Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Al Ihsaa- Educational Complex in Al Jubail - UPDATE 04-06-2020 431 02-Mar-20 A 28-Jul-21 0.29% 28-Jul-21, Al Ihsaa- Educa

Milestones 431 02-Mar-20 A 28-Jul-21 0% 28-Jul-21, Milestones

General 431 02-Mar-20 A 28-Jul-21 0% 28-Jul-21, General


A17860 Project Start 0 02-Mar-20 A 100% Project Start, 02-Mar-20 A
A17870 Project Finish 0 28-Jul-21 0% Project Finish,
Construction 9 19-Jun-21 29-Jun-21 0% 29-Jun-21, Construction
A17890 Building A Finish 0 19-Jun-21 0% Building A Finish,
A17900 Building B Finish 0 19-Jun-21 0% Building B Finish,
A17910 Building C Finish 0 29-Jun-21 0% Building C Finish,
Submission & Approvals 347 04-Jun-20 20-Jul-21 0% 20-Jul-21, Submission & App

General 347 04-Jun-20 20-Jul-21 0% 20-Jul-21, General


A21930 Qulaity Plan Submission 7 04-Jun-20 11-Jun-20 0% Qulaity Plan Submission
A21940 Safety Plan Submission 7 04-Jun-20 11-Jun-20 0% Safety Plan Submission
A21950 Civil Defense Shop Drawing Submission 7 04-Jun-20 11-Jun-20 0% Civil Defense Shop Drawing Submission
A21980 Qulaity Plan Approval 14 13-Jun-20 28-Jun-20 0% Qulaity Plan Approval
A21990 Safety Plan Approval 14 13-Jun-20 28-Jun-20 0% Safety Plan Approval
A21960 Civil Defense Approval 13 13-Jun-20 27-Jun-20 0% Civil Defense Approval
A21970 As Built Drawings Submission 5 15-Jul-21 20-Jul-21 0% As Built Drawings Submissio
Engineering 45 04-Jun-20 26-Jul-20 0% 26-Jul-20, Engineering
Shop Drawings Submittal & Approval 45 04-Jun-20 26-Jul-20 0% 26-Jul-20, Shop Drawings Submittal & Approval
A20960 Structural & Civil Shop Drawings Submission 15 04-Jun-20 21-Jun-20 0% Structural & Civil Shop Drawings Submission
A20970 Architectural Shop Drawings Submission 15 04-Jun-20 21-Jun-20 0% Architectural Shop Drawings Submission
A20980 Plumping Shop Drawings Submission 15 04-Jun-20 21-Jun-20 0% Plumping Shop Drawings Submission
A20990 HVAC Shop Drawings Submission 15 04-Jun-20 21-Jun-20 0% HVAC Shop Drawings Submission
A21000 Electrical Shop Drawings Submission 15 04-Jun-20 21-Jun-20 0% Electrical Shop Drawings Submission
A20910 Structural & Civil Shop Drawings Approval 30 22-Jun-20 26-Jul-20 0% Structural & Civil Shop Drawings Approval
A20920 Architectural Shop Drawings Approval 30 22-Jun-20 26-Jul-20 0% Architectural Shop Drawings Approval
A20930 Plumping Shop Drawings Approval 30 22-Jun-20 26-Jul-20 0% Plumping Shop Drawings Approval
A20940 HVAC Shop Drawings Approval 30 22-Jun-20 26-Jul-20 0% HVAC Shop Drawings Approval
A20950 Electrical Shop Drawings Approval 30 22-Jun-20 26-Jul-20 0% Electrical Shop Drawings Approval
Procurement 248 22-Jun-20 13-Apr-21 0% 13-Apr-21, Procurement

Civil 193 22-Jun-20 08-Feb-21 0% 08-Feb-21, Civil


Concrete 40 22-Jun-20 12-Aug-20 0% 12-Aug-20, Concrete
A21020 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21030 P.O 5 08-Jul-20 13-Jul-20 0% P.O
A21040 Material Supplying 21 14-Jul-20 12-Aug-20 0% Material Supplying
Doors 188 22-Jun-20 02-Feb-21 0% 02-Feb-21, Doors
A21090 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21100 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21110 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21120 Materials Supplying 160 25-Jul-20 02-Feb-21 0% Materials Supplying
Windows 188 22-Jun-20 02-Feb-21 0% 02-Feb-21, Windows
A21370 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21380 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21390 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21400 Materials Supplying 160 25-Jul-20 02-Feb-21 0% Materials Supplying
Waterproofing 93 22-Jun-20 14-Oct-20 0% 14-Oct-20, Waterproofing
A21130 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21140 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21150 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21160 Materials Supplying 65 25-Jul-20 14-Oct-20 0% Materials Supplying
Floor finishing materials 193 22-Jun-20 08-Feb-21 0% 08-Feb-21, Floor finishing materials
A21170 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 1 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A21180 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21190 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21200 Materials Supplying 165 25-Jul-20 08-Feb-21 0% Materials Supplying
Wall finishing materials 193 22-Jun-20 08-Feb-21 0% 08-Feb-21, Wall finishing materials
A21450 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21460 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21470 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21480 Materials Supplying 165 25-Jul-20 08-Feb-21 0% Materials Supplying
Ceiling finishing materials 168 22-Jun-20 10-Jan-21 0% 10-Jan-21, Ceiling finishing materials
A21490 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21500 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21510 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21520 Materials Supplying 140 25-Jul-20 10-Jan-21 0% Materials Supplying
Mechanical 228 22-Jun-20 21-Mar-21 0% 21-Mar-21, Mechanical
Pipes 158 22-Jun-20 29-Dec-20 0% 29-Dec-20, Pipes
A21210 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21220 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21230 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21240 Materials Supplying 130 25-Jul-20 29-Dec-20 0% Materials Supplying
Pumps 178 22-Jun-20 21-Jan-21 0% 21-Jan-21, Pumps
A21530 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21540 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21550 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21560 Materials Supplying 150 25-Jul-20 21-Jan-21 0% Materials Supplying
Valves 193 22-Jun-20 08-Feb-21 0% 08-Feb-21, Valves
A21570 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21580 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21590 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21600 Materials Supplying 165 25-Jul-20 08-Feb-21 0% Materials Supplying
Tanks 198 22-Jun-20 14-Feb-21 0% 14-Feb-21, Tanks
A21610 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21620 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21630 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21640 Materials Supplying 170 25-Jul-20 14-Feb-21 0% Materials Supplying
Fire Hose Cabinet 228 22-Jun-20 21-Mar-21 0% 21-Mar-21, Fire Hose Cabinet
A21650 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21660 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21670 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21680 Materials Supplying 200 25-Jul-20 21-Mar-21 0% Materials Supplying
HVAC Duct & AC Units 198 22-Jun-20 14-Feb-21 0% 14-Feb-21, HVAC Duct & AC Units
A21690 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21700 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21710 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21720 Materials Supplying 170 25-Jul-20 14-Feb-21 0% Materials Supplying
Sanitary Fixtures 148 22-Jun-20 17-Dec-20 0% 17-Dec-20, Sanitary Fixtures
A21730 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21740 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21750 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21760 Materials Supplying 120 25-Jul-20 17-Dec-20 0% Materials Supplying
Electrical 248 22-Jun-20 13-Apr-21 0% 13-Apr-21, Electrical
Cables 178 22-Jun-20 21-Jan-21 0% 21-Jan-21, Cables
A21290 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21300 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21310 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21320 Materials Supplying 150 25-Jul-20 21-Jan-21 0% Materials Supplying

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 2 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Lighting Fixtures 248 22-Jun-20 13-Apr-21 0% 13-Apr-21, Lighting Fixtures
A21770 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21780 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21790 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21800 Materials Supplying 220 25-Jul-20 13-Apr-21 0% Materials Supplying
Panel boards 218 22-Jun-20 09-Mar-21 0% 09-Mar-21, Panel boards
A21330 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21340 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21350 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21360 Materials Supplying 190 25-Jul-20 09-Mar-21 0% Materials Supplying
Fire Alarm system 218 22-Jun-20 09-Mar-21 0% 09-Mar-21, Fire Alarm system
A21810 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21820 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21830 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21840 Materials Supplying 190 25-Jul-20 09-Mar-21 0% Materials Supplying
telphone & Data System 218 22-Jun-20 09-Mar-21 0% 09-Mar-21, telphone & Data System
A21850 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21860 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21870 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21880 Materials Supplying 190 25-Jul-20 09-Mar-21 0% Materials Supplying
Public address System 203 22-Jun-20 20-Feb-21 0% 20-Feb-21, Public address System
A21890 Vender Approval 14 22-Jun-20 07-Jul-20 0% Vender Approval
A21900 Material Approval 9 08-Jul-20 18-Jul-20 0% Material Approval
A21910 P.O 5 19-Jul-20 23-Jul-20 0% P.O
A21920 Materials Supplying 175 25-Jul-20 20-Feb-21 0% Materials Supplying
Construction Works 334 30-May-20 A 29-Jun-21 0.3% 29-Jun-21, Construction Works

Mobilization 5 27-Jul-20 06-Aug-20 0% 06-Aug-20, Mobilization


A18110 Preparation and processing for the start of work 5 27-Jul-20 06-Aug-20 0% Preparation and processing for the start of work
General Site Works ( A & B & C ) 201 27-Oct-20 19-Jun-21 0% 19-Jun-21, General Site Works ( A &
Civil Work 201 27-Oct-20 19-Jun-21 0% 19-Jun-21, Civil Work
Sub-Structure 43 27-Oct-20 16-Dec-20 0% 16-Dec-20, Sub-Structure
A22010 Boreholes surrounding the main building 5 27-Oct-20 02-Nov-20 0% Boreholes surrounding the main building
A22030 Excavation for fence foundation 5 02-Nov-20 08-Nov-20 0% Excavation for fence foundation
A22000 Soil termite treatment 2 08-Nov-20 10-Nov-20 0% Soil termite treatment
A22070 Slab on grade 9 10-Nov-20 21-Nov-20 0% Slab on grade
A22020 Backfilling 3 13-Dec-20 16-Dec-20 0% Backfilling
Super Structure 180 21-Nov-20 19-Jun-21 0% 19-Jun-21, Super Structure
Concrete work 36 21-Nov-20 02-Jan-21 0% 02-Jan-21, Concrete work
A22060 Necks 5 21-Nov-20 26-Nov-20 0% Necks
A22050 Beams 9 02-Dec-20 13-Dec-20 0% Beams
A18230 Columns 14 16-Dec-20 02-Jan-21 0% Columns
Paving 104 26-Jan-21 27-May-21 0% 27-May-21, Paving
A10300 Leveling Works 14 26-Jan-21 11-Feb-21 0% Leveling Works
A10350 Curbstone 21 11-Feb-21 08-Mar-21 0% Curbstone
A10360 Sand Works 3 08-Mar-21 11-Mar-21 0% Sand Works
A10320 Interlock Works 28 11-Mar-21 13-Apr-21 0% Interlock Works
A10330 Cement Til es Works 24 13-Apr-21 11-May-21 0% Cement Tiles Works
A10310 Artificial grass Installation for umbrellas 7 11-May-21 19-May-21 0% Artificial grass Installation for umbrellas
A10340 Precast Concrete Chairs & Baskets Work 7 19-May-21 27-May-21 0% Precast Concrete Chairs & Baskets Work
Finishing Works 175 26-Nov-20 19-Jun-21 0% 19-Jun-21, Finishing Works
A18260 Waterproofing works for substructure works 5 26-Nov-20 02-Dec-20 0% Waterproofing works for substructure works
A18240 Masonry works 21 02-Jan-21 26-Jan-21 0% Masonry works
A18120 Plastering works 21 26-Jan-21 20-Feb-21 0% Plastering works
A18250 Metal Works 28 20-Feb-21 24-Mar-21 0% Metal Works
A18160 External Painting (Profile) 14 02-Jun-21 19-Jun-21 0% External Painting (Profile)

