Bill of quantiy and specification

Clinet :
project:SHEAD
Location: Sheraro
SUMMARY
ITEM DESCRIPTION TOTAL AMOUNT
A.SUB STRUCTURE
1 Excavation and earth work 68,612.01
2 Concrete work 62,812.87
3 Masonry work 58,603.18
Sub Total (A) 190,028.06
B. SUPER STRUCTURE
1 Concrete work 108,164.08
2 Block work 141,711.77
3 Carpentry and Joinery work 146,633.55
4 Roofing work 95,850.32
5 Floor and wall Finishing work 27,479.64
6 Painting work 64,072.80
7 Electrical Instalation Err:509
Sub Total (B) Err:509
Total (A + B) Err:509
GRAND TOTAL Err:509
BILL OF QUANTITY AND SPESFICATION
CLIENT: ATO AMANIAL HADUSH TEFERI
PROJECT: LABORATORY AND
MEDICAL STOR
LOCATION : SHERARO

ITEM DESCRIPTION TOTAL AMOUNT


A.SUB STRUCTURE
1 EXCAVATION AND EARTH WORK 68,612.01
2 Concrete work 62,812.87
3 Masonry work 58,603.18
Sub Total (A) 190,028.06
B. SUPER STRUCTURE
1 Concrete work 108,164.08
2 Block work 141,711.77
3 meatl work 146,633.55
4 Roofing work 95,850.32
5 Carpentry and Joinery work 27,479.64
6 Finishing work 64,072.80
7 painting 12,351.60
8 Electrical Instalation 49,474.96
Total ( B) 645,738.72
Total (A + B) 835,766.78
GRAND TOTAL 835,766.78

FLUX Design Lab


Specification and Bill of Quantities
Ite
m Description Unit Quantity Unit Price Total Amount
No
A. SUB STRUCTURE
1.EXCAVATION AND EARTH WORK
Clear off the site to remove the top soil to an average 72 48
1.1
depth of 20cm m2 3,456.00
1.2 Bulck excavation to a depth of not exceeding 50cm m3 36.00 300
1.3 Excavation trenches foundation ,pit excavation to a m3 42.00 16,128.00
depth of not exceeding 120cm 384

1.4 Back fill under hard core, around foundation wall and m3 4.32 1,036.80
footing column with selected materials & well
compacted at every 20 cm. select material from site. 240
Back fill under harde, around foundation wall and
1.5 footing column with selected materials & well m3 26.40 12,658.80
compacted at every 20 cm. select material from out
side the site. 479.5
Cart away surplus excavated material and deposite at 454.39
1.6 distance not exceeding 2km from site. m3 39.00 17,721.21
25 cm thick basaltic or equivalent stone hard core well 292.6
1.7 rolled consolidated and blinded with crushed stone. m3
72.00 21,067.20

Total carried to Summary 68,612.01


2. CONCRETE WORK
5cm thick lean concrete in class C-5 (150kg cement
2.1 /m3) under foundation stone masonary wall & footing
pad mix concrete(cement,sand,gravel)
A) Under Grade beam m2 12.60 166.79 2,101.55
concrete in C-25 ( 360kg cement/m3 ) mix concrete
(cement,sand,gravel)filled in to form work and vibrated
2.2 around reinforcement bar. (form work and
reinforcement bar measured separately).
A) In grade beam m3 1.92 7,456.19 14,315.88
B) In 10cm thick concrete ground floor slab m2 72.00 118.43 8,526.96

