Professional Documents
Culture Documents
Power System Simulation Lab Manual New (2)
Power System Simulation Lab Manual New (2)
INDEX
1 1
Y-BUS FORMULATION
1
LOAD FLOW STUDIES FOR A GIVEN POWER SYSTEM USING M i P o w er
4
FAULT STUDIES FOR A GIVEN POWER SYSTEM USING MiPower
LOAD FREQUENCY CONTROL OF A SINGLE AREA POWER SYSTEM USING
5 MATLAB
10 EARTH RESISTANCE
11 STUDY OF POWER FACTOR IMPOVEMENT
12
NUMERICAL OVER CURRENT RELAY TESTING
13
INSULATION TESTING HT & LT CABLE
EXPERIMENT NO:1
Figure shows the line diagram of a simple four bus system. Table gives the
line impedances identified by the buses on which they terminate. The shunt
admittance at all the buses is assumed negligible. Form Y bus
BUS 1 BUS 2
BUS 4
BUS 3
G
(3) (4)
(1)
(2) (5)
G
Table: 1.1
Bus cone Impedanc Line Charging
From- e R+jX B/2
1-2 0.02+j0.06 j 0.030
1-3 0.08+j0.24 j 0.025
2-3 0.06+j0.18 j 0.020
2-4 0.06+j0.18 j 0.020
2-5 0.04+j0.12 j 0.015
3-4 0.01+j0.03 j 0.010
4-5 0.08+j0.24 j 0.025
Open dialog box is popped up as shown below, where you are going to browse the desired
directory and specify the name of the database to be associated with the single line
diagram. Click Open button after entering the hired database name. Configure Database
dialog will appear with path chosen.
Uncheck the Power System Libraries and Standard Relay Libraries. For this example these
standard libraries are not needed, because all the data is given on pu for power system libraries
(like transformer, line\cable, generator), and relay libraries are required only for relay co-
ordinate studies. If Libraries are selected, standard libraries will be loaded along with the
database. Click Electrical Information tab. Since the impedances are given on 100 MVA
base, check the pu status. Enter the Base and Base frequency as shown below. Click on
Breaker Ratings button to give breaker ratings. Click OK to create the database to return to
Network Editor.
In the network editor, configure the base voltages for the single line diagram. Select menu
option Configure→Base voltage. The dialog shown below appears. If necessary change
the Base-voltages, color, Bus width and click OK.
Click on Bus icon provided on power system tool bar. Draw a bus and a dialog appears
prompting to give the Bus ID and Bus Name. Click OK. Database manager with
corresponding Bus Data form will appear. Modify the Area number, Zone number and
Contingency Weightage data if it is other than the default values. If this data is not furnished,
keep the default values. Usually the minimum and maximum voltage ratings are ± 5% of the
rated voltage. If these ratings are other than this, modify these fields. Otherwise keep the
default values.
Bus description field can be effectively used if the bus name is more than 8 characters. If bus
name is more than 8 characters, then a short name is given in the bus name field and the bus
description field can be used to abbreviate the bus name. For example let us say the bus name
is Northeast, then bus name can be given as NE and the bus description field can be North
East.
Figure shows a single line diagram of a 6-bus system with two identical generating units, five
lines and two transformers. Per-unit transmission line series impedances and shunt
susceptances are given on 100 MVA base, generator's transient impedance and transformer
leakage reactances are given in the accompanying table.
If a 3-phase to ground fault occurs at bus 5, find the fault MVA. The data is given below.
Generator details:
’
G1= G2 = 100MVA, 11KV with X d=10%
Transformer details:
As generators G1 and G2 have same parameters, only one generator library is required.
The same applies for transformers also.
\\enter here
to specify
the name
Open dialog box is popped up as shown below, where you are going to browse the desired
directory and specify the name of the database to be associated with the single line diagram.
Click Open button after entering the desired database name. Configure Database dialog will
appear with path chosen.
Click
OK
Click on OK button in the Configure database dialog, the following dialog appears.
Uncheck the Power System Libraries and Standard Relay Libraries. For this example these
standard libraries are not needed, because all the data is given on p u for power system
libraries (like transformer, line\cable, generator), and relay libraries are required only for relay
co-ordination studies. If Libraries are selected, standard libraries will be loaded along with the
database. Click electrical information tab.
Bus description field can be effectively used if the bus name is more than 8 characters. If bus
name is more than 8 characters, then a short name is given in the bus name field and the bus
description field can be used to abbreviate the bus name. For example let us say the bus name
is Northeast, then bus name can be given as NE and the bus description field can be North
East.