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 3 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Mechanical Works 65 11-Feb-21 28-Apr-21 0% 28-Apr-21, Mechanical Works
Plumping 30 11-Feb-21 18-Mar-21 0% 18-Mar-21, Plumping
A10640 Connection to public water 7 11-Feb-21 20-Feb-21 0% Connection to public water
A10650 water valves 7 20-Feb-21 28-Feb-21 0% water valves
A10670 Manholes 7 28-Feb-21 08-Mar-21 0% Manholes
A10660 Sanitary & Waste pipe system 9 08-Mar-21 18-Mar-21 0% Sanitary & Waste pipe system
Fire 35 18-Mar-21 28-Apr-21 0% 28-Apr-21, Fire
A10630 Fire piping intsallation 14 18-Mar-21 04-Apr-21 0% Fire piping intsallation
A10620 Gate Valve including valve box 7 04-Apr-21 12-Apr-21 0% Gate Valve including valve box
A18270 Fire Hose Cabinet & Accessories 7 12-Apr-21 20-Apr-21 0% Fire Hose Cabinet & Accessories
A18280 Siamese pipe connection 7 20-Apr-21 28-Apr-21 0% Siamese pipe connection
Electrical Works 108 26-Jan-21 01-Jun-21 0% 01-Jun-21, Electrical Works
A22120 Lighting First Fix 24 26-Jan-21 23-Feb-21 0% Lighting First Fix
A22130 Lighting Second Fix 3 01-Apr-21 05-Apr-21 0% Lighting Second Fix
A22150 Cables installation 9 05-Apr-21 15-Apr-21 0% Cables installation
A22100 Inspection Chambers 7 15-Apr-21 24-Apr-21 0% Inspection Chambers
A22110 Board & Elec distribution system installation 30 24-Apr-21 29-May-21 0% Board & Elec distribution system installation
A22140 Lighting Third Fix 3 29-May-21 01-Jun-21 0% Lighting Third Fix
BUILDING (A) 333 30-May-20 A 28-Jun-21 0.46% 28-Jun-21, BUILDING (A)
Main Building (A) 333 30-May-20 A 28-Jun-21 0.56% 28-Jun-21, Main Building (A)
Civil Works 333 30-May-20 A 28-Jun-21 0.71% 28-Jun-21, Civil Works
Sub-Structure 5 08-Aug-20 12-Aug-20 0% 12-Aug-20, Sub-Structure
A18290 Remove of residues 5 08-Aug-20 12-Aug-20 0% Remove of residues
Super Structure 333 30-May-20 A 28-Jun-21 0.71% 28-Jun-21, Super Structure
Concrete Works 158 30-May-20 A 06-Dec-20 2.12% 06-Dec-20, Concrete Works
Supporting Works 117 30-May-20 A 19-Oct-20 5.16% 19-Oct-20, Supporting Works
A22200 Columns 21 30-May-20 A 13-Oct-20 15% Columns
A22280 Foundations 24 25-Aug-20 21-Sep-20 0% Foundations
A22190 Beams 5 13-Oct-20 19-Oct-20 0% Beams
Check and treatment 10 13-Aug-20 24-Aug-20 0% 24-Aug-20, Check and treatment
A22160 Checking 3 13-Aug-20 16-Aug-20 0% Checking
A22170 Treatments 7 17-Aug-20 24-Aug-20 0% Treatments
Casting Works 41 19-Oct-20 06-Dec-20 0% 06-Dec-20, Casting Works
A22300 Slab on grade 7 19-Oct-20 27-Oct-20 0% Slab on grade
A22270 Slabs & Beams 21 27-Oct-20 21-Nov-20 0% Slabs & Beams
A22260 Columns & Beams (parapet) 5 21-Nov-20 26-Nov-20 0% Columns & Beams (parapet)
A22310 Rambs 3 26-Nov-20 30-Nov-20 0% Rambs
A22290 Staircases and entrance 5 30-Nov-20 06-Dec-20 0% Staircases and entrance
Finishing Works 175 06-Dec-20 28-Jun-21 0% 28-Jun-21, Finishing Works
A11440 Masonry Works 21 06-Dec-20 30-Dec-20 0% Masonry Works
A11610 External Cement Plastering 18 30-Dec-20 20-Jan-21 0% External Cement Plastering
A11560 Internal Cement Plastering 24 20-Jan-21 17-Feb-21 0% Internal Cement Plastering
A22650 Roof sandwich panels 26 20-Jan-21 20-Feb-21 0% Roof sandwich panels
A11640 Gypsum board 9 17-Feb-21 28-Feb-21 0% Gypsum board
A22660 Ceiling Tile s 24 20-Feb-21 20-Mar-21 0% Ceiling Tile s
A11480 Waterproofing for Bathroom & Kitchen 5 28-Feb-21 06-Mar-21 0% Waterproofing for Bathroom & Kitchen
A22450 Tiles for Walls 14 06-Mar-21 22-Mar-21 0% Tiles for Walls
A22640 Roof finishes 28 20-Mar-21 21-Apr-21 0% Roof finishes
A11460 Handrail & Protections 14 22-Mar-21 07-Apr-21 0% Handrail & Protections
A11630 Aluminium strip 5 22-Mar-21 28-Mar-21 0% Aluminium strip
A11700 Specialies 9 22-Mar-21 01-Apr-21 0% Specialies
A11570 Internal Painting Works (Primer + Filler + 1st Coat) 21 28-Mar-21 21-Apr-21 0% Internal Painting Works (Primer + Filler + 1st Coat)
A11520 Floor Finish (tiling & scerting) 30 21-Apr-21 26-May-21 0% Floor Finish (tiling & scerting)
A11500 Doors 21 26-May-21 20-Jun-21 0% Doors
A11510 Windows 28 26-May-21 28-Jun-21 0% Windows

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 4 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A11620 External Painting works 7 26-May-21 03-Jun-21 0% External Painting works
A11660 Counters 7 26-May-21 03-Jun-21 0% Counters
A22440 Painting Works (Final Coat) 10 03-Jun-21 15-Jun-21 0% Painting Works (Final Coat)
Mechanical Works 106 23-Feb-21 26-Jun-21 0% 26-Jun-21, Mechanical Works
Plumbing 80 24-Mar-21 26-Jun-21 0% 26-Jun-21, Plumbing
A10980 Domestic Water Supply System 14 24-Mar-21 10-Apr-21 0% Domestic Water Supply System
A10990 Isolation valve 3 10-Apr-21 13-Apr-21 0% Isolation valve
A11000 Electric Water Heaters 5 21-Apr-21 27-Apr-21 0% Electric Water Heaters
A11930 Water Storage Tanks 5 27-Apr-21 03-May-21 0% Water Storage Tanks
A11940 Sanitary System 11 03-May-21 16-May-21 0% Sanitary System
A11950 Roof Scupper Drain 3 16-May-21 19-May-21 0% Roof Scupper Drain
A11960 Plumbing Fixtures 9 15-Jun-21 26-Jun-21 0% Plumbing Fixtures
Fire Fighting 35 30-Mar-21 10-May-21 0% 10-May-21, Fire Fighting
A11010 Piping 21 30-Mar-21 24-Apr-21 0% Piping
A11020 Fire Hose Cabinet & Accessories 9 24-Apr-21 04-May-21 0% Fire Hose Cabinet & Accessories
A18300 fire extinguisher 5 04-May-21 10-May-21 0% fire extinguisher
HVAC 80 23-Feb-21 26-May-21 0% 26-May-21, HVAC
A10970 HVAC Ducts and Casings 14 23-Feb-21 10-Mar-21 0% HVAC Ducts and Casings
A10960 General Exhaust Fan 9 11-Mar-21 21-Mar-21 0% General Exhaust Fan
A11150 Air Curtain 5 22-Mar-21 27-Mar-21 0% Air Curtain
A10950 DX-Split wall mounted type air conditioning units 21 21-Apr-21 16-May-21 0% DX-Split wall mounted type air conditioning uni
A18310 Dx - Split units 9 16-May-21 26-May-21 0% Dx - Split units
Electrical Works 123 30-Dec-20 23-May-21 0% 23-May-21, Electrical Works
Electrical 123 30-Dec-20 23-May-21 0% 23-May-21, Electrical
A12050 Conductors and cables 21 30-Dec-20 24-Jan-21 0% Conductors and cables
A12010 Lighting System First Fix (Conduits) 14 24-Jan-21 09-Feb-21 0% Lighting System First Fix (Conduits)
A22320 Lighting System Second Fix (Wires) 14 17-Feb-21 06-Mar-21 0% Lighting System Second Fix (Wires)
A12020 Power Installation 9 06-Mar-21 16-Mar-21 0% Power Installation
A11990 Panel Boards 7 18-Mar-21 25-Mar-21 0% Panel Boards
A12070 Lightening Protection System 7 27-Mar-21 03-Apr-21 0% Lightening Protection System
A12060 Earthing system 7 04-Apr-21 11-Apr-21 0% Earthing system
A12030 Bells system 5 12-Apr-21 17-Apr-21 0% Bells system
A12040 Sockets & Switches 11 21-Apr-21 04-May-21 0% Sockets & Switches
A22330 Lighting System Third Fix (Fixtures) 14 06-May-21 23-May-21 0% Lighting System Third Fix (Fixtures)
Communications 58 24-Jan-21 01-Apr-21 0% 01-Apr-21, Communications
A12080 Telephone & Data Communication System First Fix 14 24-Jan-21 09-Feb-21 0% Telephone & Data Communication System First Fix
A12120 Fire Ala rm System First Fix 20 24-Jan-21 16-Feb-21 0% Fire Ala rm System First Fix
A22340 Fire Ala rm System Second Fix 14 17-Feb-21 06-Mar-21 0% Fire Ala rm System Second Fix
A22360 Telephone & Data Communication System Second Fix 14 17-Feb-21 06-Mar-21 0% Telephone & Data Communication System Second Fix
A12110 Public Address system 14 06-Mar-21 22-Mar-21 0% Public Address system
A22350 Fire Ala rm System Third Fix 9 18-Mar-21 28-Mar-21 0% Fire Ala rm System Third Fix
A22370 Telephone & Data Communication System Third Fix 9 22-Mar-21 01-Apr-21 0% Telephone & Data Communication System Third Fix
Canteen (A) 114 11-Feb-21 23-Jun-21 0% 23-Jun-21, Canteen (A)
Civil Works 114 11-Feb-21 23-Jun-21 0% 23-Jun-21, Civil Works
Sub-Structure 34 11-Feb-21 22-Mar-21 0% 22-Mar-21, Sub-Structure
A19140 Excavation for foundation 3 11-Feb-21 14-Feb-21 0% Excavation for foundation
A19150 Soil termite treatment 2 15-Feb-21 16-Feb-21 0% Soil termite treatment
A22380 PCC 2 17-Feb-21 18-Feb-21 0% PCC
A22390 Footing 3 20-Feb-21 22-Feb-21 0% Footing
A22410 Neck Column 5 23-Feb-21 28-Feb-21 0% Neck Column
A19190 bitumen paint 2 01-Mar-21 02-Mar-21 0% bitumen paint
A22430 Grade Beam 5 03-Mar-21 08-Mar-21 0% Grade Beam
A22400 Slab on grade 9 09-Mar-21 18-Mar-21 0% Slab on grade
A19160 Backfilling 3 20-Mar-21 22-Mar-21 0% Backfilling
Super Structure 80 23-Mar-21 23-Jun-21 0% 23-Jun-21, Super Structure

