Professional Documents
Culture Documents
1716139037529
1716139037529
25
s
The top 25 Project Management KPIs
1 # Earned man-hours
the
2 % Delivery deadlines met
3 % Project resource utilization
25
4 # Schedule performance index (SPI) KPI
5 # Cost schedule index (CSI)
6 % Project budget variance at project end
7 # To complete schedule performance index (TSPI)
8 % Timely production of management reports
9 % Project schedule variance
10 # Project issues identified
11 % Order value variance from original contract value
12 # Conflicts arising during the project
13 # To complete performance index (TCPI)
14 % Overdue project tasks
15 $ Estimate at completion (EAC)
16 # Cost performance index (CPI)
17 % Requirements changed during project execution
18 $ Cost variance
19 # Project delay
20 # Time per project task
21 $ Actual cost of work performed (ACWP)
22 $ Budgeted cost of work performed (BCWP)
23 # Third party non-conformity identified during inspections
24 % Project milestones missed
25 % Project completion predictability
1 the
25
# KPI
Earned Measures the total man-hours
corresponding to the
man-hours completed work in place.
A = $ Total Budget
B = $ Budget cost of work performed (BCWP)
C = $ Budget cost of work scheduled
(BCWS)=(A-B)/(A-C)
A value above 1 indicates that
the project team can be
lenient in utilizing the remaining
time
allocated to the project.
A value below 1 indicates the
project team needs to work
harder in utilizing the
remaining time allocated to the
project.
Eng.Mohamed Abd Elhakiem
8 the
25
% KPI
Timely Measures the percentage of
production management reports
produced on time out of the
of total management reports due.
management
reports
To evaluate the management
reporting efficiency and
compliance with the agreed
reporting schedule.
(A-B)/B*100
To indicate the
collaboration quality
between the project team
members.
A = # Tasks overdue
B = # Current tasks
(A/B)*100
CPI = A/B,
Targets should be higher than 1, this
indicating that the conditions of cost
efficiency for the project are
considered to be favorable.
A = # Requirements changed
B = # Initial requirements
(A/B)*100
Measurement and reporting requires well-
functional systems to monitor changes to
project specifications (such as a ticketing
system, in the case of software
development)
(A-B)
Targets higher than 0 indicate that the
actual costs are under budget, which can
mean a well managed
project.
If targets are lower than 0, this can indicate
the lack of cost efficiency in project
management, since the actual costs are
higher than the earned value.
A = # Milestones missed
B = # Project milestones
(A/B)*100
EOT Procedures.
https://www.udemy.com/course/construction-claims-21-major-point
******************************************************************************************
Dynamic Dashboard &Reporting.
Interactive Dashboards & EVM.-Arabic
https://www.udemy.com/course/earnedvalue2019
******************************************************************************************
Planning and Scheduling Professional.
PSP Study Guide
https://www.udemy.com/course/planning