CONSTRUCTION OF TSE NETWORK FOR

GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-CRS-00003 01 B 04/07/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


SUB -003420: GRP-08-TS000-SGC-ELE-ITP-00003 01 ITP for Installation & Testing of Electrical Panel Boards.

Reviewed by GRP/PMC Replied by Contractor


Received Replied Doc. Received Replied Doc.
Doc. Rev. No CRS Status Doc. Rev. No
Date Date Status Date Date Status
00 14/05/2024 26/05/2024 IFA C 00 26/05/2024 01/06/2024
01 01/07/2024 04/07/2024 IFC B

Name Abbreviation Discipline


Junaid Ahmed JA Electrical
Reviewers

1 GRP/PMC Comments Rev00 Contractor’s Reply


JA Contractor to confirm whether FAT Manufacturer ITP shall be submitted Noted and Confirmed that FAT, ITP will be submitted
separately? separately.
If this ITP is considering as manufacturer ITP so contractor shall attach the
FAT procedure and Manufacturer ITP along with all required tests and

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 1 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-CRS-00003 01 B 04/07/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


SUB -003420: GRP-08-TS000-SGC-ELE-ITP-00003 01 ITP for Installation & Testing of Electrical Panel Boards.

certificates.
Also, Document title shall be updated if it is manufacturer ITP
1.1 GRP/PMC Comments Rev01 Contractor’s Reply
JA Closed as confirmed that the FAT ITP shall be submitted separately.
2 GRP/PMC Comments Rev00 Contractor’s Reply
In ITP for section Specification/Drawing and Acceptance Criteria, Contractor to
add following detail for each activity. 1.complied and added.
1) Client Specs, clause, and part number 2.. complied and added.
JA
2) Wiring Drawing, Panel schedule, IFC Drawing 3. MST: complied and added. & Material submittal on going.
3) MST, Material submittal numbers 4)third party name not applicable now.
4) Third Party name shall be added (If applicable)
2.1 GRP/PMC Comments Rev01 Contractor’s Reply
1) Closed.
2) Attached drawings are not related to group-5A, please add only
JA references from group-5A.
3) Closed
4) Closed as confirmed.
3 GRP/PMC Comments Rev00 Contractor’s Reply

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 2 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-CRS-00003 01 B 04/07/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


SUB -003420: GRP-08-TS000-SGC-ELE-ITP-00003 01 ITP for Installation & Testing of Electrical Panel Boards.

Complied and filled.


QCF1 FOR Material Receiving Inspection.
JA Checklist shall be filled as per ITP activities. QCF1 FOR Material Handling, Storage and Preservation.
QCF2 FOR Installation Inspection of Panel Boards.
QCF3 FOR Testing of Panel Boards.
3.1 GRP/PMC Comments Rev01 Contractor’s Reply
JA Closed
4 GRP/PMC Comments Rev00 Contractor’s Reply
1-Complied and noted, will be submitted FAT, ITP for panel board.
Contractor to note that two ITPs shall be submitted separately as following.
2- Complied and noted, will be submitted ITP for panel board
JA 1) FAT Inspection and Test Plan for Panel Board Installation.
2) Inspection and Test plan for Installation and Testing for Panel board

4.1 GRP/PMC Comments Rev01 Contractor’s Reply


JA Closed with note.
1) Closed as confirmed that the FAT ITP shall be submitted separately

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 3 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-CRS-00003 01 B 04/07/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


SUB -003420: GRP-08-TS000-SGC-ELE-ITP-00003 01 ITP for Installation & Testing of Electrical Panel Boards.

2) Closed with note. This submitted ITP shall not need to submit again.
5.1 GRP/PMC Comments Rev01 Contractor’s Reply
As per client specs 26 24 16 clause 3.3 part b, please add more testing to ITP
activity 4.0 on page 3. Please refer below points,
JA
1) Continuity for grounding system
2) Insulation resistance test
6.1 GRP/PMC Comments Rev01 Contractor’s Reply
JA Following to be corrected and added

1) Drawing number to added as picture below

2) Need to add one more page or edit somewhere suitable to write the

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 4 of 5
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP FIVE A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-SGC-ELE-CRS-00003 01 B 04/07/2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


SUB -003420: GRP-08-TS000-SGC-ELE-ITP-00003 01 ITP for Installation & Testing of Electrical Panel Boards.

value of voltage levels for phase-to-phase, phase-to-neutral etc.


7.1 GRP/PMC Comments Rev01 Contractor’s Reply
Please confirm, It is contractor responsibility that provided detail is completely
JA
as per client specs, drawing and manufacturer.
8.1 GRP/PMC Comments Rev01 Contractor’s Reply
The documents/activity related to shelter, or its equipment shall be on hold
JA
until it is finalized from the client.

Remarks: Comments given in this Comment Sheet are for technical clarification only and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 5 of 5