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 5 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Concrete Works 28 23-Mar-21 24-Apr-21 0% 24-Apr-21, Concrete Works
A22420 Column 7 23-Mar-21 30-Mar-21 0% Column
A19170 Beams 7 31-Mar-21 07-Apr-21 0% Beams
A19180 Slabs 14 08-Apr-21 24-Apr-21 0% Slabs
Finishing Works 52 25-Apr-21 23-Jun-21 0% 23-Jun-21, Finishing Works
A22670 Masonry Works 14 25-Apr-21 10-May-21 0% Masonry Works
A22730 Internal Cement Plastering 5 11-May-21 16-May-21 0% Internal Cement Plastering
A22690 Waterproofing for Bathroom & Kitchen 3 17-May-21 19-May-21 0% Waterproofing for Bathroom & Kitchen
A22750 External Cement Plastering 7 17-May-21 24-May-21 0% External Cement Plastering
A22780 Gypsum board 5 17-May-21 22-May-21 0% Gypsum board
A22820 Tiles for Walls 3 20-May-21 23-May-21 0% Tiles for Walls
A22830 Roof finishes 7 25-May-21 01-Jun-21 0% Roof finishes
A22720 Floor tiling 3 02-Jun-21 05-Jun-21 0% Floor tiling
A22700 Doors 5 06-Jun-21 10-Jun-21 0% Doors
A22710 Windows 5 06-Jun-21 10-Jun-21 0% Windows
A22790 Counters 5 06-Jun-21 10-Jun-21 0% Counters
A22760 Painting works 7 16-Jun-21 23-Jun-21 0% Painting works
Mechanical Works 31 11-May-21 15-Jun-21 0% 15-Jun-21, Mechanical Works
Plumbing 31 11-May-21 15-Jun-21 0% 15-Jun-21, Plumbing
A13320 Domestic Water Supply System 3 11-May-21 13-May-21 0% Domestic Water Supply System
A14180 Sanitary Waste Piping Specialties 3 11-May-21 13-May-21 0% Sanitary Waste Piping Specialties
A14150 Sanitary System 5 15-May-21 19-May-21 0% Sanitary System
A14160 Roof Scupper Drain 4 20-May-21 24-May-21 0% Roof Scupper Drain
A13340 Electric Water Heaters 3 06-Jun-21 08-Jun-21 0% Electric Water Heaters
A14170 Plumbing Fixtures 4 12-Jun-21 15-Jun-21 0% Plumbing Fixtures
Fire Fighting 3 12-Jun-21 14-Jun-21 0% 14-Jun-21, Fire Fighting
A13350 fire extinguisher 3 12-Jun-21 14-Jun-21 0% fire extinguisher
HVAC 4 17-May-21 20-May-21 0% 20-May-21, HVAC
A13300 General Exhaust Fan 1 17-May-21 17-May-21 0% General Exhaust Fan
A13290 DX-Split wall mounted type air conditioning units 3 18-May-21 20-May-21 0% DX-Split wall mounted type air conditioning un
Electrical Works 16 11-May-21 29-May-21 0% 29-May-21, Electrical Works
Electrical Power 16 11-May-21 29-May-21 0% 29-May-21, Electrical Power
A22840 Lighting System First Fix (Conduits) 5 11-May-21 16-May-21 0% Lighting System First Fix (Conduits)
A14260 Conductors and cables 7 17-May-21 24-May-21 0% Conductors and cables
A22850 Lighting System Second Fix (Wires) 2 17-May-21 18-May-21 0% Lighting System Second Fix (Wires)
A14200 Power and Lighting panel 3 19-May-21 22-May-21 0% Power and Lighting panel
A14250 Disconnect Switches 2 23-May-21 24-May-21 0% Disconnect Switches
A14230 Power Installation 2 25-May-21 26-May-21 0% Power Installation
A22860 Lighting System Third Fix (Fixtures) 2 27-May-21 29-May-21 0% Lighting System Third Fix (Fixtures)
Communications 8 17-May-21 25-May-21 0% 25-May-21, Communications
A22870 Telephone & Data Communication System First Fix 4 17-May-21 20-May-21 0% Telephone & Data Communication System Fi
A22880 Fire Ala rm System First Fix 4 17-May-21 20-May-21 0% Fire Ala rm System First Fix
A22890 Fire Ala rm System Second Fix 2 22-May-21 23-May-21 0% Fire Ala rm System Second Fix
A22910 Telephone & Data Communication System Second Fix 2 22-May-21 23-May-21 0% Telephone & Data Communication System S
A22900 Fire Ala rm System Third Fix 2 24-May-21 25-May-21 0% Fire Ala rm System Third Fix
A22920 Telephone & Data Communication System Third Fix 2 24-May-21 25-May-21 0% Telephone & Data Communication System T
Guard House ( A ) 218 17-Sep-20 30-May-21 0% 30-May-21, Guard House ( A )
Civil Works 218 17-Sep-20 30-May-21 0% 30-May-21, Civil Works
Sub-Structure 22 17-Sep-20 13-Oct-20 0% 13-Oct-20, Sub-Structure
A23610 Excavation for foundation 2 17-Sep-20 19-Sep-20 0% Excavation for foundation
A23630 Soil termite treatment 2 20-Sep-20 21-Sep-20 0% Soil termite treatment
A23650 PCC 2 22-Sep-20 24-Sep-20 0% PCC
A23660 Footing 5 26-Sep-20 30-Sep-20 0% Footing
A23680 Neck Column 3 01-Oct-20 04-Oct-20 0% Neck Column
A23690 Grade Beam 3 05-Oct-20 07-Oct-20 0% Grade Beam

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 6 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A23670 Slab on grade 3 08-Oct-20 11-Oct-20 0% Slab on grade
A23620 Backfilling 2 12-Oct-20 13-Oct-20 0% Backfilling
Super Structure 196 14-Oct-20 30-May-21 0% 30-May-21, Super Structure
Concrete Works 51 14-Oct-20 12-Dec-20 0% 12-Dec-20, Concrete Works
A23720 Column 21 14-Oct-20 07-Nov-20 0% Column
A23700 Beams 9 08-Nov-20 17-Nov-20 0% Beams
A23710 Slabs 21 18-Nov-20 12-Dec-20 0% Slabs
Finishing Works 145 13-Dec-20 30-May-21 0% 30-May-21, Finishing Works
A23010 Masonry Works 5 13-Dec-20 17-Dec-20 0% Masonry Works
A23090 External Cement Plastering 5 19-Dec-20 23-Dec-20 0% External Cement Plastering
A23070 Internal Cement Plastering 5 24-Dec-20 29-Dec-20 0% Internal Cement Plastering
A23110 Aluminium strip 7 24-Dec-20 31-Dec-20 0% Aluminium strip
A23030 Waterproofing for Bathroom & Kitchen 7 30-Dec-20 06-Jan-21 0% Waterproofing for Bathroom & Kitchen
A23580 Roof finishes 5 20-Jan-21 25-Jan-21 0% Roof finishes
A23570 Tiles for Walls 17 26-Jan-21 14-Feb-21 0% Tiles for Walls
A23390 Specialies 4 15-Feb-21 18-Feb-21 0% Specialies
A23040 Doors 21 20-Feb-21 15-Mar-21 0% Doors
A23050 Windows 28 20-Feb-21 23-Mar-21 0% Windows
A23130 Counters 7 20-Feb-21 27-Feb-21 0% Counters
A23060 Floor Finish (tiling & scerting) 17 12-Apr-21 01-May-21 0% Floor Finish (tiling & scerting)
A23100 Painting works 11 18-May-21 30-May-21 0% Painting works
Mechanical Works 129 19-Dec-20 17-May-21 0% 17-May-21, Mechanical Works
A22960 Domestic Water Supply System 14 19-Dec-20 03-Jan-21 0% Domestic Water Supply System
A26490 Sanitary Specialties 14 19-Dec-20 03-Jan-21 0% Sanitary Specialties
A23150 Sanitary System 11 04-Jan-21 16-Jan-21 0% Sanitary System
A23160 Roof Scupper Drain 3 17-Jan-21 19-Jan-21 0% Roof Scupper Drain
A22940 General Exhaust Fan 9 28-Feb-21 09-Mar-21 0% General Exhaust Fan
A22930 DX-Split Units 28 10-Mar-21 11-Apr-21 0% DX-Split Units
A22980 Electric Water Heaters 14 02-May-21 17-May-21 0% Electric Water Heaters
A23170 Plumbing Fixtures 14 02-May-21 17-May-21 0% Plumbing Fixtures
A23370 fire extinguisher 14 02-May-21 17-May-21 0% fire extinguisher
Electrical Works 76 09-Feb-21 08-May-21 0% 08-May-21, Electrical Works
Electrical 76 09-Feb-21 08-May-21 0% 08-May-21, Electrical
A23220 Lighting System First Fix (Conduits) 14 09-Feb-21 24-Feb-21 0% Lighting System First Fix (Conduits)
A23500 Lighting System Second Fix (Wires) 14 25-Feb-21 13-Mar-21 0% Lighting System Second Fix (Wires)
A23260 Conductors and cables 16 15-Mar-21 01-Apr-21 0% Conductors and cables
A23200 Panel Boards 14 18-Mar-21 03-Apr-21 0% Panel Boards
A23230 Power Installation 9 03-Apr-21 12-Apr-21 0% Power Installation
A23250 Sockets & Switches 14 04-Apr-21 19-Apr-21 0% Sockets & Switches
A23510 Lighting System Third Fix (Fixtures) 14 22-Apr-21 08-May-21 0% Lighting System Third Fix (Fixtures)
Communications 54 09-Feb-21 12-Apr-21 0% 12-Apr-21, Communications
A23290 Telephone & Data Communication System First Fix 24 09-Feb-21 08-Mar-21 0% Telephone & Data Communication System First Fix
A23330 Fire Ala rm System First Fix 24 09-Feb-21 08-Mar-21 0% Fire Ala rm System First Fix
A23520 Fire Ala rm System Second Fix 15 09-Mar-21 25-Mar-21 0% Fire Ala rm System Second Fix
A23540 Telephone & Data Communication System Second Fix 15 09-Mar-21 25-Mar-21 0% Telephone & Data Communication System Second Fix
A23530 Fire Ala rm System Third Fix 15 27-Mar-21 12-Apr-21 0% Fire Ala rm System Third Fix
A23550 Telephone & Data Communication System Third Fix 15 27-Mar-21 12-Apr-21 0% Telephone & Data Communication System Third Fix
Electrical Room (A) 200 30-Sep-20 20-May-21 0% 20-May-21, Electrical Room (A)
Civil Works 200 30-Sep-20 20-May-21 0% 20-May-21, Civil Works
Sub-Structure 58 30-Sep-20 06-Dec-20 0% 06-Dec-20, Sub-Structure
A24300 Excavation for foundation 5 30-Sep-20 05-Oct-20 0% Excavation for foundation
A24320 Soil termite treatment 2 06-Oct-20 07-Oct-20 0% Soil termite treatment
A24340 PCC 9 08-Oct-20 18-Oct-20 0% PCC
A24350 Footing 9 19-Oct-20 28-Oct-20 0% Footing
A24370 Neck Column 9 29-Oct-20 08-Nov-20 0% Neck Column