After entering data click save, which invokes Network Editor. Follow the same procedure
for remaining buses. Following table gives the data for other buses.
Bus data
Bus Number 1 2 3 4 5 6
Bus Name Bus1 Bus2 Bus3 Bus4 Bus5 Bus6
Nominal voltage 11 11 110 110 110 110
Area number 1 1 1 1 1 1
Zone number 1 1 1 1 1 1
Contingency Weightage 1 1 1 1 1 1
Enter Element ID number and click OK. Database manager with corresponding Line\Cable
Data form will be open. Enter the details of that line as shown below.
Enter Structure Ref No. as 1 and click on Transmission Line Library >> button. Line &
Cable Library form will appear. Enter transmission line library data in the form as shown for
Line3-4.
After entering data, Save and Close. Line\Cable Data form will appear. Click Save, which
invokes network editor. Data for remaining elements given in the following table. Follow the
same procedure for rest of the elements.
Click on Two Winding Transformer icon provided on power system tool bar. To draw the
transformer click in between two buses and to connect to the from bus, double click LMB
(Left Mouse Button) on the From Bus and join it to another bus by double clicking the mouse
button on the To Bus Element ID dialog will appear. Click OK.
Transformer Element Data form will be open. Enter the Manufacturer Ref. Number as 30.
Enter transformer data in the form as shown below. Click on Transformer Library >>button.
Transformer library form will be open. Enter the data as shown below. Save and close library
screen.
nd
2 Transformer details
Transformer Number 2
Transformer Name 2T2
From Bus Number 6
To Bus Number 2
Control Bus Number 2
Number of Units in Parallel 1
Manufacturer ref. Number 30
De Rated MVA 100
From Breaker Rating 5000
To Breaker Rating 350
Nominal Tap Position 5
Click on Generator icon provided on power system tool bar. Draw the generator by clicking
LMB (Left Mouse Button) on the Bus1. Element ID dialog will appear. Click OK.
Generator Data form will be opened. Enter the Manufacturer Ref. Number as 20. Enter Generator data in
the form as shown below.
Click on Generator Library >> button. Enter generator library details as shown below.
Save and Close the library screen. Generator data screen will be reopened. Click Save button,
which invokes Network Editor. Connect another generator to Bus 2. Enter its details as given
in the following table.
2 nd Generator details
Name GEN-
2
Bus Number 2
Manufacturer Ref. Number 20
Number of Generators in Parallel 1
Capability Curve Number 0
De-Rated MVA 100
Specified Voltage 11
Scheduled Power 20
Reactive Power Minimum 0
Reactive Power Maximum 60
Breaker Rating 350
Type of Modeling Infinit
e
Note: To neglect the transformer resistance, in the multiplicationfactor table give the X to R Ratio
as 9999.
TO solve short circuit studies choose menu option Solve →Short Circuit Analysis or click
on SCS button on the toolbar on the right side of the screen. Short circuit analysis screen
appears
2 Click here to open short circuit studies screen
Study Information.
3. Click here
1. Click here
2. Click here
Click OK
Afterwards click Execute. Short circuit study will be executed. Click on Report to view the
report file.
1 Click here
for report
’
’
EXPERIMENT NO:5
LOAD FREQUENCY CONTROL OF A SINGLE AREA POWER SYSTEM
Aim: To obtain the frequency response of single and two area power system using MATLAB
Formula used:
1)
2)
3)
4)
Where
D = damping coefficient
GG – gain of generator
GT - gain of turbine
GP - gain of power
Procedure:
SIMULINK RESULTS:
Graph:
RESULT
EXPERIMENT NO:6
Aim: To obtain the frequency response of two area power system using MATLAB
Apparatus: MATLAB
Formula used:
1)
2)
3)
4)
Where
D = damping coefficient
GG – gain of generator
GT - gain of turbine
GP - gain of power
Procedure:
SIMULINK RESULTS:
RESULT
EXPERIMENT NO : 6
AIM
To determine the power diagram, active, reactive, apparent power, power factor
correction in a 3 phase transmission line with RL load
SOFTWARE USED
MATLAB
THEORY
Power in an AC Circuit
Inductive Loads
90% of the industrial load consists of Induction Machines (1-ϕ and 3-ϕ). Such
machines draw magnetizing current to produce the magnetic field and hence work
at low power factor.
For Induction motors, the pf is usually extremely low (0.2 - 0.3) at light loading
conditions and it is 0.8 to 0.9 at full load.
