UTV400 ROV MOBILIZATION FOR DNEX PACIFIC LINK

ID WBS Task Name Duration Start Finish May Jun


W-3 W-2 W-1 W1 W2 W3 W4
0 0 UTV400 ROV Mobilization at UTRACO 15.13 days Fri 10/5/24 Fri 31/5/24
1 1 Steel Material for existing Umbilical Winch Base and LARS Base 4.5 days Fri 10/5/24 Thu 16/5/24
2 1.1 Steel ordering confirmation to UTRACO by Delta Maritim 1 day Fri 10/5/24 Fri 10/5/24
3 1.2 Issuance of PO to supplier by UTRACO 1 day Fri 10/5/24 Fri 10/5/24
4 1.3 Steel material preparation for transport 1 day Mon 13/5/24 Mon 13/5/24
5 1.4 Shipment from Singapore to Batam 1 day Tue 14/5/24 Tue 14/5/24
6 1.5 Custom Clearance 0.5 days Wed 15/5/24 Wed 15/5/24
7 1.6 Cutting and fitting to the specification 1 day Wed 15/5/24 Thu 16/5/24
8 1.7 Steel material ready for delivery tu UTRACO 0 days Thu 16/5/24 Thu 16/5/24 Steel material ready for delivery tu UTRACO
9 2 Vessel Mobilisation 14.63 days Mon 13/5/24 Mon 27/5/24
10 2.1 DPL Alongside at the shipyard 0 days Mon 13/5/24 Mon 13/5/24 DPL Alongside at the shipyard
11 2.2 Hot Work and PTW Issuance 1 day Mon 13/5/24 Mon 13/5/24
12 2.2.1 Submission of application 0.5 days Mon 13/5/24 Mon 13/5/24
13 2.2.2 Issuance process 0.5 days Mon 13/5/24 Mon 13/5/24
14 2.2.3 Hot Work and PTW issued 0 days Mon 13/5/24 Mon 13/5/24 Hot Work and PTW issued
15 2.3 Material delivery to UTRACO 3.63 days Mon 13/5/24 Thu 16/5/24
16 2.3.1 Fabrication equipment 0.13 days Mon 13/5/24 Mon 13/5/24
17 2.3.2 Shoreside fabrication 0.13 days Mon 13/5/24 Mon 13/5/24
18 2.3.3 Electrical supplies 0.13 days Mon 13/5/24 Mon 13/5/24
19 2.3.4 Steel material for existing Umb Winch and LARS bases 0.13 days Thu 16/5/24 Thu 16/5/24
20 2.3.5 Material delivery to UTRACO completed 0 days Thu 16/5/24 Thu 16/5/24 Material delivery to UTRACO completed
21 2.4 Electrical supply installation 6 days Tue 14/5/24 Sun 19/5/24
22 2.4.1 Laying new cable as per requirement 5 days Tue 14/5/24 Sat 18/5/24
23 2.4.2 System termination and testing 1 day Sun 19/5/24 Sun 19/5/24
24 2.4.3 Electical supply installation completed 0 days Sun 19/5/24 Sun 19/5/24 Electical supply installation completed
25 2.5 Modification of existing Umbilical Winch Base 4.63 days Tue 14/5/24 Sat 18/5/24
26 2.5.1 Cutting existing Umbilical Winch legs to ready for repositioning 0.5 days Tue 14/5/24 Tue 14/5/24
27 2.5.2 Reposition Umbilical Winch base as per requirement 1 day Tue 14/5/24 Wed 15/5/24
28 2.5.3 Sea fastening of the existing base 0.5 days Wed 15/5/24 Wed 15/5/24
29 2.5.4 Refit and weld steel material beam onto the existing base 1 day Thu 16/5/24 Fri 17/5/24
30 2.5.5 NDT structure 1 day Fri 17/5/24 Sat 18/5/24
31 2.5.6 Modification Umb Winch Base Completed 0 days Sat 18/5/24 Sat 18/5/24 Modification Umb Winch Base Completed
32 2.6 Modification of existing LARS Base 2 days Thu 16/5/24 Sat 18/5/24
33 2.6.1 Refit and weld steel material beam onto the existing base 1 day Thu 16/5/24 Fri 17/5/24
34 2.6.2 NDT structure 1 day Fri 17/5/24 Sat 18/5/24
35 2.6.3 Modification LARS Base Completed 0 days Sat 18/5/24 Sat 18/5/24 Modification LARS Base Completed
36 2.7 Transport and shift equipment to quayside 7.38 days Tue 14/5/24 Tue 21/5/24
37 2.7.1 A-Frame - Dynacon 676 0.25 days Tue 14/5/24 Tue 14/5/24
38 2.7.2 A-Frame HPU - Dynacon 659 0.25 days Tue 14/5/24 Tue 14/5/24
39 2.7.3 Winch HPU - 10ft ISO 0.25 days Tue 14/5/24 Tue 14/5/24
40 2.7.4 Deck Control Stand 0.25 days Tue 14/5/24 Tue 14/5/24