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 7 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A24380 Grade Beam 9 09-Nov-20 18-Nov-20 0% Grade Beam
A24330 bitumen paint 3 19-Nov-20 22-Nov-20 0% bitumen paint
A24360 Slab on grade 9 23-Nov-20 02-Dec-20 0% Slab on grade
A24310 Backfilling 3 03-Dec-20 06-Dec-20 0% Backfilling
Super Structure 142 07-Dec-20 20-May-21 0% 20-May-21, Super Structure
Concrete Works 51 07-Dec-20 03-Feb-21 0% 03-Feb-21, Concrete Works
A24410 Column 21 07-Dec-20 30-Dec-20 0% Column
A24390 Beams 9 31-Dec-20 10-Jan-21 0% Beams
A24400 Slabs 21 11-Jan-21 03-Feb-21 0% Slabs
Finishing Works 91 04-Feb-21 20-May-21 0% 20-May-21, Finishing Works
A23810 Masonry Works 14 04-Feb-21 20-Feb-21 0% Masonry Works
A23870 Cement Plastering 28 21-Feb-21 24-Mar-21 0% Cement Plastering
A23840 Doors 14 25-Mar-21 10-Apr-21 0% Doors
A23850 Windows 14 25-Mar-21 10-Apr-21 0% Windows
A24270 Roof finishes 14 25-Mar-21 10-Apr-21 0% Roof finishes
A23860 Floor finish (concrete screed & epoxy) 17 11-Apr-21 29-Apr-21 0% Floor finish (concrete screed & epoxy)
A23900 Painting works 11 09-May-21 20-May-21 0% Painting works
Mechanical Works 30 25-Mar-21 28-Apr-21 0% 28-Apr-21, Mechanical Works
A23740 General Exhaust Fan 12 25-Mar-21 07-Apr-21 0% General Exhaust Fan
A23960 Gargouri drainage 9 08-Apr-21 18-Apr-21 0% Gargouri drainage
A24160 fire extinguisher 9 19-Apr-21 28-Apr-21 0% fire extinguisher
Electrical Works 66 21-Feb-21 08-May-21 0% 08-May-21, Electrical Works
A24020 Lighting System First Fix (Conduits) 24 21-Feb-21 20-Mar-21 0% Lighting System First Fix (Conduits)
A24130 Fire Ala rm System First Fix 24 27-Feb-21 25-Mar-21 0% Fire Ala rm System First Fix
A24060 Conductors and cables 12 21-Mar-21 03-Apr-21 0% Conductors and cables
A24190 Lighting System Second Fix (Wires) 14 21-Mar-21 05-Apr-21 0% Lighting System Second Fix (Wires)
A24210 Fire Ala rm System Second Fix 15 27-Mar-21 12-Apr-21 0% Fire Ala rm System Second Fix
A24030 Power Installation 9 04-Apr-21 13-Apr-21 0% Power Installation
A24000 Panel Boards 7 06-Apr-21 13-Apr-21 0% Panel Boards
A24070 Earthing system 7 06-Apr-21 13-Apr-21 0% Earthing system
A24220 Fire Ala rm System Third Fix 15 13-Apr-21 29-Apr-21 0% Fire Alarm System Third Fix
A24200 Lighting System Third Fix (Fixtures) 14 22-Apr-21 08-May-21 0% Lighting System Third Fix (Fixtures)
Gate (A & B) 218 12-Sep-20 24-May-21 0% 24-May-21, Gate (A & B)
Civil Works 218 12-Sep-20 24-May-21 0% 24-May-21, Civil Works
Sub-Structure 58 12-Sep-20 18-Nov-20 0% 18-Nov-20, Sub-Structure
A24990 Excavation for foundation 5 12-Sep-20 16-Sep-20 0% Excavation for foundation
A25010 Soil termite treatment 2 17-Sep-20 19-Sep-20 0% Soil termite treatment
A25030 PCC 9 20-Sep-20 30-Sep-20 0% PCC
A25040 Footing 9 01-Oct-20 11-Oct-20 0% Footing
A25060 Neck Column 9 12-Oct-20 21-Oct-20 0% Neck Column
A25070 Grade Beam 9 22-Oct-20 01-Nov-20 0% Grade Beam
A25020 bitumen paint 3 02-Nov-20 04-Nov-20 0% bitumen paint
A25050 Slab on grade 9 05-Nov-20 15-Nov-20 0% Slab on grade
A30060 Backfilling 3 16-Nov-20 18-Nov-20 0% Backfilling
Super Structure 160 19-Nov-20 24-May-21 0% 24-May-21, Super Structure
Concrete Works 51 19-Nov-20 17-Jan-21 0% 17-Jan-21, Concrete Works
A25100 Column 21 19-Nov-20 13-Dec-20 0% Column
A25080 Beams 9 14-Dec-20 23-Dec-20 0% Beams
A25090 Slabs 21 24-Dec-20 17-Jan-21 0% Slabs
Finishing Works 109 18-Jan-21 24-May-21 0% 24-May-21, Finishing Works
A24500 Masonry Works 18 18-Jan-21 07-Feb-21 0% Masonry Works
A24560 Cement Plastering 14 08-Feb-21 23-Feb-21 0% Cement Plastering
A24520 Waterproofing for Bathroom & Kitchen 7 24-Feb-21 03-Mar-21 0% Waterproofing for Bathroom & Kitchen
A24960 Roof finishes 21 24-Feb-21 20-Mar-21 0% Roof finishes
A24950 Tiles for Walls 17 04-Mar-21 23-Mar-21 0% Tiles for Walls

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 8 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A24600 Aluminium strip 7 21-Mar-21 28-Mar-21 0% Aluminium strip
A24870 Specialies 4 24-Mar-21 28-Mar-21 0% Specialies
A24550 Floor Finish (tiling & scerting) 17 29-Mar-21 17-Apr-21 0% Floor Finish (tiling & scerting)
A24510 Handrail & Protections 14 18-Apr-21 03-May-21 0% Handrail & Protections
A24530 Doors 7 18-Apr-21 25-Apr-21 0% Doors
A24540 Windows 7 18-Apr-21 25-Apr-21 0% Windows
A24970 External metal shades 14 18-Apr-21 03-May-21 0% External metal shades
A24590 Painting works 11 12-May-21 24-May-21 0% Painting works
Mechanical Works 80 08-Feb-21 11-May-21 0% 11-May-21, Mechanical Works
A24450 Domestic Water Supply System 14 08-Feb-21 23-Feb-21 0% Domestic Water Supply System
A24640 Sanitary System 11 24-Feb-21 08-Mar-21 0% Sanitary System
A26500 Sanitary Specialties 9 09-Mar-21 18-Mar-21 0% Sanitary Specialties
A24430 General Exhaust Fan 9 18-Apr-21 27-Apr-21 0% General Exhaust Fan
A24660 Plumbing Fixtures 12 18-Apr-21 01-May-21 0% Plumbing Fixtures
A24420 DX-Split units 7 28-Apr-21 05-May-21 0% DX-Split units
A24470 Electric Water Heaters 5 04-May-21 09-May-21 0% Electric Water Heaters
A24850 fire extinguisher 7 04-May-21 11-May-21 0% fire extinguisher
Electrical Works 77 08-Feb-21 08-May-21 0% 08-May-21, Electrical Works
Electrical 77 08-Feb-21 08-May-21 0% 08-May-21, Electrical
A24710 Lighting System First Fix (Conduits) 14 08-Feb-21 23-Feb-21 0% Lighting System First Fix (Conduits)
A24750 Conductors and cables 15 24-Feb-21 13-Mar-21 0% Conductors and cables
A24880 Lighting System Second Fix (Wires) 15 24-Feb-21 13-Mar-21 0% Lighting System Second Fix (Wires)
A24690 Panel Boards 14 18-Mar-21 03-Apr-21 0% Panel Boards
A24720 Power Installation 15 31-Mar-21 17-Apr-21 0% Power Installation
A24740 Sockets & Switches 12 04-Apr-21 17-Apr-21 0% Sockets & Switches
A24890 Lighting System Third Fix (Fixtures) 14 22-Apr-21 08-May-21 0% Lighting System Third Fix (Fixtures)
Communications 54 08-Feb-21 11-Apr-21 0% 11-Apr-21, Communications
A24780 Telephone & Data Communication System First Fix 24 08-Feb-21 07-Mar-21 0% Telephone & Data Communication System First Fix
A24820 Fire Ala rm System First Fix 24 08-Feb-21 07-Mar-21 0% Fire Ala rm System First Fix
A24900 Fire Ala rm System Second Fix 15 08-Mar-21 24-Mar-21 0% Fire Ala rm System Second Fix
A24920 Telephone & Data Communication System Second Fix 15 08-Mar-21 24-Mar-21 0% Telephone & Data Communication System Second Fix
A24810 Public Address system 15 25-Mar-21 11-Apr-21 0% Public Address system
A24910 Fire Ala rm System Third Fix 15 25-Mar-21 11-Apr-21 0% Fire Ala rm System Third Fix
A24930 Telephone & Data Communication System Third Fix 15 25-Mar-21 11-Apr-21 0% Telephone & Data Communication System Third Fix
Water Tank & Pump Room (A) 142 30-Dec-20 14-Jun-21 0% 14-Jun-21, Water Tank & Pump Room
Civil Works 125 30-Dec-20 25-May-21 0% 25-May-21, Civil Works
A25680 Excavation 5 30-Dec-20 05-Jan-21 0% Excavation
A25700 Soil termite treatment 2 05-Jan-21 07-Jan-21 0% Soil termite treatment
A25720 PCC 9 07-Jan-21 18-Jan-21 0% PCC
A25730 Footing 9 18-Jan-21 28-Jan-21 0% Footing
A25790 Wall 21 28-Jan-21 22-Feb-21 0% Wall
A25210 Waterproofing membrane 7 22-Feb-21 02-Mar-21 0% Waterproofing membrane
A25190 Masonry Works 4 02-Mar-21 07-Mar-21 0% Masonry Works
A25690 Backfilling 3 07-Mar-21 10-Mar-21 0% Backfilling
A25780 Slab 21 10-Mar-21 04-Apr-21 0% Slab
A25770 Pumps foundation 9 04-Apr-21 14-Apr-21 0% Pumps foundation
A25200 Cover & Ladder 14 14-Apr-21 01-May-21 0% Cover & Ladder
A26510 Pump Room 14 14-Apr-21 01-May-21 0% Pump Room
A25250 Waterproof cement plaster 14 01-May-21 17-May-21 0% Waterproof cement plaster
A26520 Waterproofing Epoxy 7 17-May-21 25-May-21 0% Waterproofing Epoxy
Mechanical Works 8 22-May-21 31-May-21 0% 31-May-21, Mechanical Works
A25150 Piping & Valves 3 22-May-21 25-May-21 0% Piping & Valves
A25180 Fire Pump 5 25-May-21 31-May-21 0% Fire Pump
A25320 Water Transfer Pumps 5 25-May-21 31-May-21 0% Water Transfer Pumps
Electrical Works 12 31-May-21 14-Jun-21 0% 14-Jun-21, Electrical Works

