Date : 04 / 05 / 2024
WEEKLY REPORT N°17
Réf :
Written by : NDINDJOCK Jacques Martial (Monotoring Civil Engineer)
_____________________________________________________________________________
Weekly report N°17- from 29 April to 04 May 2024
1/7
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS
___________________________________________________________________________
Table des matières
1. Project characteristics .......................................................................................... 3
3. Contractor resources............................................................................................ 4
_____________________________________________________________________________
Weekly report N°17- from 29 April to 04 May 2024
2/7
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS
___________________________________________________________________________
1. Project characteristics
N° Qualification Number
1 Head of Mission 01
2 Manager of the topography, earthworks and geometric 01
design work package
3 Geotechnical Manager 01
4 Monotoring Civil Engineer 01
5 Geotechnical monitoring engineer 01
6 Head of topography brigade 01
7 Geotechnical engineer 01
8 Maintenance engineer 01
9 Assistant Geotech engineer 01
10 Topographer operator 01
11 Monitoring technician 01
12 Monitoring laboratory 01
13 Assistant topographer 01
14 Driver 01
_____________________________________________________________________________
Weekly report N°17- from 29 April to 04 May 2024
3/7
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS
___________________________________________________________________________
3. Contractor resources
_____________________________________________________________________________
Weekly report N°17- from 29 April to 04 May 2024
4/7
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS
___________________________________________________________________________
Others
Designation Number Comments
Total station 02
Level for topographic survey 01 To be replaced
4. Work for the week (see pictures at the end of the document)
Rain on the night of 02/05/2024 flooded the site from 03 to 04/05/2024. This was a
blockage for the continuity of the earthworks these two days.
• The supply of pozzolan will have to be resumed in order to cover the access
roads already available;
_____________________________________________________________________________
Weekly report N°17- from 29 April to 04 May 2024
5/7
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS
___________________________________________________________________________
• The itinerary of the access road from the KSA gatehouse to PF2 must follow the
alignment of the project axes; to this end, the TSP of this road must be brought
up to the project grade, then backfilled with pozzolan;
• BHYGRAPH has been asked to prepare a new file of quantities due to the
modifications made to the platforms, to enable the project owner to make a
decision on this matter;
• CAMBUILD's bid for the RN3-KSA roadworks is awaited;
• The trench along the RN3-KSA track will be used to pass OMNIUM's electrical
cables; CAMBUILD will not be able to start work on this track until OMNIUM has
passed the cables.
The quantitative progress of the work in relation to the basic BOQ is approximately
92%, compared with a time consumption of 130%. This progress is 90% in relation to
the Quantity Index Number 2. It should be noted that CAMBUILD will have to speed
up the large-scale earthworks on platform N4 in addition to the adjustments being
made on platform 1. It should also be noted that the supply of pozzolan remains low
(around 30%) compared with the estimated quantities.
_____________________________________________________________________________
Weekly report N°17- from 29 April to 04 May 2024
6/7
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS
___________________________________________________________________________
Layout of the RN3-KSA roadway RN3-KSA Layout of backfill altitude at PF1 Cut at PF1
Backfilling at PF1. Adjustment of UES at PF1. Cut and Adjustment of the excavation slope at
PF4
_____________________________________________________________________________
Weekly report N°17- from 29 April to 04 May 2024
7/7