FLUX Design Lab


Provide,Cut & Fix in Possition Form Work for
footing,column& beams. Price including with all
neccessories accessories (material quality approved by
the engineer)
A) Grade beam m2 533.69
steel reinforcement bars according to structural
drawings. Price shal include supply,cutting, bending,
2.3 placing in position and tying wires.(material quality
approved by engineer)
A) Ø 8 mm Deformed bar Kg 130.82 146.82 19,207.58
B) Ø 12 mm Deformed bar Kg 131.42 141.99 18,660.89
Total carried to Summary 62,812.87
3. MASONRY WORK
50cm thick trachytic or equivalent roughly dressed
stone masonry foundation wall bedded in cement sand
3.1 mortar (1:4) ratio.(material quality approved by the
engineer)
m3 36.00 2,548.96 91,762.56
50 cm Thick Trachytic or equivalent one side semi-
dressed stone masonry wall above natural ground level
3.2 beded in cement sand mortar internally & externally
left for pointing or plastering (1:3)ratio (material
quality approved by the engineer)
m3 21.60 2,713.11 58,603.18
Total carried to Summary 58,603.18
B. SUPER STRUCTURE
1. CONCRETE WORK
concrete in C-25 ( 360kg cement/m3 ) mix concrete
(cement,sand,gravel)filled in to form work and vibrated
1.1 around reinforcement bar. (form work and
reinforcement bar measured separately).
A) In elevation columns. m3 1.06 7,456.19 7,873.74
B) In floor beams. m3 1.92 7,456.19 14,315.88
Provide,Cut & Fix in Possition Form Work for
footing,column& beams. Price including with all
1.2
neccessories accessories (material quality approved by
the engineer)
A) In elevation columns. m2 26.40 533.12 14,074.37
B) In floor beams. m2 21.60 533.12 11,515.39
steel reinforcement bars according to structural
drawings. Price shal include supply,cutting, bending,
1.3 placing in position and tying wires.(material quality
approved by engineer)
A) Ø 8 mm Deformed bar Kg 164.35 141.99 23,335.54
D) Ø 14 mm Deformed bar Kg 260.93 141.99 37,049.17
Total carried to Summary 108,164.08

FLUX Design Lab


2. BLOCK WORK
20*20*40cm thick hollow concrete block wall beded in
2.1 cement sand mortar 1:3 ratio (class of H.C.B should be m2 169.20 837.54 141,711.77
class"B"
Total carried to Summary 141,711.77
3.Metal Work
supply and fix metal doors shall be fabricated
from locally manufactured 3.8 *1.2 mm thicknes
LTZ tubular steel profile cover 1.25mm thick flat
iron sheet metal price including hinges,
3.1 cylindrical locks ,one coats of antirust & two m2
coats oil paint, with all its accessories,(drawing
& material quality approved by the engineer)

a) Door size 200*275 cm m2 16.50 6,982.55 115,212.08


Supply & fix METAL window of 3.8*1.25mm
thick LTZ tuber steel profile cover 1.25 mm
thick flat iron sheet meatal price includes
3.20 frame, handle & with other accessories, m2 4.50 6,982.55 31,421.48
(material quality approved by the engineer).

Total carried to Summary 146,633.55


4. ROOFING WORK
Roof covering in G-30 corrugated galavanized
iron sheet price including roof ridge cover fixed
to purlins with dome headed galvanized nails
& with all its accessories(purlin measured
4.1 separetely ) and roof cover measured in m2 81.92 1,042.23 85,379.48
horziontal projection (material quality approved
by the engineer)l

Supply & fix G-28 galvanized iron sheet metal gutter


devolepment length 100 cm welded at joints. provide
4.2 ml. 12.00 443.18 5,318.16
2% slope towards down pipe & shall include 3 coats of
oil paint.

Supply & fix diameter 80 mm PVC Down pipe fixed to


4.3 wall with metal straps welded joints towards to ground ml. 18.00 286.26 5,152.68
& shall price inculds elbow & 3 coats oil paint.

Total carried to Summary 95,850.32


5-CARPENTARY& JOINARY WORK -
All structural members shall be well seasoned
and free of harmful defects. Each truss shall be
painted anti- termite solution and firmly fixed to
R.C beams with Dia 6mm plain bars &with
other accessories( material quality approved by
the engineer)

5.1 -
a)Diametr 10-12 cm eucalyptus upper & lower,
members of truss. ml 72.00 107.99 7,775.28
b)Diametr 8-10cm eucalyptus vertical &
diagonal truss member ml 36.00 96.59 3,477.24
5.2 Diametr 8-10cm eucalyptus purlins. ml 168.00 96.59 16,227.12
Total carried to Summary 27,479.64

5. FLOOR AND WALL FINISHING WORK


Apply 3 coats of plastering in cement sand
mortar (1:3) up to fine finish to all indicated
5.1 internal Hollow concrete block/HCB/wall, m2 169.20 234.00 39,592.80
column, beam

5.2 cement screed floor finish m2 72.00 340.00 24,480.00


Total carried to Summary 64,072.80

FLUX Design Lab


6. PAINTING WORK
Apply 3 coats of approved type plastic paint to
6.1 m2 169.20 73.00 12,351.60
all indicated internal
Total carried to Summary 12,351.60
8, ELECTRICAL INSTALLATION
Internal Electircal instaletion