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 9 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A25430 Sockets & Switches 12 31-May-21 14-Jun-21 0% Sockets & Switches
BUILDING (B) 312 30-May-20 A 03-Jun-21 0.71% 03-Jun-21, BUILDING (B)
Main Building (B) 301 30-May-20 A 22-May-21 0.74% 22-May-21, Main Building (B)
Civil Works 301 30-May-20 A 22-May-21 1.05% 22-May-21, Civil Works
Sub-Structure 7 12-Sep-20 19-Sep-20 0% 19-Sep-20, Sub-Structure
A26960 Remove of residues 7 12-Sep-20 19-Sep-20 0% Remove of residues
Super Structure 301 30-May-20 A 22-May-21 1.06% 22-May-21, Super Structure
Concrete Works 70 20-Sep-20 10-Dec-20 0% 10-Dec-20, Concrete Works
Supporting Works 42 15-Oct-20 02-Dec-20 0% 02-Dec-20, Supporting Works
A27060 Foundations 21 15-Oct-20 08-Nov-20 0% Foundations
A27020 Beams 7 09-Nov-20 16-Nov-20 0% Beams
A27030 Columns 14 17-Nov-20 02-Dec-20 0% Columns
Check and treatment 21 20-Sep-20 14-Oct-20 0% 14-Oct-20, Check and treatment
A27000 Checking 7 20-Sep-20 28-Sep-20 0% Checking
A27010 Treatments 14 29-Sep-20 14-Oct-20 0% Treatments
Casting Works 7 03-Dec-20 10-Dec-20 0% 10-Dec-20, Casting Works
A27090 Rambs 7 03-Dec-20 10-Dec-20 0% Rambs
Finishing Works 301 30-May-20 A 22-May-21 1.66% 22-May-21, Finishing Works
A26630 Waterproofing (check & treatment) 14 30-May-20 A 13-Feb-21 35% Waterproofing (check & treatment)
A26610 Masonry Works 24 12-Dec-20 07-Jan-21 0% Masonry Works
A26670 Internal Cement Plastering 21 09-Jan-21 01-Feb-21 0% Internal Cement Plastering
A26720 Gypsum board 14 13-Feb-21 01-Mar-21 0% Gypsum board
A26660 Floor finish (check & treatment) 23 17-Feb-21 15-Mar-21 0% Floor finish (check & treatment)
A27170 Tiles for Walls 9 01-Mar-21 11-Mar-21 0% Tiles for Walls
A27200 Ceiling Tile s 9 01-Mar-21 11-Mar-21 0% Ceiling Tile s
A26990 Specialies 9 11-Mar-21 22-Mar-21 0% Specialies
A26620 Handrail & Protections 14 16-Mar-21 31-Mar-21 0% Handrail & Protections
A26710 Aluminium strip 12 01-Apr-21 14-Apr-21 0% Aluminium strip
A26680 Internal Painting Works (Primer + Filler + 1st Coat) 14 03-Apr-21 18-Apr-21 0% Internal Painting Works (Primer + Filler + 1st Coat)
A26700 External Painting works 21 15-Apr-21 09-May-21 0% External Painting works
A26640 Doors 18 19-Apr-21 09-May-21 0% Doors
A26650 Windows 20 19-Apr-21 11-May-21 0% Windows
A26730 Counters 7 19-Apr-21 26-Apr-21 0% Counters
A27160 Painting Works (Final Coat) 9 12-May-21 22-May-21 0% Painting Works (Final Coat)
Mechanical Works 104 09-Jan-21 09-May-21 0% 09-May-21, Mechanical Works
Plumbing 104 09-Jan-21 09-May-21 0% 09-May-21, Plumbing
A26560 Domestic Water Supply System 15 09-Jan-21 25-Jan-21 0% Domestic Water Supply System
A26750 Sanitary System 7 26-Jan-21 02-Feb-21 0% Sanitary System
A26760 Roof Scupper Drain 8 03-Feb-21 11-Feb-21 0% Roof Scupper Drain
A26570 Isolation valve 7 17-Feb-21 24-Feb-21 0% Isolation valve
A26740 Water Storage Tanks 14 25-Feb-21 13-Mar-21 0% Water Storage Tanks
A26770 Plumbing Fixtures 17 14-Mar-21 01-Apr-21 0% Plumbing Fixtures
A26580 Electric Water Heaters 11 27-Apr-21 09-May-21 0% Electric Water Heaters
Fire Fighting 102 09-Jan-21 06-May-21 0% 06-May-21, Fire Fighting
A26590 Piping 24 09-Jan-21 04-Feb-21 0% Piping
A26600 Fire Hose Cabinet & Accessories 9 19-Apr-21 28-Apr-21 0% Fire Hose Cabinet & Accessories
A26970 fire extinguisher 7 29-Apr-21 06-May-21 0% fire extinguisher
HVAC 45 27-Feb-21 19-Apr-21 0% 19-Apr-21, HVAC
A26550 HVAC Ducts and Casings 9 27-Feb-21 08-Mar-21 0% HVAC Ducts and Casings
A26540 General Exhaust Fan 9 09-Mar-21 18-Mar-21 0% General Exhaust Fan
A26530 DX-Split units 24 20-Mar-21 15-Apr-21 0% DX-Split units
A26950 Air Curtain 3 17-Apr-21 19-Apr-21 0% Air Curtain
Electrical Works 103 09-Jan-21 08-May-21 0% 08-May-21, Electrical Works
Electrical 103 09-Jan-21 08-May-21 0% 08-May-21, Electrical
A26820 Lighting System First Fix (Conduits) 21 09-Jan-21 01-Feb-21 0% Lighting System First Fix (Conduits)

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 10 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A27100 Lighting System Second Fix (Wires) 21 02-Feb-21 25-Feb-21 0% Lighting System Second Fix (Wires)
A27210 Remove Pre-Installed Electrical Works 24 02-Feb-21 01-Mar-21 0% Remove Pre-Installed Electrical Works
A26860 Conductors and cables 24 02-Mar-21 29-Mar-21 0% Conductors and cables
A26800 Panel Boards 14 18-Mar-21 03-Apr-21 0% Panel Boards
A26840 Bells system 14 18-Mar-21 03-Apr-21 0% Bells system
A26850 Sockets & Switches 24 18-Mar-21 14-Apr-21 0% Sockets & Switches
A26870 Earthing system 14 18-Mar-21 03-Apr-21 0% Earthing system
A26880 Lightening Protection System 14 18-Mar-21 03-Apr-21 0% Lightening Protection System
A26830 Power Installation 18 30-Mar-21 19-Apr-21 0% Power Installation
A27110 Lighting System Third Fix (Fixtures) 14 22-Apr-21 08-May-21 0% Lighting System Third Fix (Fixtures)
Communications 102 09-Jan-21 06-May-21 0% 06-May-21, Communications
A26890 Telephone & Data Communication System First Fix 30 09-Jan-21 11-Feb-21 0% Telephone & Data Communication System First Fix
A26930 Fire Ala rm System First Fix 30 02-Feb-21 08-Mar-21 0% Fire Ala rm System First Fix
A27140 Telephone & Data Communication System Second Fix 30 13-Feb-21 18-Mar-21 0% Telephone & Data Communication System Second Fix
A27120 Fire Ala rm System Second Fix 30 09-Mar-21 12-Apr-21 0% Fire Ala rm System Second Fix
A26910 Floor Boxes 21 20-Mar-21 12-Apr-21 0% Floor Boxes
A26920 Public Address system 21 20-Mar-21 12-Apr-21 0% Public Address system
A27130 Fire Ala rm System Third Fix 21 13-Apr-21 06-May-21 0% Fire Ala rm System Third Fix
A27150 Telephone & Data Communication System Third Fix 21 13-Apr-21 06-May-21 0% Telephone & Data Communication System Third
Electrical Room (B) 126 09-Jan-21 03-Jun-21 0% 03-Jun-21, Electrical Room (B)
Civil Works 106 09-Jan-21 11-May-21 0% 11-May-21, Civil Works
Sub-Structure 42 09-Jan-21 25-Feb-21 0% 25-Feb-21, Sub-Structure
A27420 Excavation for foundation 5 09-Jan-21 13-Jan-21 0% Excavation for foundation
A27440 Soil termite treatment 2 14-Jan-21 16-Jan-21 0% Soil termite treatment
A27460 PCC 2 17-Jan-21 18-Jan-21 0% PCC
A27470 Footing 5 19-Jan-21 24-Jan-21 0% Footing
A27490 Neck Column 7 25-Jan-21 01-Feb-21 0% Neck Column
A27500 Grade Beam 7 02-Feb-21 09-Feb-21 0% Grade Beam
A27450 bitumen paint 2 10-Feb-21 11-Feb-21 0% bitumen paint
A27480 Slab on grade 7 13-Feb-21 20-Feb-21 0% Slab on grade
A27430 Backfilling 5 21-Feb-21 25-Feb-21 0% Backfilling
Super Structure 64 27-Feb-21 11-May-21 0% 11-May-21, Super Structure
Concrete Works 23 27-Feb-21 24-Mar-21 0% 24-Mar-21, Concrete Works
A27530 Column 7 27-Feb-21 06-Mar-21 0% Column
A27510 Beams 7 07-Mar-21 14-Mar-21 0% Beams
A27520 Slabs 9 15-Mar-21 24-Mar-21 0% Slabs
Finishing Works 41 25-Mar-21 11-May-21 0% 11-May-21, Finishing Works
A27230 Masonry Works 15 25-Mar-21 11-Apr-21 0% Masonry Works
A27270 Internal Cement Plastering 9 12-Apr-21 21-Apr-21 0% Internal Cement Plastering
A27240 Doors 5 22-Apr-21 27-Apr-21 0% Doors
A27250 Windows 5 22-Apr-21 27-Apr-21 0% Windows
A27410 Roof finishes 5 22-Apr-21 27-Apr-21 0% Roof finishes
A27260 Floor finish (concrete screed & epoxy) 5 28-Apr-21 03-May-21 0% Floor finish (concrete screed & epoxy)
A27280 External Painting works 7 04-May-21 11-May-21 0% External Painting works
Mechanical Works 10 22-Apr-21 03-May-21 0% 03-May-21, Mechanical Works
A27220 General Exhaust Fan 4 22-Apr-21 26-Apr-21 0% General Exhaust Fan
A27290 Gargouri drainage 3 27-Apr-21 29-Apr-21 0% Gargouri drainage
A27360 fire extinguisher 3 01-May-21 03-May-21 0% fire extinguisher
Electrical Works 46 12-Apr-21 03-Jun-21 0% 03-Jun-21, Electrical Works
A27310 Lighting System First Fix (Conduits) 5 12-Apr-21 17-Apr-21 0% Lighting System First Fix (Conduits)
A27350 Fire Ala rm System First Fix 5 12-Apr-21 17-Apr-21 0% Fire Alarm System First Fix
A27330 Conductors and cables 3 18-Apr-21 20-Apr-21 0% Conductors and cables
A27320 Power Installation 3 21-Apr-21 24-Apr-21 0% Power Installation
A27370 Lighting System Second Fix (Wires) 5 12-May-21 17-May-21 0% Lighting System Second Fix (Wires)
A27390 Fire Ala rm System Second Fix 5 12-May-21 17-May-21 0% Fire Ala rm System Second Fix

