procedureload tes overhead crane at CW Pump House
procedureload tes overhead crane at CW Pump House
1 of 7
- SDCC : Original
- CNEEC : Copy
- Originator: Copy
Hartanto H. Alamsyah Iman Paryaman Agus Subagyo
Rigging Engineer BOPArea Manager Site Manag. Site Manager
Rep
ISSUED EFFECTIVE
REV. NO BRIEF OF REVISION
DATE DATE
0 28– 9 – 2009 28 – 9 – 2009 ISSUED FOR APPROVAL
TABLE OF CONTENT
No. Descriptions Page
1 Title 1 of 7
2 Scope 3 of 7
3 Objective 3 of 7
4 Reference 3 of 7
5 Preparation of Load Test 3 of 7
6 Sequence of Load Test 3 of 7
1. TITLE
Load Test Procedure For Over Head Crane at Circulating Water Pump
House.
2. SCOPE
This procedure describes the load test over head crane capacity 32 ton and 10
ton at circulating water Pump House, Indramayu 3 x 330 MW Coal Fire Steam
Power Plant. In this connection, if there is any modification to this instruction
shall be carried out after reviewed with the concern person.
3. OBJECTIVE
This procedure is the guidance for related Supervisor or Engineer for load test
over head crane.
4. REFERENCE
Dynamics load test is aimed to test and verify the functions of brakes and
every part of the crane. First dynamics load test for ever part of crane should
be conducted respectively. Then, conduct coordinated test by starting two
parts in same time (Attn: the main/auxiliary hooks should not be operated in
same times)
Add load exceeds 10% than rated loads on the hoist. During the test, the
test load should not active reversely when air-starting the hanging test load;
when conducting the braking test during the falling process, hook should not
slide off. When test is in process, operation intermission time should be
reserved according to the electrifying persistence ratio of the motor of this
machine and then conduct the control according to operation regulations, and
the accelerated speed, decelerated speed and speed should be limited in the
normal range. If all the parts have successfully passed the functions test, and
during the following visual inspection, no damage have been found on the
parts, no connections is loosen or damaged, motor and their control device
run normally, position limit switches and interlock protection device active
properly and precisely, then, the test result is qualified.
Static load test is aimed to inspect the carrying capacity of crane and each
part of crane. The static test for main hook and auxiliary hook should be
conducted respectively. Before conducting the static load test for main hook,
DOCUMENT NO. :
LOAD TEST PROCEDURE FOR OVER HEAD CRANE P-T3109-RED-013
AT CIRCULATING WATER PUMP HOUSE ISSUED DATE :
28 September 2009
place the no-load trolley at the center position of span and determine the
reference point.
Add load exceeds 25% than rated loads on the hoist. The hoisting height
ranges from 100 mm to 200 mm and suspending time should be no less than
10 minutes. After unloading, check the basing-point of girder to see whether
the permanent distortion exist. Repeat the above test for tree times and no
permanent distortion should exist. After static test, if cracks, permanent
distortions, painting damages or damages that affect the performance and
safety of crane have not been found, and no connections is loosened or
damaged, then, the test result is qualified.
PREPARATION WORKS
TRIAL RUN
INSPECTION
INSPECTION
(6.1/6.2/6.3)
INSPECTION
INSPECTION
FINAL
INSPECTION AND
HANDLING OVER