ 20 %
iii. CBR Puncture Resistance as per ASTMD 6241 ≥
850 N
iv. Mullen burst ASTMD 3786 ≥ 700 kPa
v. AOS as per ASTMD 4751 ≤ 425 micron
vi. Water flow/Permeability 60 Lt/m2/min
10.16 Stitching of Bags should be mouth open and Bottom Each ₹ 19.29
SFDS. including 3 mm dia. polyester rope of length 75
cm, punched 10 cm from the top & 3 cm from edge,
Rope strength 300 lbs.
(Bags are to be supplied a bundle of 100 numbers,
properly packed with name of Manufacturer and Batch
Number and each bag to be marked with “WRD Govt.
of ASSAM” to be printed with minimum font size height
of 50 mm on each bag and mentioning properly the
GSM and type of Geo bag polymer. Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material).

Supply of Geo Mega Bags (Size 2.00 m × 1.50 m) inner


dimension made of composite layers of Geo-textile as
per specifications below:
Woven Geo-textile for the outer cover. The woven geo
textile is PP woven with UV resistant slit film tape fibre
10. 17 with MAVR values of the following properties. Geo- Each ₹ 441.20
textile used to manufacture geo-textile bags should
have high mechanical properties for enhanced
durability along with enhanced puncture, abrasion and
U.V. resistance characteristics. Geo-textile should be
inert to biological degradation and resistant to
naturally encountered chemicals, alkalis and acids.
[57]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


 Weight (ISO-9864/ASTM D5261) ≥ 210 Gms/Sqm,
 Tensile strength (MD) (ASTM D4595) ≥ 29 kN/m.
 Tensile strength (CD) (ASTM D4595) ≥ 29 kN/m.
 Tensile Elongation (ASTM D4595) ≥ 5% & ≤ 25%.
 Grab Elongation (ASTM D4632) ≥ 5% & ≤ 25%.
 Tensile strength (ASTM D4632) = 1.5 kN.
 UV resistance (ASTM D4355) = 80%/500 hrs
Non-woven Geo-textile for the inner layer. It is needle
punched non-woven geo-textile made of 100%
polyester staple fibres which are formed into a random
network for dimensional stability. It should resist UV
degradation, rotting and alkalis.
 Weight (ISO-9864/ASTM D5261) ≥ 150 Gms/Sqm,
 Tensile strength (MD) (ASTM D4595) ≥ 5kN/m.
 Tensile strength (CD) (ASTM D4595) ≥ 5 kN/m.
 Tensile Elongation (ASTM D4595) ≥ 5% & ≤ 25%.
 Grab Elongation (ASTM D4632) ≥ 5% & ≤ 25%.
 Tensile strength (ASTM D4632) = 1.5 kN.
 UV resistance (ASTM D4355) = 35%/500 hrs.
(Bags are to be supplied of 100 numbers or part in a
bundle, properly packed with name of Manufacturer
and Batch Number is to be marked on each bag with
“WRD Govt. of ASSAM” to be printed on each bag and
mentioning properly the GSM and type of Geo bag
polymer. Test Certificate from approved NABL
accredited and ISO Certified Laboratory should
invariably be submitted against each batch of
material).
FOR GUWAHATI
(To be supplied only as emergency flood fighting
material during flood season)

Supply of Geo-textile bags of Size (1.00 × 0.70 m) inner


to inner made of staple fibre needle-punched
nonwoven geotextile sheets of 300 GSM manufactured
from 100% polyester fibre with minimum properties
 Tensile strength as per ISO 10319 (CD) ≥ 9 kN/m
 Tensile strength (MD) ≥ 9 kN/m
10.18  Nominal Masses as per ASTMD 5261 ≥ 300.00 Each ₹ 79.56
Gm/m²
 CBR Puncture Resistance as per ASTEMD 6241 ≥
1400 N
 Tensile Elongation as per ASTMD 4595 (CD) ≥
50%
 Elongation (MD) ≥ 50%
[58]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