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 11 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A27300 Panel Boards 5 18-May-21 23-May-21 0% Panel Boards
A27340 Earthing system 5 24-May-21 29-May-21 0% Earthing system
A27380 Lighting System Third Fix (Fixtures) 5 30-May-21 03-Jun-21 0% Lighting System Third Fix (Fixtures)
A27400 Fire Ala rm System Third Fix 5 30-May-21 03-Jun-21 0% Fire Ala rm System Third Fix
BUILDING (C) 279 08-Aug-20 29-Jun-21 0% 29-Jun-21, BUILDING (C)
Main Building (C) 265 08-Aug-20 13-Jun-21 0% 13-Jun-21, Main Building (C)
Civil Works 265 08-Aug-20 13-Jun-21 0% 13-Jun-21, Civil Works
Sub-Structure 9 08-Aug-20 17-Aug-20 0% 17-Aug-20, Sub-Structure
A27920 Remove of residues 9 08-Aug-20 17-Aug-20 0% Remove of residues
Super Structure 256 18-Aug-20 13-Jun-21 0% 13-Jun-21, Super Structure
Concrete Works 113 18-Aug-20 28-Dec-20 0% 28-Dec-20, Concrete Works
Supporting Works 66 14-Sep-20 30-Nov-20 0% 30-Nov-20, Supporting Works
A27990 Foundations 28 14-Sep-20 17-Oct-20 0% Foundations
A27980 Columns 24 18-Oct-20 14-Nov-20 0% Columns
A27970 Beams 14 15-Nov-20 30-Nov-20 0% Beams
Check and treatment 23 18-Aug-20 13-Sep-20 0% 13-Sep-20, Check and treatment
A27950 Checking 9 18-Aug-20 27-Aug-20 0% Checking
A27960 Treatments 14 29-Aug-20 13-Sep-20 0% Treatments
Casting Works 24 01-Dec-20 28-Dec-20 0% 28-Dec-20, Casting Works
A28120 Slabs & Beams 14 01-Dec-20 16-Dec-20 0% Slabs & Beams
A28110 Columns for staircase 5 17-Dec-20 22-Dec-20 0% Columns for staircase
A28000 Rambs 5 23-Dec-20 28-Dec-20 0% Rambs
Finishing Works 143 29-Dec-20 13-Jun-21 0% 13-Jun-21, Finishing Works
A28130 Masonry Works 14 29-Dec-20 13-Jan-21 0% Masonry Works
A28190 Internal Cement Plastering 14 14-Jan-21 30-Jan-21 0% Internal Cement Plastering
A28210 External Cement Plastering 17 14-Jan-21 02-Feb-21 0% External Cement Plastering
A28150 Waterproofing for Bathroom & Kitchen 3 31-Jan-21 02-Feb-21 0% Waterproofing for Bathroom & Kitchen
A28240 Gypsum board 9 03-Feb-21 13-Feb-21 0% Gypsum board
A28300 Roof sandwich panels 9 03-Feb-21 13-Feb-21 0% Roof sandwich panels
A28260 Specialies 14 06-Feb-21 21-Feb-21 0% Specialies
A28290 Roof finishes 14 14-Feb-21 01-Mar-21 0% Roof finishes
A28310 Ceiling Tile s 21 14-Feb-21 09-Mar-21 0% Ceiling Tile s
A28280 Tiles for Walls 7 22-Feb-21 01-Mar-21 0% Tiles for Walls
A28140 Handrail & Protections 14 02-Mar-21 17-Mar-21 0% Handrail & Protections
A28160 Doors 15 02-Mar-21 18-Mar-21 0% Doors
A28170 Windows 24 02-Mar-21 29-Mar-21 0% Windows
A28220 External Painting works 14 10-Mar-21 25-Mar-21 0% External Painting works
A28230 Aluminium strip 7 18-Mar-21 25-Mar-21 0% Aluminium strip
A28200 Internal Painting Works (Primer + Filler + 1st Coat) 14 30-Mar-21 14-Apr-21 0% Internal Painting Works (Primer + Filler + 1st Coat)
A28180 Floor Finish (tiling & scerting) 24 15-Apr-21 12-May-21 0% Floor Finish (tiling & scerting)
A28250 Counters 16 15-Apr-21 03-May-21 0% Counters
A28270 Painting Works (Final Coat) 9 03-Jun-21 13-Jun-21 0% Painting Works (Final Coat)
Mechanical Works 120 14-Jan-21 02-Jun-21 0% 02-Jun-21, Mechanical Works
Plumbing 113 14-Jan-21 25-May-21 0% 25-May-21, Plumbing
A27570 Domestic Water Supply System 9 14-Jan-21 24-Jan-21 0% Domestic Water Supply System
A27750 Sanitary System 9 14-Jan-21 24-Jan-21 0% Sanitary System
A27580 Isolation valve 3 25-Jan-21 27-Jan-21 0% Isolation valve
A27760 Roof Scupper Drain 6 02-Mar-21 08-Mar-21 0% Roof Scupper Drain
A27590 Electric Water Heaters 11 13-May-21 25-May-21 0% Electric Water Heaters
A27740 Water Storage Tanks 11 13-May-21 25-May-21 0% Water Storage Tanks
A27770 Plumbing Fixtures 11 13-May-21 25-May-21 0% Plumbing Fixtures
Fire Fighting 102 31-Jan-21 29-May-21 0% 29-May-21, Fire Fighting
A27600 Piping 5 31-Jan-21 04-Feb-21 0% Piping
A27610 Fire Hose Cabinet & Accessories 21 15-Apr-21 09-May-21 0% Fire Hose Cabinet & Accessories
A27930 fire extinguisher 7 13-May-21 20-May-21 0% fire extinguisher

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 12 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A28320 Testing and calibrating existing works 7 22-May-21 29-May-21 0% Testing and calibrating existing works
HVAC 56 30-Mar-21 02-Jun-21 0% 02-Jun-21, HVAC
A27550 General Exhaust Fan 9 30-Mar-21 08-Apr-21 0% General Exhaust Fan
A27560 HVAC Ducts and Casings 14 10-Apr-21 25-Apr-21 0% HVAC Ducts and Casings
A27540 DX-Split units 28 26-Apr-21 27-May-21 0% DX-Split units
A27910 Air Curtain 5 29-May-21 02-Jun-21 0% Air Curtain
Electrical Works 116 14-Jan-21 29-May-21 0% 29-May-21, Electrical Works
Electrical 116 14-Jan-21 29-May-21 0% 29-May-21, Electrical
A27790 Lighting System First Fix (Conduits) 7 14-Jan-21 21-Jan-21 0% Lighting System First Fix (Conduits)
A27800 Power Installation 9 14-Jan-21 24-Jan-21 0% Power Installation
A27830 Conductors and cables 7 25-Jan-21 01-Feb-21 0% Conductors and cables
A28010 Lighting System Second Fix (Wires) 7 08-Apr-21 15-Apr-21 0% Lighting System Second Fix (Wires)
A27780 Panel Boards 9 17-Apr-21 26-Apr-21 0% Panel Boards
A27810 Bells system 9 17-Apr-21 26-Apr-21 0% Bells system
A27840 Earthing system 9 17-Apr-21 26-Apr-21 0% Earthing system
A27850 Lightening Protection System 9 17-Apr-21 26-Apr-21 0% Lightening Protection System
A27820 Sockets & Switches 14 27-Apr-21 12-May-21 0% Sockets & Switches
A28020 Lighting System Third Fix (Fixtures) 14 13-May-21 29-May-21 0% Lighting System Third Fix (Fixtures)
Communications 112 14-Jan-21 24-May-21 0% 24-May-21, Communications
A27860 Telephone & Data Communication System First Fix 12 14-Jan-21 27-Jan-21 0% Telephone & Data Communication System First Fix
A27900 Fire Ala rm System First Fix 12 14-Jan-21 27-Jan-21 0% Fire Ala rm System First Fix
A28030 Fire Ala rm System Second Fix 9 15-Apr-21 25-Apr-21 0% Fire Ala rm System Second Fix
A28050 Telephone & Data Communication System Second Fix 9 15-Apr-21 25-Apr-21 0% Telephone & Data Communication System Second F
A27880 Floor Boxes 9 26-Apr-21 05-May-21 0% Floor Boxes
A27890 Public Address system 9 26-Apr-21 05-May-21 0% Public Address system
A28330 Check in and check out monitoring system 7 06-May-21 13-May-21 0% Check in and check out monitoring system
A28040 Fire Ala rm System Third Fix 9 15-May-21 24-May-21 0% Fire Ala rm System Third Fix
A28060 Telephone & Data Communication System Third Fix 9 15-May-21 24-May-21 0% Telephone & Data Communication System T
Canteen (C) 143 14-Jan-21 29-Jun-21 0% 29-Jun-21, Canteen (C)
Civil Works 143 14-Jan-21 29-Jun-21 0% 29-Jun-21, Civil Works
Sub-Structure 42 14-Jan-21 03-Mar-21 0% 03-Mar-21, Sub-Structure
A28480 Excavation for foundation 4 14-Jan-21 18-Jan-21 0% Excavation for foundation
A28500 Soil termite treatment 1 19-Jan-21 19-Jan-21 0% Soil termite treatment
A28540 PCC 2 20-Jan-21 21-Jan-21 0% PCC
A28550 Footing 7 23-Jan-21 30-Jan-21 0% Footing
A28570 Neck Column 7 31-Jan-21 07-Feb-21 0% Neck Column
A28590 Grade Beam 7 08-Feb-21 15-Feb-21 0% Grade Beam
A28530 bitumen paint 3 16-Feb-21 18-Feb-21 0% bitumen paint
A28560 Slab on grade 9 20-Feb-21 01-Mar-21 0% Slab on grade
A28490 Backfilling 2 02-Mar-21 03-Mar-21 0% Backfilling
Super Structure 101 04-Mar-21 29-Jun-21 0% 29-Jun-21, Super Structure
Concrete Works 39 04-Mar-21 18-Apr-21 0% 18-Apr-21, Concrete Works
A28580 Column 9 04-Mar-21 14-Mar-21 0% Column
A28510 Beams 9 15-Mar-21 24-Mar-21 0% Beams
A28520 Slabs 21 25-Mar-21 18-Apr-21 0% Slabs
Finishing Works 62 19-Apr-21 29-Jun-21 0% 29-Jun-21, Finishing Works
A28600 Masonry Works 14 19-Apr-21 04-May-21 0% Masonry Works
A28660 External Cement Plastering 7 05-May-21 12-May-21 0% External Cement Plastering
A28650 Internal Cement Plastering 7 13-May-21 20-May-21 0% Internal Cement Plastering
A28680 Gypsum board 5 22-May-21 26-May-21 0% Gypsum board
A28610 Waterproofing for Bathroom & Kitchen 3 27-May-21 30-May-21 0% Waterproofing for Bathroom & Kitchen
A28710 Roof finishes 7 27-May-21 03-Jun-21 0% Roof finishes
A28700 Tiles for Walls 7 31-May-21 07-Jun-21 0% Tiles for Walls
A28640 Floor tiling 5 08-Jun-21 13-Jun-21 0% Floor tiling
A28620 Doors 5 14-Jun-21 19-Jun-21 0% Doors

