CONSTRUCTION OF TSE NETWORK FOR

GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
00 00 C 01/06/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


Pre-Qualification for Instrumentation (FLOW METER &PRESSURE
GRP-08-TS000-SGC-ICA-PRQ-00006 00
TRANSMITTER & LEVEL TRANSMITTER) (NAMA)

Reviewed by GRP/PMC Replied by Contractor


Received Replied Doc. Received Replied Doc.
Doc. Rev. No CRS Status Doc. Rev. No
Date Date Status Date Date Status
00 12/05/2024 01/06/2024 IFA C

Name Abbreviation Discipline


Jeffry Maala JM I&C
Sadath Nizami SN QA
Reviewers

1 GRP/PMC Comments Rev00 Contractor’s Reply


Contractor provide a “general” subject for I&C instruments. The subject shall NOTED, MODIFIED, the PQ IS FOR Flow meters & pressure
JM
be specific to clarify the intended purpose of these PQ. transmitters, and level switch

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 1 of 3
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
00 00 C 01/06/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


Pre-Qualification for Instrumentation (FLOW METER &PRESSURE
GRP-08-TS000-SGC-ICA-PRQ-00006 00
TRANSMITTER & LEVEL TRANSMITTER) (NAMA)

2. GRP/PMC Comments Rev00 Contractor’s Reply


Contractors shall clarify which product (flow meter, pressure transmitter, level Noted and Modified, nama is to Supplying of Flow meters &
switch) to consider for this PQ. It shall not be in general terms, as per the pressure transmitters, and level switch. Please refer to page 46
JM
subject. The attached statement of compliance should relate only to the up to 124, and detailed BOM will be submitted during material
product list that is required to be included. submittal stage.
3. GRP/PMC Comments Rev00 Contractor’s Reply
Noted and complied, please refer to page 209
JM Client compliance statement shall be stamped by vendor.

4. GRP/PMC Comments Rev00 Contractor’s Reply


Contractor shall submit Technical & Commercial certification (Partnership,
Support Service, etc. between propose specific Vendor (NAMA) and the Please refer to page 328, Siemens Support letter which state that
selected Control systems manufacturers, such as Siemens or other reputable Nama Green is an authorized to execute commercial and
JM technical works with siemens support.
manufacturers. The above certification should give NAMA the authorization to
execute commercial and technical works related to the selected manufacturer
control system and all its related product portfolio.
5. GRP/PMC Comments Rev00 Contractor’s Reply
JM Contractor to clarify and provide a list of relevant projects that are 100% Added NAMA project reference list related to SOW.

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 2 of 3
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
00 00 C 01/06/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


Pre-Qualification for Instrumentation (FLOW METER &PRESSURE
GRP-08-TS000-SGC-ICA-PRQ-00006 00
TRANSMITTER & LEVEL TRANSMITTER) (NAMA)

completed. Please refer to page 133

6. GRP/PMC Comments Rev00 Contractor’s Reply


SGC shall attach ZAKAT, tax valid certificates & valid international
SN Noted, valid certificated added
certifications.

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.