Walkdown comments of 14BAY01(Protection Panel For GT-14)

RFI No. 19K9-SCT-RFI-E10-0201 4/18/2024


Package. 14BAY01(Protection Panel For GT-14)
Desc.
Location GT-14 Electrical Building
S. No. Comment Description Category Remarks
Spare control cables heat shrinkable sleeves to be provided inside the Protection /Marshalling
1 panel.
C
2 Cable dressing inside the Trunks to be provided. C
3 13BBA01-0222C Cables ferrules to be changed ( as written site modification required ) after C
confirmation from Engineering team.
4 GT-14 Marshalling panel permanent KKS to be provided. C
5 GT-14 Marshalling panel missing panel bolts to be provided. C
6 14BAY01-0001C cable to be terminated as per latest Rev-3 interconnection schdule. C
7 General cleaning inside the Marshalling Panel work to be completed . C
8 Marshalling panel touch up paint . C
9 Spare conduit in the GCB side to be extended upto the the GCB with outdoor rated sealant. C
10 Inside the Mrashalling Panel general cable dressing work to be completed . C
11 Inside the Generator protection panel FOC Patch cords cables tags to be provided . C
12 Inside the Marshalling Panel/Protection panels some of the control cables ferrules are C
oversized ,need to be replaced as per cable size.
13 Cable route of the tray numbering is not matching with the schdule (actual ) on the site. C
Missing RFI to be attached of the system boundary and need to be confirmed cables are B
14 terminated as per latest interconnection drawing .