The current drawn by inductive loads is lagging and results in low pf.
Other inductive machines such as transformers, generators, arc lamps, electric
furnaces etc work at low pf too.
. The R and L are present in all inductive equipments and the C is used for pf
improvement.
Here, IL = current drawn by the circuit capacitor C isn't used,
ϕL = phase angle between voltage V and load current IL,
IC = capacitive current drawn by C,
I = resultant current when C is used,
ϕ = phase angle between voltage V and net current I.
RESULT
EXPERIMENT NO: 7
To plot the V-I Characteristics of the solar cell and hence determine the maximum power point
and fill factor
THEORY:
The solar cell is a semi conductor device, which converts the solar energy into electrical energy.
It is also called a photovoltaic cell. A solar panel consists of numbers of solar cells connected in
series or parallel. The number of solar cell connected in a series generates the desired output
voltage and connected in parallel generates the desired output current. The conversion of
sunlight
(Solar Energy) into electric energy takes place only when the light is falling on the cells of the
solar panel. Therefore in most practical applications, the solar panels are used to charge the lead
acid or Nickel-Cadmium batteries. In the sunlight, the solar panel charges the battery and also
supplies the power to the load directly. When there is no sunlight, the charged battery supplies
the required power to the load
IV Curve
The IV curve of a solar cell is the superposition of the IV curve of the solar cell diode in
the dark with the light-generated current.1 The light has the effect of shifting the IV
curve down into the fourth quadrant where power can be extracted from the diode.
Illuminating a cell adds to the normal "dark" currents in the diode so that the diode law
becomes:
Plotting the above equation gives the IV curve.The power curve has a a maximum
denoted as PMP where the solar cell should be operated to give the maximum power
output. It is also denoted as P MAX or maximum power point (MPP) and occurs at a
voltage of VMP and a current of IMP.
CIRCUIT DIAGRAM
RESULT
Vmp =
Imp =
Voc =
Isc =
Fill factor =
Pmax =
EXPERIMENT – 8
AIM
PROBLEM DESCRIPTION
RESULT
Simulated the phenomenon of Ferranti effect for medium, transmission line
using MATLAB SIMULINK model. It is observed that receiving end voltage is
greater than sending end voltage
EXPERIMENT No.9
EARTH RESISTANCE
AIM
To determine the resistance to earth of the given earthing system and design an earthing
system from soil resistivity of the given area.
OPERATING PRINCIPLE
The principle used in measuring the earth resistance is based on simple Ohm’s law.
a) MEASUREMENT OF EARTH RESISTANCE
To measure the earth resistance with digital earth tester it should be used three terminal
type. For that terminals E1 and P1 are to be shorted and connected to the earth
connection whose resistance has to be found.
Connected as per the Fig.1 and take the reading by pressing the test switch. Note down
the reading displayed on the L.C.D of the instrument.
All the four spikes to be buried in one straight line and distance between them to be
kept same. The value of ‘L’ may be kept between 10m to 20m. Take the reading by
pressing the test switch (taking care of range factor). Observed value is in ohms. Let it be
( Rm). The value of Earth resistivity( ρ) may be obtained from the following formula.
ρ=2πLR ohms cm
Where R= value of Earth Resistance measured in ohms.
L= Distance between spikes incms.
ρ=Earth resistivity in ohms cm.
π=3.14
To avoid error due to the wire resistance first short the wires and note down the
meter reading Let it be (Rw). Then connect the wires to the electrodes as explained
above. This reading minus the reading with the wire shorted will give actual value of
resistance.
So actual R= Rm - Rw .
RESULT
Earth Resistance =
Earth resistivity =
300 V
0-5 0-5 A
M L
A
A C V
240 Inducti
V ve
50 V 0-300 Load
Hz V
Figure 1: Circuit for study of improvement of power factor.
not connected, from the meter readings, we get
P . Σ
P
P = V I cos θ1 =⇒ cos θ1 = =⇒ θ 1 = cos−1 VI (1)
VI
From this we can find the reactive power supplied by the source
Q1 = V I sin θ1 (2)
when capacitor is not connected. If the desirable power factor is cos θ2 > cos θ 1, then, the over-
all reactive power supplied by the source corresponding to the new power factor cos θ2 is given
by
Q2 =V I sin(cos−1 θ2) (3)
where Q2 < Q1. Therefore, the reactive power to be supplied by the capacitor to be connected
in parallel with the load, and its reactance are given by
V2 V2
Q
1 − Q2 = X =⇒ XC = (4)
C Q1 − Q2
TABULAR COLUMN
Load 1:
Case V Volts I Amps Power Factor
Without C
With C =
Load 2:
Procedure
1. Realize the circuit shown in Figure 1 by connecting one inductive load
using patch cords on the front panel of the trainer.