 UV Resistance as per ASTMD 4355 ≥ 35%
 AOS as per ASTMD 4751 ≤ 100 micron
 Permittivity as per ASTMD4491 ≥ 1.25/sec,
 Trapezoidal Tear Strength (Weaker direction) as
per ASTMD4533 ≤ 260 N
 Permeability as per ASTMD4491= 62.5Lt/m2/sec.
Stitching of Bags should be double line chain stitch
with overlap
(Bags are to be supplied a bundle of 100 numbers,
properly packed with name of Manufacturer and Batch
Number and each bag to be marked with “WRD Govt.
of ASSAM” to be printed with minimum font size height
of 50 mm on each bag and mentioning properly the
GSM and type of Geo bag polymer. Test Certificate from
approved NABL accredited and ISO Certified
Laboratory should invariably be submitted against
each batch of material).
FOR GUWAHATI
(To be supplied only as emergency flood fighting
material during flood season)

Supply of Sewing Thread/Yarn PPMF Stitching Thread


10.19 Rm ₹ 0.10
(2000 Den. Kaplon).
Supply of Geo-Textile Bags, Type C of Size 1.50 m × 1.00
m, inner dimension made of composite layers of geo-
textile as per specifications below:
Woven Geo-textile for the outer cover. The woven
geo textile is woven with UV resistant slit film tape
fibre with MAVR values of the following properties.
Geo-textile used to manufacture geo-textile bags
should have high mechanical properties for enhanced
durability along with enhanced puncture, abrasion and
U.V. resistance characteristics. Geo-textile should be
10.20 inert to biological degradation and resistant to Each ₹ 496.00
naturally encountered chemicals, alkalis, and acids.
 Weight (ISO-9864/ASTMD 5261) ≥ 250
Gms/Sqm.
 Tensile strength (MD) (ASTMD 4595) ≥35
kN/m.
 Tensile strength (CD) (ASTMD 4595) ≥ 35
kN/m.
 Tensile Elongation (ASTMD 4595) ≥ 5% & ≤
30%.
 Grab Elongation (ASTMD 4632) ≥ 5% & ≤ 30%.
[59]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


 Tensile strength (ASTMD 4632) = 1.5 kN.
 UV resistance (ASTMD 4355) = 70%/500 hrs.
Non-woven Geo-textile for the inner layer. It is
needle punched non-woven geo-textile made of 100%
polypropylene staple fibers which are formed into a
random network for dimensional stability. It should
resist UV degradation, rotting and alkalis.
 Weight (ISO-9864/ASTMD 5261) ≥ 300
Gms/Sqm.
 Tensile strength (MD) (ASTMD 4595) ≥ 12
kN/m
 Tensile strength (CD) (ASTMD 4595) ≥ 12
kN/m
 Tensile Elongation (ASTMD 4595) ≥ 5% & ≤
30%
 Grab Elongation (ASTMD 4632) ≥ 5% & ≤ 30%
 Tensile strength (ASTMD 4632) = 1.5 KN
 UV resistance (ASTMD 4355) = 70%/500 hrs
(Bags are to be supplied of 100 numbers or part in a
bundle, properly packed with name of Manufacturer
and Batch Number is to be marked on each bag with
“WRD Govt. of ASSAM” to be printed on each bag and
mentioning properly the GSM and type of Geo bag
polymer. Test Certificate from approved NABL
accredited and ISO Certified Laboratory should
invariably be submitted against each batch of
material)

