GRP-08-TS000-SGC-ICA-CRS-00005_Rev01
GRP-08-TS000-SGC-ICA-CRS-00005_Rev01
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ICA-CRS-00005 01 B 06/07/2024 C = Approved with comments & F = No action
resubmit
1.0
GRP/PMC Comments Rev00 Contractor’s Reply
1
QA SGC shall attach valid certificate for Ministry of commerce. NOTED, VALID CERTIFICATE ADDED
1.1 GRP/PMC Comments Rev01 Contractor’s Reply
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 1 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ICA-CRS-00005 01 B 06/07/2024 C = Approved with comments & F = No action
resubmit
QA Attached closed.
2. GRP/PMC Comments Rev00 Contractor’s Reply
QA Member certificate of chamber of commerce is expired. NOTED, VALID CERTIFICATE ADDED
2.1 GRP/PMC Comments Rev01 Contractor’s Reply
QA Added closed.
3. GRP/PMC Comments Rev00 Contractor’s Reply
QA A valid Zakat & Saudization certificate is to be attached. NOTED, VALID CERTIFICATE ADDED
3.1 GRP/PMC Comments Rev01 Contractor’s Reply
QA Attached closed.
4. GRP/PMC Comments Rev00 Contractor’s Reply
QA International certifications for ISO: 9001:2015, ISO 14001:2015 are expired. NOTED, VALID CERTIFICATE ADDED
4.1 GRP/PMC Comments Rev01 Contractor’s Reply
QA Added closed.
5. GRP/PMC Comments Rev00 Contractor’s Reply
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 2 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ICA-CRS-00005 01 B 06/07/2024 C = Approved with comments & F = No action
resubmit
Provide the table of content with page number, in which all the required
QA Noted, the page content please refer to page 4
information as per the PQ checklist are traceable
5.1 GRP/PMC Comments Rev01 Contractor’s Reply
QA Attached Closed.
6. GRP/PMC Comments Rev00 Contractor’s Reply
In accordance with the Client Specification 40 70 00, the HDPE conduits and
QA Noted, confirmed
fittings shall comply with DIN 16874. The Contractor to confirm
QA Confirmed
7. GRP/PMC Comments Rev00 Contractor’s Reply
QA Contractor to confirm the following shall be complied, subject for detailed Noted , confirmed
review in the material submittal.
1. The conduit shall be HDPE dual duct with a size of DN40 for each duct.
2. The minimum length in the drum shall be 1000 m.
3. Material density is >=0.74 g/cm3
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 3 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ICA-CRS-00005 01 B 06/07/2024 C = Approved with comments & F = No action
resubmit
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 4 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A
CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ICA-CRS-00005 01 B 06/07/2024 C = Approved with comments & F = No action
resubmit
Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 5 of 5