2. Switch on power and record all meter readings in Table 1. Calculate the
power factor without capacitor and enter it in the same table.
3. Assume a new power factor value which is greater than the value found in
the previous step. For this new desirable power factor calculate the capacitor
to be connected in parallel using Eqs. (3) to (5).
RESULT
EXPERIMENT NO. 11
OVER CURRENT RELAY
AIM
This trainer kit consists of three parts-Current source, Relay and Timer
a) Current source
This part consists of 0-20A AC current source with Digital AC Ammeter.
Variable current output terminals are provided on the front panel. The 230V single
phase AC is applied to the autotransformer through the Mains ON switch.The
secondary of the autotransformer is connected to the primary of the stepdown
transformer. The 3.5V/ 20A secondary of this step down transformer is connected to
the series circuit consisting of a 20A Digital panel ammeter and a front panel
mounted Selector switch.
b). Relay
This part consists of PROK DEVICES make 1 phase Numerical / Microprocessor
based over current relay. Relay inputs and Trip outputs are terminated on the front
panel. Current Transformer of 4A/1A are connected to the Relay input.
c). Timer
A 4 digit Timer with a resolution of 0.001 sec is connected to one set of normally
open contact of the Relay under test. Another set of normally open contact is
connected to the Trip indicator. After setting the required test current with the
Selector switch in the Set position , this switch is put to the Start position. This
causes the set current to flow through the CT input of the Relay under test and
simultaneously the Timer is started as indicated by the relay ON indicator. At the
end of the preset time , Relay under test closes it’s NO contacts connected to the
Timer and the Trip indicator . The Timer stops and the Trip indicator glows.
PROCEDURE
1. Set the output current source setting control to minimum position.
2. Switch On the aux. power supply of the Kit . Remove Relay front cover.
3. Put the selector switch to OFF position. In this position the Relay
parameters can be set.
4. Set the required trip time(TM), trip characteristics (MODE) and set over
current (PM) values on the relay. Refer relay manual for setting the
parameters.
5. Connect the OUTPUT current terminals to CT input terminals and CT
output terminals are internally connected to Relay input terminals. Connect
Trip input terminals to Trip output terminals of the Relay.
6. Set the load current above the set over load current by varying the
autotransformer. Ammeter current is 4 times the relay input current, because
of 4A/1ACT. Relay shows the current ¼ of Ammeter current and this
current is the fault current.
8. Put the selector switch to START position. The Relay ON indicator glows.
Timer starts counting . DEF/IDMT LED on the relay starts blinking
depending on which mode we have selected .DEF Led blinks if DEF is
selected . IDMT LED blinks if NI, NI-1.3 or L Time is selected.
9. Relay will Trip after the set time, since the current is more than the set over
current and trip indicator glows and current source also trips. DEF/IDMT
LED on the relay stops blinking . Timer stops. Note down the current and
time.
10. Repeat the above for different TMS and note down the time and current.
11. Repeat the same for different PMS- different set current-Is
TABULAR COLUMN
Experiment No.1 : Normal inverse Time Characteristics of OC Relay:
GRAPH
A graph of the operating characteristics of the relay is drawn. The plug setting
multiplier is plotted on the X-axis and the time of operation on the Y-axis . Curves
are drawn for different time setting multipliers. The curves are plotted for Normal
Inverse., very inverse and extremely inverse characteristics.
RESULT
EXPERIMENT NO: 12
INSULATION TESTING HT AND LT CABLE
Technical Specification
PANEL INSTRUCTION
OPERATION:
1. INSULATION MEASUREMENT
1. Connect the test line to terminal L/U/V and E . Then connect to the testing
insulation. Terminal G should be connected to the protection ring or earth
throughout the whole testing period.
4. Turn the function selection switch to choose proper range, Press the TEST
button, then the high voltage between terminal E and L/V will be output.
5. Press and Hold the TEST button for over 2secs, beeper alarms which
indicates that the meter enters into testing mode and automatically
extends the testing time for 30 seconds. Beeper alarms in every 2
seconds. Press the button again to exit the mode at any time.
6. During the testing ,press the HOLD button to hold the result. Press the
button again to exit hold mode.
7. When in testing mode, if LCD displays1, there may be two reasons:
A) the tested insulation is over the max .range or