DPL - UTV400 Mobilisation at UTRACO Page 1 Mon 13/5/24 12:17 PM


UTV400 ROV MOBILIZATION FOR DNEX PACIFIC LINK
ID WBS Task Name Duration Start Finish May Jun
W-3 W-2 W-1 W1 W2 W3 W4
41 2.7.5 Umbilical Winch 0.25 days Tue 14/5/24 Tue 14/5/24
42 2.7.6 Mechanical Workshop Container (20' ISO) 0.25 days Mon 20/5/24 Mon 20/5/24
43 2.7.7 Electrical Workshop Container (20' ISO) 0.25 days Mon 20/5/24 Tue 21/5/24
44 2.7.8 Control Container (20' ISO) 0.25 days Tue 21/5/24 Tue 21/5/24
45 2.7.9 Shiting of equipment to quayside Completed 0 days Tue 21/5/24 Tue 21/5/24 Shiting of equipment to quayside Completed
46 2.8 Lift Equipment to Deck and secure to deck including NDT 4 days Sat 18/5/24 Wed 22/5/24
47 2.8.1 A-Frame - Dynacon 676 2 days Sat 18/5/24 Mon 20/5/24
48 2.8.2 A-Frame HPU - Dynacon 659 2 days Mon 20/5/24 Wed 22/5/24
49 2.8.3 Winch HPU - 10ft ISO 2 days Mon 20/5/24 Wed 22/5/24
50 2.8.4 Deck Control Stand 2 days Mon 20/5/24 Wed 22/5/24
51 2.8.5 Umbilical Winch 2 days Mon 20/5/24 Wed 22/5/24
52 2.8.6 Mechanical Workshop Container (20' ISO) 1 day Tue 21/5/24 Wed 22/5/24
53 2.8.7 Electrical Workshop Container (20' ISO) 1 day Tue 21/5/24 Wed 22/5/24
54 2.8.8 Control Container (20' ISO) 1 day Tue 21/5/24 Wed 22/5/24
55 2.8.9 UTV400 Equipment lifted onboard DPL Completed 0 days Wed 22/5/24 Wed 22/5/24 UTV400 Equipment lifted onboard DPL Completed
56 2.9 Assembly 5 days Mon 20/5/24 Sat 25/5/24
57 2.9.1 A-Frame - Dynacon 676 1 day Mon 20/5/24 Tue 21/5/24
58 2.9.1.1 Lift Docking Head Assembly with yard crane and attach the 1 day Mon 20/5/24 Tue 21/5/24
A-Frame boom cylinders
59 2.9.2 Umbilical Winch 3 days Wed 22/5/24 Sat 25/5/24
60 2.9.2.1 Lift Sheave Wheel and mount on fleeting carriage 1 day Wed 22/5/24 Thu 23/5/24
61 2.9.2.2 Spool off umbilical to allow Lynksyn installation 1 day Wed 22/5/24 Thu 23/5/24
62 2.9.2.3 Terminate Bullet Assembly 1 day Thu 23/5/24 Fri 24/5/24
63 2.9.2.4 Pull umbilical through A-Frame and position on deck ready 1 day Fri 24/5/24 Sat 25/5/24
for pull test
64 2.9.3 Mechanical Workshop Container (20' ISO) 0.5 days Wed 22/5/24 Thu 23/5/24
65 2.9.3.1 Install foot step to container from deck to side door 0.5 days Wed 22/5/24 Thu 23/5/24
66 2.9.4 Electrical Workshop Container (20' ISO) 0.5 days Thu 23/5/24 Thu 23/5/24
67 2.9.4.1 Install foot step to container from deck to side door 0.5 days Thu 23/5/24 Thu 23/5/24
68 2.10 Connections 4 days Wed 22/5/24 Sun 26/5/24
69 2.10.1 A-Frame HPU - Dynacon 659 1 day Wed 22/5/24 Thu 23/5/24
70 2.10.1.1 Connect cooling water from vessel 1 day Wed 22/5/24 Thu 23/5/24
71 2.10.1.2 Connect HPU to A-Frame using hydraulic hoses 1 day Wed 22/5/24 Thu 23/5/24
72 2.10.1.3 Make Electrical Connection to vessel supply 1 day Wed 22/5/24 Thu 23/5/24
73 2.10.2 Winch HPU - 10ft ISO 1 day Thu 23/5/24 Fri 24/5/24
74 2.10.2.1 Connect cooling water from vessel 1 day Thu 23/5/24 Fri 24/5/24
75 2.10.2.2 Connect HPU to A-Frame and Umbilical Winch using 1 day Thu 23/5/24 Fri 24/5/24
hydraulic hoses
76 2.10.2.3 Make Electrical Connection to vessel supply 1 day Thu 23/5/24 Fri 24/5/24
77 2.10.3 Deck Control Stand 2 days Fri 24/5/24 Sun 26/5/24
78 2.10.3.1 Make connections to Control System 2 days Fri 24/5/24 Sun 26/5/24
79 2.10.4 Umbilical Winch 1 day Fri 24/5/24 Sat 25/5/24

DPL - UTV400 Mobilisation at UTRACO Page 2 Mon 13/5/24 12:17 PM


UTV400 ROV MOBILIZATION FOR DNEX PACIFIC LINK
ID WBS Task Name Duration Start Finish May Jun
W-3 W-2 W-1 W1 W2 W3 W4
80 2.10.4.1 Connect hydraulic lines from HPU - 10ft ISO 1 day Fri 24/5/24 Sat 25/5/24
81 2.10.4.2 Connected comms cables from Control Cabin and HPU - 10ft ISO 1 day Fri 24/5/24 Sat 25/5/24
82 2.10.5 Mechanical Workshop Container (20' ISO) 0.5 days Sat 25/5/24 Sun 26/5/24
83 2.10.5.1 Install suitable electrical earth connection to Workshop 0.5 days Sat 25/5/24 Sun 26/5/24
Container
84 2.10.6 Electrical Workshop Container (20' ISO) 0.5 days Sun 26/5/24 Sun 26/5/24
85 2.10.6.1 Install suitable electrical earth connection to Workshop 0.5 days Sun 26/5/24 Sun 26/5/24
Container
86 2.10.7 Control Container (20' ISO) 2 days Wed 22/5/24 Fri 24/5/24
87 2.10.7.1 Install suitable electrical earth connection to Control Container 1 day Wed 22/5/24 Thu 23/5/24
88 2.10.7.2 Connect power supply from Control Container to Workshop 1 day Wed 22/5/24 Thu 23/5/24
Container
89 2.10.7.3 Make control connection to Umbilical Winch 1 day Thu 23/5/24 Fri 24/5/24
90 2.10.7.4 Make electrical power connection to the Control Container 1 day Thu 23/5/24 Fri 24/5/24
from the vessel power supply
91 2.11 Deck Cabling and System Vessel Interconnections 4 days Thu 23/5/24 Mon 27/5/24
92 2.11.1 Install Remote Clearcomms station on vessel bridge (plus 1 day Thu 23/5/24 Fri 24/5/24
other locations) and run cabling to CC
93 2.11.2 Check power connections to WC from CC and test lights / sockets 1 day Thu 23/5/24 Fri 24/5/24
94 2.11.3 Install NAV screen/cabling run in CC and check 1 day Fri 24/5/24 Sat 25/5/24
95 2.11.4 Connect logging and video output cables to bridge from CC 1 day Fri 24/5/24 Sat 25/5/24
96 2.11.5 Install Deck Lighting 1 day Fri 24/5/24 Sat 25/5/24
97 2.11.6 Check and Commission power cable runs to vessel power supply 1 day Sat 25/5/24 Sun 26/5/24
98 2.11.7 Run survey data cables between TROV control and vessel 1 day Sat 25/5/24 Sun 26/5/24
survey suite
99 2.11.8 Run cables to vessel systems 1 day Sat 25/5/24 Sun 26/5/24
100 2.11.9 Ensure complete system integration and fucntion 1 day Sat 25/5/24 Sun 26/5/24
101 2.11.10 Connect to vessel fire alarm system and perform test (if possible) 1 day Sun 26/5/24 Mon 27/5/24
102 2.11.11 UTV400 Assembly and Connection completed 0 days Mon 27/5/24 Mon 27/5/24 UTV400 Assembly and Connection completed
103 3 Testing 4 days Sun 26/5/24 Thu 30/5/24
104 3.1 A-Frame Load Test 1 day Sun 26/5/24 Mon 27/5/24
105 3.2 LARS Systems Load Test 1 day Mon 27/5/24 Tue 28/5/24
106 3.3 UTV400 Connection and Dry Test 1 day Tue 28/5/24 Wed 29/5/24
107 3.4 UTV400 Dry Test Completed 0 days Wed 29/5/24 Wed 29/5/24 UTV400 Dry Test Completed
108 3.5 UTV400 Wet Test 1 day Wed 29/5/24 Thu 30/5/24
109 3.6 UTV400 Wet Test Completed 0 days Thu 30/5/24 Thu 30/5/24 UTV400 Wet Test Completed
110 4 Preparation for Departure 0.5 days Thu 30/5/24 Fri 31/5/24
111 4.1 Ensure Checklists of Tasks Completed 0.5 days Thu 30/5/24 Fri 31/5/24
112 4.2 UTV400 ROV Installation Completed 0 days Fri 31/5/24 Fri 31/5/24 UTV400 ROV Installation Completed

DPL - UTV400 Mobilisation at UTRACO Page 3 Mon 13/5/24 12:17 PM