Daily Progress Report
Rev. : 9
Issued : 2023.12.05 SYSTEM
Project : DABN Mobilisation DPR No. : 025
Client : DABN Date : 2024.06.06
Vessel : Pacific Link Location : Bintan 99 Jetty, Batu Ampar Batam, Indonesia

A) Contact Details :
Email - Equipment Superintendent mark.maddison@pharos-offshore.com Email - Project Manager andy.ratford@pharos-offshore.com
Tel. - Equipment Supervisor Richard.McLaughlin@pharos-offshore.com Tel. - Project Manager

B) Equipment On-Hire :
Pharos Offshore Group UTV400
Pharos 3rd Party

C) Personnel :
Date No. Days Date due to
Position Name Shift Pattern
Embarked Onboard Disembark
Superintendent Mark Maddison 25/02/2024 102 07:00 - 19:00
Supervisor Richard McLaughlin 13/05/2024 24 07:00 - 19:00
Pilot Technician Rhodri Thomas 28/03/2024 70 07:00 - 19:00
Pilot Technician Will Dougal 13/05/2024 24 07:00 - 19:00

D) Operational Summary :
Today's Summary : Complete Umbilical Termination.

Look Ahead : Complete mobilisation, carry out Vehicle Wet Test.

E) Operational Analysis : Today Previously Project Total


Mobilisation/ Demobilisation 24:00 576:00 600:00
Operational 00:00 00:00 00:00
Operational Standby 00:00 00:00 00:00
Operational Standby - WOW 00:00 00:00 00:00
Downtime - Environmental Influence 00:00 00:00 00:00
Downtime - Asset Breakdown 00:00 00:00 00:00
24:00 Total 24:00 1.0 576:00 24.0 600:00 25.0

F) Dairy of Events :
Time KP Description
Vessel at anchorage Batam
Pre Shift TBT completed.
Complete stripping and cleaning of Umbilical cores.
Complete routing of umbilical through vehicle and into Termination JB.
Added protection to Umbilical in necessary areas.
Temporary weather protection placed above Termination JB due to bad weather.
Make off and connect all Umbilical conductors and fibres.
Full check of control van and vehicle safety circuits.
ROV powered on Telemetry established.

G) Spares Issued From Inventory :


Qty Part No. Description
6 ST SM Hotmelts
1 Box of Chem wipes
1 5 meters of 40mm spiral wrap.
16 10mm x M12 copper tube lugs
1 3 meters 20mm Heat shrink
1 Pack of 25 1.0mm bootlace crimps
1 Pack of 10 6mm2 insulated crimps M6 hole

H) Acknowledgement
Comment : Pharos Offshore Group

Mark Maddison
Equipment Superintendent
Comment : DABN

Resvicar Alwan
Project Coordinator

E Shed, Port of Blyth, Blyth. Northumberland


Tel: +44 (0) 1242 574041 www.pharosoffshoregroup.com Page 1 of 1