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 13 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A28630 Windows 5 14-Jun-21 19-Jun-21 0% Windows
A28690 Counters 7 14-Jun-21 21-Jun-21 0% Counters
A28670 External Painting works 7 22-Jun-21 29-Jun-21 0% External Painting works
Mechanical Works 37 05-May-21 16-Jun-21 0% 16-Jun-21, Mechanical Works
Plumbing 37 05-May-21 16-Jun-21 0% 16-Jun-21, Plumbing
A28360 Domestic Water Supply System 3 05-May-21 08-May-21 0% Domestic Water Supply System
A28400 Sanitary System 3 05-May-21 08-May-21 0% Sanitary System
A28470 Sanitary Waste Piping Specialties 3 05-May-21 08-May-21 0% Sanitary Waste Piping Specialties
A28410 Roof Scupper Drain 3 13-May-21 16-May-21 0% Roof Scupper Drain
A28370 Electric Water Heaters 3 14-Jun-21 16-Jun-21 0% Electric Water Heaters
A28420 Plumbing Fixtures 3 14-Jun-21 16-Jun-21 0% Plumbing Fixtures
Fire Fighting 2 14-Jun-21 15-Jun-21 0% 15-Jun-21, Fire Fighting
A28380 fire extinguisher 2 14-Jun-21 15-Jun-21 0% fire extinguisher
HVAC 6 27-May-21 02-Jun-21 0% 02-Jun-21, HVAC
A28350 General Exhaust Fan 3 27-May-21 30-May-21 0% General Exhaust Fan
A28340 DX-Split wall mounted type air conditioning units 3 31-May-21 02-Jun-21 0% DX-Split wall mounted type air conditionin
Electrical Works 28 05-May-21 06-Jun-21 0% 06-Jun-21, Electrical Works
Electrical Power 28 05-May-21 06-Jun-21 0% 06-Jun-21, Electrical Power
A28720 Lighting System First Fix (Conduits) 5 05-May-21 10-May-21 0% Lighting System First Fix (Conduits)
A28460 Conductors and cables 3 11-May-21 13-May-21 0% Conductors and cables
A28440 Power Installation 2 15-May-21 16-May-21 0% Power Installation
A28750 Lighting System Second Fix (Wires) 5 22-May-21 26-May-21 0% Lighting System Second Fix (Wires)
A28430 Power and Lighting panel 3 27-May-21 30-May-21 0% Power and Lighting panel
A28450 Disconnect Switches 1 31-May-21 31-May-21 0% Disconnect Switches
A28760 Lighting System Third Fix (Fixtures) 5 01-Jun-21 06-Jun-21 0% Lighting System Third Fix (Fixtures)
Communications 15 05-May-21 22-May-21 0% 22-May-21, Communications
A28730 Telephone & Data Communication System First Fix 5 05-May-21 10-May-21 0% Telephone & Data Communication System First
A28740 Fire Ala rm System First Fix 5 05-May-21 10-May-21 0% Fire Alarm System First Fix
A28770 Fire Ala rm System Second Fix 5 11-May-21 16-May-21 0% Fire Ala rm System Second Fix
A28790 Telephone & Data Communication System Second Fix 5 11-May-21 16-May-21 0% Telephone & Data Communication System Se
A28780 Fire Ala rm System Third Fix 5 17-May-21 22-May-21 0% Fire Ala rm System Third Fix
A28800 Telephone & Data Communication System Third Fix 5 17-May-21 22-May-21 0% Telephone & Data Communication System T
Guard House (C) 143 14-Jan-21 29-Jun-21 0% 29-Jun-21, Guard House (C)
Civil Works 143 14-Jan-21 29-Jun-21 0% 29-Jun-21, Civil Works
Sub-Structure 40 14-Jan-21 01-Mar-21 0% 01-Mar-21, Sub-Structure
A29150 Excavation for foundation 5 14-Jan-21 19-Jan-21 0% Excavation for foundation
A29170 Soil termite treatment 2 20-Jan-21 21-Jan-21 0% Soil termite treatment
A29190 PCC 2 23-Jan-21 24-Jan-21 0% PCC
A29200 Footing 7 25-Jan-21 01-Feb-21 0% Footing
A29220 Neck Column 7 02-Feb-21 09-Feb-21 0% Neck Column
A29230 Grade Beam 7 10-Feb-21 17-Feb-21 0% Grade Beam
A29210 Slab on grade 7 18-Feb-21 25-Feb-21 0% Slab on grade
A29160 Backfilling 3 27-Feb-21 01-Mar-21 0% Backfilling
Super Structure 103 02-Mar-21 29-Jun-21 0% 29-Jun-21, Super Structure
Concrete Works 36 02-Mar-21 12-Apr-21 0% 12-Apr-21, Concrete Works
A29260 Column 7 02-Mar-21 09-Mar-21 0% Column
A29240 Beams 9 10-Mar-21 20-Mar-21 0% Beams
A29250 Slabs 20 21-Mar-21 12-Apr-21 0% Slabs
Finishing Works 67 13-Apr-21 29-Jun-21 0% 29-Jun-21, Finishing Works
A28850 Masonry Works 14 13-Apr-21 28-Apr-21 0% Masonry Works
A28910 External Cement Plastering 9 29-Apr-21 09-May-21 0% External Cement Plastering
A28900 Internal Cement Plastering 9 10-May-21 19-May-21 0% Internal Cement Plastering
A28930 Aluminium strip 7 10-May-21 17-May-21 0% Aluminium strip
A29140 Roof finishes 14 18-May-21 02-Jun-21 0% Roof finishes
A28860 Waterproofing for Bathroom & Kitchen 3 20-May-21 23-May-21 0% Waterproofing for Bathroom & Kitchen

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 14 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A29130 Tiles for Walls 5 24-May-21 29-May-21 0% Tiles for Walls
A29060 Specialies 3 30-May-21 01-Jun-21 0% Specialies
A28890 Floor Finish (tiling & scerting) 5 02-Jun-21 07-Jun-21 0% Floor Finish (tiling & scerting)
A28870 Doors 5 08-Jun-21 13-Jun-21 0% Doors
A28880 Windows 5 08-Jun-21 13-Jun-21 0% Windows
A28940 Counters 3 08-Jun-21 10-Jun-21 0% Counters
A28920 External Painting works 9 20-Jun-21 29-Jun-21 0% External Painting works
Mechanical Works 44 29-Apr-21 19-Jun-21 0% 19-Jun-21, Mechanical Works
A28830 Domestic Water Supply System 3 29-Apr-21 02-May-21 0% Domestic Water Supply System
A29270 Sanitary Specialties 5 29-Apr-21 04-May-21 0% Sanitary Specialties
A28950 Sanitary System 5 05-May-21 10-May-21 0% Sanitary System
A28960 Rain water Pipe & Scupper Drain 3 11-May-21 13-May-21 0% Rain water Pipe & Scupper Drain
A28820 General Exhaust Fan 5 08-Jun-21 13-Jun-21 0% General Exhaust Fan
A28840 Electric Water Heaters 2 08-Jun-21 09-Jun-21 0% Electric Water Heaters
A28970 Plumbing Fixtures 5 08-Jun-21 13-Jun-21 0% Plumbing Fixtures
A29050 fire extinguisher 3 08-Jun-21 10-Jun-21 0% fire extinguisher
A28810 DX-Split Units 5 14-Jun-21 19-Jun-21 0% DX-Split Units
Electrical Works 40 29-Apr-21 14-Jun-21 0% 14-Jun-21, Electrical Works
Electrical 40 29-Apr-21 14-Jun-21 0% 14-Jun-21, Electrical
A28990 Lighting System First Fix (Conduits) 7 29-Apr-21 06-May-21 0% Lighting System First Fix (Conduits)
A29020 Conductors and cables 5 08-May-21 12-May-21 0% Conductors and cables
A29000 Power Installation 5 13-May-21 18-May-21 0% Power Installation
A29070 Lighting System Second Fix (Wires) 7 20-May-21 27-May-21 0% Lighting System Second Fix (Wires)
A28980 Panel Boards 3 29-May-21 31-May-21 0% Panel Boards
A29010 Sockets & Switches 5 01-Jun-21 06-Jun-21 0% Sockets & Switches
A29080 Lighting System Third Fix (Fixtures) 7 07-Jun-21 14-Jun-21 0% Lighting System Third Fix (Fixtures)
Communications 28 29-Apr-21 31-May-21 0% 31-May-21, Communications
A29030 Telephone & Data Communication System First Fix 5 29-Apr-21 04-May-21 0% Telephone & Data Communication System First Fi
A29040 Fire Ala rm System First Fix 5 29-Apr-21 04-May-21 0% Fire Alarm System First Fix
A29090 Fire Ala rm System Second Fix 5 20-May-21 25-May-21 0% Fire Ala rm System Second Fix
A29110 Telephone & Data Communication System Second Fix 5 20-May-21 25-May-21 0% Telephone & Data Communication System S
A29100 Fire Ala rm System Third Fix 5 26-May-21 31-May-21 0% Fire Ala rm System Third Fix
A29120 Telephone & Data Communication System Third Fix 5 26-May-21 31-May-21 0% Telephone & Data Communication System
Electrical Room (C) 127 14-Jan-21 10-Jun-21 0% 10-Jun-21, Electrical Room (C)
Civil Works 127 14-Jan-21 10-Jun-21 0% 10-Jun-21, Civil Works
Sub-Structure 41 14-Jan-21 02-Mar-21 0% 02-Mar-21, Sub-Structure
A29480 Excavation for foundation 3 14-Jan-21 17-Jan-21 0% Excavation for foundation
A29500 Soil termite treatment 2 18-Jan-21 19-Jan-21 0% Soil termite treatment
A29520 PCC 2 20-Jan-21 21-Jan-21 0% PCC
A29530 Footing 7 23-Jan-21 30-Jan-21 0% Footing
A29550 Neck Column 7 31-Jan-21 07-Feb-21 0% Neck Column
A29560 Grade Beam 7 08-Feb-21 15-Feb-21 0% Grade Beam
A29510 bitumen paint 2 16-Feb-21 17-Feb-21 0% bitumen paint
A29540 Slab on grade 9 18-Feb-21 28-Feb-21 0% Slab on grade
A29490 Backfilling 2 01-Mar-21 02-Mar-21 0% Backfilling
Super Structure 86 03-Mar-21 10-Jun-21 0% 10-Jun-21, Super Structure
Concrete Works 44 03-Mar-21 22-Apr-21 0% 22-Apr-21, Concrete Works
A29590 Column 14 03-Mar-21 18-Mar-21 0% Column
A29570 Beams 9 20-Mar-21 29-Mar-21 0% Beams
A29580 Slabs 21 30-Mar-21 22-Apr-21 0% Slabs
Finishing Works 42 24-Apr-21 10-Jun-21 0% 10-Jun-21, Finishing Works
A29290 Masonry Works 12 24-Apr-21 06-May-21 0% Masonry Works
A29330 Internal Cement Plastering 5 08-May-21 12-May-21 0% Internal Cement Plastering
A29320 Floor finish (concrete screed & epoxy) 5 13-May-21 18-May-21 0% Floor finish (concrete screed & epoxy)
A29300 Doors 5 19-May-21 24-May-21 0% Doors