[60]
Schedule of Rate 2022 - 23

CHAPTER - 11 :: MISCELLANEOUS

Sl. no. Description Unit Basic rate


Labour charge for clearing white ant nest from the
embankment including digging earth, clearing white
ant nest, applying anti termite chemical and carrying
11.1 Cum ₹ 441.98
spoils to a safe distance and filling the pits by fresh
earth including ramming, watering etc. Complete as
directed.
Dewatering by 5 H.P. water pump including supply of
11.2 necessary fuel, engine oil and pump operator etc. Hour ₹ 214.50
complete as directed.
Labour charge for laying of soling stone, brick bats,
broken stone metal, sand gravel etc. on approach road
11.3 including ramming dressing the seat and local carriage Cum ₹ 155.03
of materials up to a distance of 60 m complete as
directed.
Preparation of stack yard of boulder/metal etc.
including cutting light jungles and removing the same
11.4 Cum ₹ 7.42
to a safe distance, levelling the ground, filling up
depressions etc. complete as directed
Labour charge for driving C.G.I. Sheets by hydraulic
driving equipment up to specified depth including hire
charge of equipment, cost of P.O.L. etc. complete as
11.5 Sqm ₹ 72.05
directed.
(C.G.I. sheets will be supplied by the department free
of cost)
Labour charge for driving Asbestos sheets by Manual
means up to specified depth. complete as directed.
11.6 Sqm ₹ 164.15
(Asbestos sheets will be supplied by the department
free of cost)
Providing approved variety of Vetiver plantation
certified by The Vetiver Network International (TVNI)
or its affiliate in India including pouching of tiller with
selected soil for agricultural use mixed with farmyard
manure in 8” × 6” poly pouch, maintaining the pouched
plants for at least 1 (One) month with application of
11.7 growth promoter, fertilizer, watering, weeding etc., Rm ₹ 242.52
dressing of the area of plantation, planting the pouched
plants as per design approved by The Vetiver Network
International (TVNI) or its affiliate in India. (Excluding
jungle clearance, earth work in trimming, cutting,
filling etc.) and Maintenance of the Vetiver plants by
watering, pruning, weeding, mulching, application of
manure, fertilizer, growth promoter etc. for 4 (Four)

[61]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


months after completion of plantation etc. complete as
directed.
Supply of wooden flood gauge of size 100 mm × 75 mm
of length 3.00m, including dressing properly,
chamfering one end, coal taring properly for a length
of 1.00m from the chamfered end, painting two coats
11.8 Nos ₹ 1,990.96
with white paint over one coat of priming coat in the
remaining length of 2.00 m, marking the metric scale
one side (100 mm side) on the painted length of 2.00
m with black and red paint complete as directed.
Supply of circular float made of local wood in
cylindrical shape of length 300 mm of diameter 100
11.9 Nos ₹ 122.96
mm at one side and 50 mm at the other side, dressing
properly, complete as directed
Collection and supply of brick bats 10 - 40 mm size to
work site including loading, unloading transportation
11.10 Cum ₹ 1,742.59
and stacking in measurable stacks including sale tax,
compensation if any, etc. complete as directed
Manufacturing, supplying and fixing retro reflective
sign boards of size 1.22 m × 0.76 m made up of 4 mm
thick aluminium sheet, face to be fully covered with
high intensity encapsulated type heat activated retro
reflective sheeting conforming to type - IV of ASTM-D
4956-01 in blue and silver white or other colour
combination including subject matter, message (Bi -
lingual), symbols and borders etc. as per IRC: 67-2001,
pasted on substrate by an adhesive backing which
shall be activated by applying heat and pressure
conforming to Class - 2 of ASTM-D-4956-01 and fixing
the same with suitable sized aluminium alloy rivets @
20 cm C/C to back support frame of M.S. angle iron of
size 25 × 25 × 3 mm along with theft resistant Nos ₹ 13,266.80
11.11
measures, mounted and fixed with 2 nos. of 900 mm
thick pipe vertical post (AISI 202 Grade) of length 3750
mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete
30 cm × 30 cm × 30 cm etc. complete. and including
making holes in pipes, angles flats, providing & fixing
M.S. message plate of required size, steel work to be
painted with two or more coats of synthetic enamel
paint of required shade and of approved brand &
manufacture over priming coat of Zinc chromate
yellow primer (Vertical post to be painted in black and
white colours). Backside of aluminium sheet to be
painted with two or more coats of epoxy paint over and
including appropriate priming coat including all leads
[62]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


