02_06_2024_UTV400_DPR
02_06_2024_UTV400_DPR
: OPRE120
Daily Progress Report
Rev. : 9
A) Contact Details :
Email - Equipment Superintendent mark.maddison@pharos-offshore.com Email - Project Manager andy.ratford@pharos-offshore.com
Tel. - Equipment Supervisor Tel. - Project Manager
Richard.McLaughlin@pharos-offshore.com
B) Equipment On-Hire :
Pharos Offshore Group UTV400
Pharos 3rd Party
C) Personnel :
Date No. Days Date due to
Position Name Shift Pattern
Embarked Onboard Disembark
Superintendent Mark Maddison 25/02/2024 98 07:00 - 19:00
Supervisor Richard McLaughlin 13/05/2024 20 07:00 - 19:00
Pilot Technician Adam Page 18/05/2024 15 07:00 - 19:00
Pilot Technician Rhodri Thomas 28/03/2024 66 07:00 - 19:00
Pilot Technician Jason Dickson 30/04/2024 33 07:00 - 19:00
Superintendent Shane McFall 13/05/2024 20 07:00 - 19:00
Pilot Technician Will Dougal 13/05/2024 20 07:00 - 19:00
D) Operational Summary :
Today's Summary : Continue Mobilisation - Cable Tray Works complete, assist as required with installation of LARS Walkway, Heavy Rain on/off most of
the day
Look Ahead : Complete Mobilisation
F) Dairy of Events :
Time KP Description
Pre Shift TBT completed
Jason Dickson - Sign off
Run Deck Umbilical - Start Termination
Cable Tray Top Deck Complete Remove and reroute/connect all harnesses and hydraulic hose cooling etc - Complete
Run and Bleed Fresh water Cooling circuit
Start Unpacking Control Room
H) Acknowledgement
Comment : Pharos Offshore Group
All Pharos Members traveling back to Hotels each night due to visa restrictions.
Load Test certificates to be issued from PT.Dalaz Teknik Utama on Monday 3rd June Mark Maddison
Equipment Superintendent
Comment : DABN
Rizki A. Santoso
Project Coordinator