Professional Documents
Culture Documents
PMBOK-IND502-Lecture_03-243
PMBOK-IND502-Lecture_03-243
IND-502
Project Management
Body Of Knowledge
“PMBOK”
Lecture #3
Dr. Sayed Ali Zayan Summer Term 2023_2024
Project Scheduling
Scheduling is the determination of the timing and sequence of
operations in the project and their assembly to give the overall
completion time. Project planning answers the questions, What is
going to be done? How? Where? By whom?, and When (in
general terms, the project’s start and end)? Scheduling deals with
when on a detailed level
Why Schedule Projects?
Contractors need project scheduling to:
1. Calculate the project completion date
2. Calculate the start or end of a specific activity
3. Coordinate among trades and subcontractors, and
expose and adjust conflicts
4. Predict and calculate the cash flow
5. Improve work efficiency
6. Serve as an effective project control tool
7. Evaluate the effect of changes
8. Prove delay claims
Why Schedule Projects?
Project owners and developers need project scheduling
to:
1. Get an idea on project’s expected finish date
2. Ensure contractor’s proper planning for timely finish
3. Predict and calculate the cash flow
4. Serve as an effective project monitoring tool
5. Evaluate the effect of changes
6. Verify delay claims
Scheduling Tools: Bar(Gantt) Chart
A bar chart is ‘‘a graphic representation of project activities, shown in
a time-scaled bar line with no links shown between activities’’. The bar
chart was originally developed by Henry L. Gantt in 1917 and is
alternatively called a Gantt chart. It quickly became popular—
especially in the construction industry—because of its ability to
graphically represent a project’s activities on a time scale.
• Activity-On-Arrow (AOA).
Project Network: Construction
Basic Rules to Follow in Developing Project Networks:
Networks flow typically from left to right.
An activity cannot begin until all preceding connected activities have been
completed.
Arrows on networks indicate precedence and flow. Arrows can cross over
each other.
Each activity should have a unique identification number.
An activity identification number must be larger than that of any activities
that precede it.
Looping is not allowed (in other words, recycling through a set of activities
cannot take place).
Conditional statements are not allowed (that is, this type of statement
should not appear: If successful, do something; if not, do nothing).
Experience suggests that when there are multiple starts, a common start
node can be used to indicate a clear project beginning on the network.
Similarly, a single project end node can be used to indicate a clear ending.
Project Network: Activity-on-Node (AON)
The wide availability of personal computers and graphics programs has
served as an impetus for use of the Activity-On-Node (AON) method
(sometimes called the precedence diagram method). An activity is
represented by a node (box). The node can take many forms figure, but in
recent years the node represented as a rectangle (box) has dominated.
The different
forms of Node
Project Network: Activity-on-Node (AON)
Activity-on-Node Network Fundamentals
Project Network: Activity-on-Node (AON)
There are three basic relationships that must be established
for activities included in a project network. The
relationships can be found by answering the following
three questions for each activity:
Which activities must be completed immediately before
this activity? These activities are called predecessor
activities.
Which activities must immediately follow this activity?
These activities are called successor activities.
Which activities can occur while this activity is taking
place? This is known as a concurrent or parallel
relationship.
Project Network: Activity-on-Node (AON)
Recommendations for Proper Node Diagram Drawing
1. Nodes and milestones in node networks:
5. Try to minimize line crossings (see Figure). When two lines (relationships) must
intersect, make a “jump” on one of them to indicate that they do not intersect or
meet.
Project Network: Activity-on-Node (AON)
6. Start the network with one node and finish it with one node.
Project Network: Activity-on-Node (AON)
7. In many cases of hand drawing, you will need to redraw
the network after your first attempt. Although your first
attempt may be logically correct, it may look awkward
and confusing. Redraw it to minimize lines crossing and
relocate activities to be as near as possible to their
predecessors and successors.
Example:
Draw a project network from the following information.
What activity(s) is a burst activity? What activity(s) is a
merge activity?
Solution: