WEEKLY SAFETY STATISTICS

REPORT FOR

Report No : 001
Location : Arabian Ranches 03 Development- Phase 3ABC & 4B, Boulevard and
Central Park – Landscape Work

Man, hours Man, hours Man, hours Man, Av. No of Av. No of


previous week for the for the period hours to Employees Subcontract
(cumulative) period (Subcontract) date (Inc. Employees
(A) (Contractor) (C) cumulative staffs)
(B) (A+B+C)
3996 3780 0 7776 70 0

(2) OVERALL MAN-HOURS:


This Cumulative till this
Details Previous
Period Date
In-direct Man-hours 0 0
Direct Man-hours 3996 3780 27162
Total Man-hours 3996 3780 27162
(3) LOST TIME INCIDENT MANHOURS

Man, hours worked Man, hours worked after


Date of last LTI
prior to last LTI
0 0 0

(4) ACCIDENTS:

For the period For the period To date


No. Type of Accident (cumulative
(Contractor) (Subcontract)
1 Near Misses / DO 1 0 1
2 First Aid Case (FAC) 0 0 0
3 Property Damage (PD) 0 0 0
4 Fire Incident 0 0 0
5 Environmental (E) 0 0 0
6 Medical Treatment Case (MTC) 0 0 0
7 L.T. I 0 0 0
8 Restricted Work Case (RWC) 0 0 0
9 Lost Work Day Case (LWC) 0 0 0
10 Permanent Partial Disability (PPD) 0 0 0
11 Permanent Total Disability (PTD) 0 0 0
12 Fatality (F) 0 0 0

(5) OTHER ACTIVITIES:


Previous To date
No Types For the period
cumulative cumulativ
.
e
1 Safety Corrective Action Reports 0 0 0

2 Safety Awards 0 0 0

3 Safety Violation Issued by Contractor 0 0 0

4 Safety Violation Issued by PARSONS 0 0 0

5 Training 1 1 2
(a) Safety Induction 15 14 60
WEEKLY SAFETY STATISTICS
REPORT FOR

(b) Tool Box Talks 2 2 12


(c) STAART Briefing 02 02 06

(6) SITE HOUSE KEEPING:


Last Week
Poor
Satisfactory
Improved
Good 
This Week
Poor
Satisfactory
Improved
Good 

(7) SAFETY SIGNAGE:


Inadequate :
Adequate : Adequate
Good :
(8) NUMBER OF SAFETY PERSONAL
AT SITE: HSE Officer :
01
HSE Assistant 01
Site First Aiders/Nurse : 01
First Aiders : 01
(9) SITE SECURITY:
Security officers are available at
site.
Day Shift :
Night Shift : 01
(10) IMPORTANT AND NECESSARY REQUIREMENTS:

(11) CONTRACTOR'S SAFETY AWARENESS:

12) HS&E CAMPAIGNSHELD

(13) REMARKS: NILs

Prepared by : Salahuddin Mir

Date : 24-06-24