Daily Progress Report
Rev. : 9
A) Contact Details :
Email - Equipment Superintendent mark.maddison@pharos-offshore.com Email - Project Manager andy.ratford@pharos-offshore.com
Tel. - Equipment Supervisor Richard.McLaughlin@pharos-offshore.com Tel. - Project Manager
B) Equipment On-Hire :
Pharos Offshore Group UTV400
Pharos 3rd Party
C) Personnel :
Date No. Days Date due to
Position Name Shift Pattern
Embarked Onboard Disembark
Superintendent Mark Maddison 25/02/2024 104 07:00 - 19:00
Supervisor Richard McLaughlin 13/05/2024 26 07:00 - 19:00
Pilot Technician Rhodri Thomas 28/03/2024 72 07:00 - 19:00
Pilot Technician Will Dougal 13/05/2024 26 07:00 - 19:00
D) Operational Summary :
Today's Summary : Complete Wet Test, Vessel departs for Mercassar.
F) Dairy of Events :
Time KP Description
Vessel at anchorage Batam
Pre Shift TBT completed.
Complete VAC test on POD
Complete set of Pre dive checks.
Fitted Jabsco.
Complete system Wet Test.
Complete sea fastening of all deck equipment.
Vessel departs for Mercassar.
H) Acknowledgement
Comment : Pharos Offshore Group
Mark Maddison
Equipment Superintendent
Comment : DABN