and lifts etc. complete as per drawing, specification
and direction of Engineer-in-Charge
Galvanized Wire Netting Sheet made of 8 SWG wire
152 mm square mesh in sheet 2.57 m × 1.66 m with
longitudinal wire at 152 mm centre and 76 mm
11.12 projection of each wire on all sides beyond the net size Sheet ₹ 902.62
of 2.42 m × 1.5 m having knots of 12 SWG at every
joints, weight of each sheet should not be less than 6.3
Kg/sheet.
Hexagonal Wire Netting Roll made of 8 SWG wire triply
twisted 152 mm mesh of size 15.24 m × 3.66 m
11.13 Roll ₹ 11,871.83
longitudinal. Weight of each roll should not be less
than 83 Kg/roll.

[63]
Schedule of Rate 2022 - 23

[64]
Schedule of Rate 2022 - 23

CHAPTER - 12 :: MAINTENANCE OF DRAINAGE CHANNEL

Sl. no. Description Unit Basic rate


Clearing of deposited compact water hyacinth root
and other aquatic plants from the bed of
12.01 drains/channels including cutting, removing and Sqm ₹ 105.77
stacking at places away from the bank etc. Complete
with all lead and lift etc. complete as directed.
Earthwork in de-siltation of drainage channel to
proper grade and slope up to required section
including excavation of side slopes and bed of the
channel in marshy/muddy soil, removal of all derbies
like decomposed organic matters, plastic garbage,
12.02 Cum ₹ 339.58
aquatic plants, water hyacinth etc., dewatering by
manual means if necessary etc. and removing of the
excavated soil and garbage/spoils up to a distance of
100 m etc. including all lead and lift complete as
directed.
Construction of temporary blockade of size 0.75 m ×
0.40 m by earth filled cement bags supported with
Bholuka bamboo palisading at both sides in the bed of
channel for draining water through a restricted path at
the time of re-sectioning/construction of foundations
12.03 Rm ₹ 848.97
of flood walls etc. including driving of bamboo posts
0.80 m above ground and 1.00 m below ground at 0.30
m clear apart, tying with one row half Jati bamboo
kamies and removing of the blockade after completion
of the work etc. complete as directed.
Clearing of garbage, derbies and waste materials from
the drainage channel up to a depth of 0.60 m along bed
12.04 and bank slopes of the channel including carriage of Cum ₹ 407.10
the spoils to a safe distance up to 100 m and stacking
in measurable stacks etc. complete as directed.
Carriage of excavated muddy/slushy soil/garbage by
truck of 10 MT capacity and depositing the same in
12.05 suitable dumping ground within an average lead of Cum ₹ 274.93
5.00 Km including cost of P.O.L. and loading/unloading
charges etc. complete as directed.

[65]
Schedule of Rate 2022 - 23

[66]
Schedule of Rate 2022 - 23

CHAPTER - 13 :: MECHANICAL RATES FOR CONSTRUCTION OF SLUICE

Sl. no. Description Unit Basic rate

Supply of M.S. Shaft (Best quality) of diameter


a) 40 mm mtr ₹ 2,460.00
13.1 b) 50 mm mtr ₹ 3,420.00
c) 63 mm mtr ₹ 3,780.00
d) 75 mm mtr ₹ 5,040.00
Thread cutting (Square) 1 TPI/2 TPI including fine
finishing and making hole in one end as per direction
for sizes as given below
a) 40 mm mtr ₹ 2,000.00
13.2
b) 50 mm mtr ₹ 2,250.00
c) 63 mm mtr ₹ 2,450.00
d) 75 mm mtr ₹ 2,800.00
Shaft pin with length up to 150 mm for the following
diameters
a) 12 mm No ₹ 150.00
13.3
b) 16 mm No ₹ 160.00
c) 20 mm No ₹ 170.00
C.I. Boss with internal thread cutting 1 TPI/2 TPI,
making groove for bearing slot for lock plate and 1.5"
drill for providing handle as per direction for the
following sizes: (dia. × height)
13.4
a) 125 mm × 150 mm No ₹ 6,840.00
b) 125 mm × 175 mm No ₹ 7,200.00
c) 150 mm × 200 mm No ₹ 8,100.00
Making & supply of C.I. roller with suitable collar 10 -
12 mm & centre hole 10 - 20 mm as per direction
13.5 (Machine finished), size (dia. × height)
a) 100 mm × 150 mm No ₹ 1,700.00
C.I. plain roller with centre hole 10 - 25 mm of the
following size: (dia. × height) (Machine finished)
13.6 a) 65 mm × 75 mm No ₹ 1,250.00
b) 75 mm × 100 mm No ₹ 1,600.00
[67]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate

M.S. base plate 300 mm × 300 mm of the following


thickness as per direction including supply of
materials. (Machine finished)
13.7
a) 10 mm No ₹ 1,950.00
b) 12 mm No ₹ 2,040.00
M.S. lock plate 300 mm × 300 mm of the following
thickness as per direction including supply of
materials. (Machine finished)
13.8
a) 8 mm No ₹ 1,400.00
b) 10 mm No ₹ 1,550.00
F' shaped roller bracket made of 10 mm thick plate of
13.9 size 75 × 200 mm with hole as per direction to
accommodate with the roller size: (Machine finished)

a) 100 mm × 150 mm No ₹ 1,200.00


13.10 Clamp for lock plate. No ₹ 140.00
H.D. Thrust ball bearing (Best quality) ISI specified
a) 50 mm dia. No ₹ 1,200.00
13.11
b) 65 mm dia. No ₹ 1,250.00
c) 75 mm dia. No ₹ 1,410.00
C.I. counter weight circular type 1.5" thick with 25 mm
13.12 dia. hole & weight of 35 Kg each as per direction
(machine finished & fine grinded) Kg ₹ 90.00
C.C. counter weight circular type 400 mm dia. around
100 mm thick with 25 mm dia. hole at centre & two
13.13
handles for carrying weight of 30 Kg each as per
direction (Machine finished) Kg ₹ 42.00
13.14 Counter weight holder No ₹ 500.00
C.I pulley 16 mm to 25 mm dia. with centre hole as per
direction (Machine finished)
13.15 a) 125 mm No ₹ 800.00
b) 150 mm No ₹ 870.00
Pulley stand made of 100 × 50 mm channel for (As per
13.16 direction)
a) 125 mm No ₹ 760.00

[68]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate

b) 150 mm No ₹ 800.00
13.17 Pulley pin of 16 mm dia. No ₹ 200.00
13.18 M.S. Angles (Different sizes) Kg ₹ 80.00
13.19 M.S. Channels (Different sizes) Kg ₹ 80.00
13.20 M.S. Plates (Different sizes) Kg ₹ 95.00
13.21 M.S. Flats (Different sizes) Kg ₹ 75.00
13.22 M.S. Joists (Different sizes) Kg ₹ 90.00
M.S. Electrodes (Best quality)
13.23 a) 8 SWG Pkt. ₹ 700.00
b) 10 SWG Pkt. ₹ 545.00
Separator stud with nut on both end with tube of
13.24
length 250 mm to 460 mm Set ₹ 600.00
Distant tube with pin of the following size (Machine
finished)
13.25 a) 75 × 12 mm No ₹ 150.00
b) 100 × 12 mm No ₹ 160.00
C.I. roller pin of length 150 mm to 250 mm dia.
(Machine finished)
13.26 a) 16 mm No ₹ 90.00
b) 20 mm No ₹ 120.00
"J" type rubber seal of the following sizes (Best quality)
ISI specified
13.27 a) 75 mm mtr ₹ 550.00
b) 125 mm mtr ₹ 676.00
“J” type rubber seal corner of the following sizes
13.28
a) 75 mm No ₹ 120.00
b) 125mm No ₹ 140.00
Steel wire rope (Tested quality) of the following sizes
(ISI standard)
13.29 a) 16 mm mtr ₹ 410.00
b) 19 mm mtr ₹ 450.00