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 15 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A29310 Windows 5 19-May-21 24-May-21 0% Windows
A29470 Roof finishes 5 25-May-21 30-May-21 0% Roof finishes
A29340 External Painting works 5 06-Jun-21 10-Jun-21 0% External Painting works
Mechanical Works 15 19-May-21 05-Jun-21 0% 05-Jun-21, Mechanical Works
A29280 General Exhaust Fan 5 19-May-21 24-May-21 0% General Exhaust Fan
A29350 Gargouri drainage 5 25-May-21 30-May-21 0% Gargouri drainage
A29420 fire extinguisher 5 31-May-21 05-Jun-21 0% fire extinguisher
Electrical Works 20 08-May-21 30-May-21 0% 30-May-21, Electrical Works
A29370 Lighting System First Fix (Conduits) 5 08-May-21 12-May-21 0% Lighting System First Fix (Conduits)
A29410 Fire Ala rm System First Fix 5 08-May-21 12-May-21 0% Fire Ala rm System First Fix
A29390 Conductors and cables 5 13-May-21 18-May-21 0% Conductors and cables
A29430 Lighting System Second Fix (Wires) 5 13-May-21 18-May-21 0% Lighting System Second Fix (Wires)
A29450 Fire Ala rm System Second Fix 5 13-May-21 18-May-21 0% Fire Ala rm System Second Fix
A29360 Panel Boards 5 19-May-21 24-May-21 0% Panel Boards
A29380 Power Installation 5 19-May-21 24-May-21 0% Power Installation
A29400 Earthing system 5 19-May-21 24-May-21 0% Earthing system
A29440 Lighting System Third Fix (Fixtures) 5 25-May-21 30-May-21 0% Lighting System Third Fix (Fixtures)
A29460 Fire Ala rm System Third Fix 5 25-May-21 30-May-21 0% Fire Ala rm System Third Fix
Gate (C) 139 14-Jan-21 24-Jun-21 0% 24-Jun-21, Gate (C)
Civil Works 139 14-Jan-21 24-Jun-21 0% 24-Jun-21, Civil Works
Sub-Structure 45 14-Jan-21 07-Mar-21 0% 07-Mar-21, Sub-Structure
A29940 Excavation for foundation 3 14-Jan-21 17-Jan-21 0% Excavation for foundation
A29950 Soil termite treatment 2 18-Jan-21 19-Jan-21 0% Soil termite treatment
A29970 PCC 2 20-Jan-21 21-Jan-21 0% PCC
A29980 Footing 5 23-Jan-21 27-Jan-21 0% Footing
A30000 Neck Column 7 28-Jan-21 04-Feb-21 0% Neck Column
A30010 Grade Beam 7 06-Feb-21 13-Feb-21 0% Grade Beam
A29960 bitumen paint 2 14-Feb-21 15-Feb-21 0% bitumen paint
A29990 Slab on grade 14 16-Feb-21 03-Mar-21 0% Slab on grade
A30070 Backfilling 3 04-Mar-21 07-Mar-21 0% Backfilling
Super Structure 94 08-Mar-21 24-Jun-21 0% 24-Jun-21, Super Structure
Concrete Works 37 08-Mar-21 19-Apr-21 0% 19-Apr-21, Concrete Works
A30040 Column 9 08-Mar-21 17-Mar-21 0% Column
A30020 Beams 7 18-Mar-21 25-Mar-21 0% Beams
A30030 Slabs 21 27-Mar-21 19-Apr-21 0% Slabs
Finishing Works 57 20-Apr-21 24-Jun-21 0% 24-Jun-21, Finishing Works
A29640 Masonry Works 14 20-Apr-21 05-May-21 0% Masonry Works
A29700 Cement Plastering 7 06-May-21 13-May-21 0% Cement Plastering
A29660 Waterproofing for Bathroom & Kitchen 5 15-May-21 19-May-21 0% Waterproofing for Bathroom & Kitchen
A29720 Aluminium strip 3 15-May-21 17-May-21 0% Aluminium strip
A29650 Handrail & Protections 5 18-May-21 23-May-21 0% Handrail & Protections
A29910 Tiles for Walls 5 20-May-21 25-May-21 0% Tiles for Walls
A29930 External metal shades 14 24-May-21 08-Jun-21 0% External metal shades
A29840 Specialies 3 26-May-21 29-May-21 0% Specialies
A29690 Floor Finish (tiling & scerting) 7 30-May-21 06-Jun-21 0% Floor Finish (tiling & scerting)
A29670 Doors 5 07-Jun-21 12-Jun-21 0% Doors
A29680 Windows 5 07-Jun-21 12-Jun-21 0% Windows
A29920 Roof finishes & mosaic tile 7 09-Jun-21 16-Jun-21 0% Roof finishes & mosaic tile
A29710 External Painting works 7 17-Jun-21 24-Jun-21 0% External Painting works
Mechanical Works 34 06-May-21 14-Jun-21 0% 14-Jun-21, Mechanical Works
A29620 Domestic Water Supply System 7 06-May-21 13-May-21 0% Domestic Water Supply System
A29730 Sanitary System 7 06-May-21 13-May-21 0% Sanitary System
A29610 General Exhaust Fan 5 15-May-21 19-May-21 0% General Exhaust Fan
A29600 DX-Split units 7 20-May-21 27-May-21 0% DX-Split units
A29630 Electric Water Heaters 5 07-Jun-21 12-Jun-21 0% Electric Water Heaters

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 16 of 17
Actual Work Milestone 04-Jun-20
Al Ihsaa- Educational Complex in Al Jubail D.D 04-Jun-20 UPDATE
04-06-2020
Activity ID Activity Name Original Start Finish Performance % 2020 2021
Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A29740 Plumbing Fixtures 7 07-Jun-21 14-Jun-21 0% Plumbing Fixtures
A30050 Sanitary Specialties 5 07-Jun-21 12-Jun-21 0% Sanitary Specialties
Electrical Works 18 06-May-21 26-May-21 0% 26-May-21, Electrical Works
Electrical 18 06-May-21 26-May-21 0% 26-May-21, Electrical
A29760 Lighting System First Fix (Conduits) 7 06-May-21 13-May-21 0% Lighting System First Fix (Conduits)
A29790 Conductors and cables 5 15-May-21 19-May-21 0% Conductors and cables
A29850 Lighting System Second Fix (Wires) 5 15-May-21 19-May-21 0% Lighting System Second Fix (Wires)
A29750 Panel Boards 3 20-May-21 23-May-21 0% Panel Boards
A29770 Power Installation 3 20-May-21 23-May-21 0% Power Installation
A29780 Sockets & Switches 3 20-May-21 23-May-21 0% Sockets & Switches
A29860 Lighting System Third Fix (Fixtures) 3 24-May-21 26-May-21 0% Lighting System Third Fix (Fixtures)
Communications 18 06-May-21 26-May-21 0% 26-May-21, Communications
A29800 Telephone & Data Communication System First Fix 9 06-May-21 16-May-21 0% Telephone & Data Communication System Firs
A29820 Fire Ala rm System First Fix 7 06-May-21 13-May-21 0% Fire Ala rm System First Fix
A29870 Fire Ala rm System Second Fix 5 15-May-21 19-May-21 0% Fire Ala rm System Second Fix
A29890 Telephone & Data Communication System Second Fix 3 17-May-21 19-May-21 0% Telephone & Data Communication System Se
A29810 Public Address system 3 20-May-21 23-May-21 0% Public Address system
A29880 Fire Ala rm System Third Fix 3 24-May-21 26-May-21 0% Fire Ala rm System Third Fix
A29900 Telephone & Data Communication System Third Fix 3 24-May-21 26-May-21 0% Telephone & Data Communication System
Water Tank & Pump Room (C) 121 14-Jan-21 03-Jun-21 0% 03-Jun-21, Water Tank & Pump Room (C)
Civil Works 24 14-Jan-21 10-Feb-21 0% 10-Feb-21, Civil Works
A30120 Test the filtration of the existing tank 5 14-Jan-21 19-Jan-21 0% Test the filtration of the existing tank
A30240 Pump Room 14 20-Jan-21 04-Feb-21 0% Pump Room
A30110 Cover & Ladder 5 06-Feb-21 10-Feb-21 0% Cover & Ladder
Mechanical Works 35 11-Feb-21 23-Mar-21 0% 23-Mar-21, Mechanical Works
A30090 Fire Pump 21 11-Feb-21 07-Mar-21 0% Fire Pump
A30140 Water Transfer Pumps 14 08-Mar-21 23-Mar-21 0% Water Transfer Pumps
Electrical Works 62 24-Mar-21 03-Jun-21 0% 03-Jun-21, Electrical Works
A30260 Fire Ala rm System First Fix 3 24-Mar-21 27-Mar-21 0% Fire Ala rm System First Fix
A30270 Fire Ala rm System Second Fix 3 28-Mar-21 30-Mar-21 0% Fire Ala rm System Second Fix
A30150 Sockets & Switches 3 31-Mar-21 03-Apr-21 0% Sockets & Switches
A30280 Fire Ala rm System Third Fix 3 01-Jun-21 03-Jun-21 0% Fire Ala rm System Third Fix

Testing & Commissioning 13 30-Jun-21 14-Jul-21 0% 14-Jul-21, Testing & Commiss


A21010 Testing & Commissioning 13 30-Jun-21 14-Jul-21 0% Testing & Commissioning
Hnading Over 7 21-Jul-21 28-Jul-21 0% 28-Jul-21, Hnading Over
A4300 Handing Over 7 21-Jul-21 28-Jul-21 0% Handing Over

Actual Level of Effort Remaining Work summary Date Revision Checked Approved
Page 17 of 17
Actual Work Milestone 04-Jun-20