[69]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate

13.30 Nylon Rope Kg ₹ 200.00


13.31 Waste Cotton Kg ₹ 130.00
13.32 M.S. Rod (Different sizes) Kg ₹ 60.00
13.33 Welding goggle Pair ₹ 220.00
13.34 Arc welding mask No ₹ 365.00
13.35 Arc welding dark glass No ₹ 138.00
13.36 Arc welding holder, 400/600 Amp No ₹ 355.00
13.37 Leather hand gloves Pair ₹ 270.00
13.38 Gas cutting nozzle No ₹ 365.00
13.39 Arc welding cable, 400/600 Amp mtr ₹ 485.00
13.40 Nuts & bolts (Assorted size) Kg ₹ 170.00
13.41 M.S. washer (Assorted size) Kg ₹ 135.00
13.42 Hacksaw blade 1.5" × 12", (D/E) Dozen ₹ 310.00
13.43 Coir rope Kg ₹ 115.00
13.44 Steel wire brush No ₹ 100.00
13.45 Painting brush 3"11 inch ₹ 195.00
13.46 W.B. Grease Kg ₹ 360.00
13.47 Turpentine oil Ltr ₹ 160.00
13.48 Antisol red oxide paint Ltr ₹ 330.00
13.49 Red oxide primer Ltr ₹ 300.00
13.50 Gas cutting hose, 12 mm dia. (Red & Black) mtr ₹ 170.00
Matured full length bamboo
13.51 a) Bhaluka No ₹ 140.00
b) Jati No ₹ 110.00
"U" clamp of size
13.52 a) 16 mm No ₹ 170.00
b) 19mm No ₹ 190.00
13.53 G.I. pipe of sizes mtr ₹ 350.00

[70]
Schedule of Rate 2022 - 23

Sl. no. Description Unit Basic rate


a) 25 mm dia.

b) 40 mm dia. mtr ₹ 450.00


13.54 Transformer oil Ltr ₹ 275.00
13.55 Lubricating oil Ltr ₹ 325.00
13.56 Emery paper Dozen ₹ 175.00
13.57 Hurricane lamp No ₹ 500.00
G. I. wire
13.58 a) 22 SWG Kg ₹ 160.00
b) 24 SWG Kg ₹ 180.00
M.S. chain of size
13.59 a) 6 mm Kg ₹ 130.00
b) 8 mm Kg ₹ 160.00
Lock & Key of size
13.60 a) 45 mm No ₹ 250.00
b) 55 mm No ₹ 280.00
Tarpaulin Sheet
13.61
a) 3.4 m × 2.7 m Sqm ₹ 480.00
13.62 Coptic Red paint Ltr ₹ 275.00
Gas cutting Kit (Including Oxygen meter, Acetylene
13.63
meter, cutting torch, regulator etc.) Kit ₹ 5,150.00
First Aid kit (comprising of items like Band - Aid, Dettol
13.64 100 ml, Iodine solution, Antiseptic cream, Scissor,
Cotton, Bandage, Burnol, Spray etc. complete). Kit ₹ 850.00
13.65 Filled DA Gas Cum ₹ 480.00
13.66 Filled Oxygen Gas Cum ₹ 67.00

[71]
Schedule of Rate 2022 - 23

[72]
Schedule of Rate 2022 - 23

CHAPTER - 14 :: DREDGING

Sl. no. Description Unit Rate


14.01 Dredging by cutter suction dredger by suitable size,
type and capacity as per general and special condition,
technical specification to provide for 3.50 m Least
Available Depth (LAD) and channel width up to 350 m
in tributary river of Brahmaputra in Assam round the
year for 3 (Three) years.
The rate shall include the surveys (at all stage; pre and
post dredging survey) mobilization and de
mobilization chainages, shifting charge from shoal to
shoal, dumping dredging spoil up to 1,000 m through
pipelines or road transportation including all taxes,
charges as applicable, complete in all respect as
directed. m3 ₹ 200.91
14.02 Rate for disposal of dredging materials for additional
1,000 m m3 ₹ 100.46

[73]