Supply,install & connect surfase/flash mounted sub-


distribution board ,SDB ,made of steel with
locable doors connected to 4X4mm2 cable with 16A
main circuit breaker ,3-phase & also consist of and with
phase neutral with consisting
8.1 No 1.00 10,524.32 10,524.32
of
2ps ACB of 16A-3ph
3pc ACB of 10A-3ph
Complete with bus bar rating of 25A & earthing lead
all accessories wirh 25% Reserve

Supply & install light points fed through PVC insulated


conductors of 2x2.5mm2 in thermoplastic conduits of
8.2 dia -13.5mm for recessed installation price including No 6.00 895.22 5,371.32
junction boxes
with covers (screw type) & insulating caps .
Supply & install fan points fed through PVC insulated
conductors of 2x2.5mm2 in thermoplastic conduits of
8.3 dia -13.5mm for recessed installation price including No 4.00 895.22 3,580.88
junction boxes
with covers (screw type) & insulating caps .

Supply & install flush mounted socket outlet point of


16A, single phase & with earthing contact fed through
PVC insulated conductors of 3x2.5mm2 in the
8.4 No 6.00 2,424.33 14,545.98
thermoplastic condits of dia 16mm for recessed
installation price including junction boses with covers
& insulating caps - all complete,
Socket fittings -
Supply and fix Flush or Surface mounting two way
8.5 no 6.00 247.16 1,482.96
socket outlet 16-25 A/1ph
Switch fittings -
A. Supply and fix flush or surface mounted two way
8.6 No 4.00 188.94 755.76
switch with off indicatore lamp
Supply and install Fan fitting for cilling complete with
8.7 all the necessary accessories.( material quality No 3.00 2,851.30 8,553.90
approved by the engineer)
Light fittings
A. Supply and fix LED bubl light o -type 40w lamps
8.9 energy saving LED bubl type with lamp holder and pcs 6.00 776.64 4,659.84
all accesoceries.

TOTAL CARRIED TO SUMMARY 49,474.96

FLUX Design Lab


PROJECT - BLOCK D
LOCATION - SHERARO
CLIENT -
NO L/W/D QTY DESCRIPITION NO L/W/D QTY DESCRIPITION
A. SUB STRUCTURE 2. Concrete Work
1. EXCAVATION & EARTH WORK 2.1, 5cm thick lean concrete.
1.1, Site Clerance A) Under Footing
1 12.00 2.4
6.00 2.4
72.00 M² TOTAL -
1.2, Bulk Excavation - M2 TOTAL
1 12.00 L= 36.25m
6.00 W= 11.8m B) Under Grade beam
0.50 D= 0.50 m AXIS: A,C
36.00 2 12
0.3
36.00 M³ TOTAL 7.20 M
2

1.3, Trench Excavation in ordinary soil AXIS: 1,7,9


not exceeding 150cm from NGL. 3 6
2 12.00 0.3
5.40 M
2
1.00
1.00 12.60 M2
24.00 M³ 12.60 M2 TOTAL
2.2, Reinforced concrete of class C-25.
3 6.00 A) In foundation footings
1.00 2.2 F1
1.00 2.2
18.00 M³ 0.5
42.00 M³ TOTAL -
1.4, Excavation for foundation footings
not exceeding150cm from NGL. 0.00 M3 TOTAL
F1
2.70 B) In foundation columns
2.70 0.25 C1
1.50 0.25
- M³ 1
- M³
0.00 M³ TOTAL 0.00 M3 TOTAL
1.5, Back fill around foundation footings. C) In grade beam
F1
2.70 2 12.00
2.70 0.20
1.50 Total Pit Volume 0.20
- M³ 0.96 M³
2.40
2.40 Deduction for Concrete Volume 4 6.00
0.60 0.20
- M³ 0.20
- M3 TOTAL 0.96 M³
1.6, Back fill Under mesh 1.92 M³
1 12 1.92 M3 TOTAL
0.6 D) 10cm mass concrete at ground floor
0.6 1 12.00
4.32 6.00
4.32 M3 TOTAL 72.00
1.7, Cart away 72.00 M2 TOTAL
2.3, Form work
1 36.00 A) Foundation footings
42 2.20 F1
0 0.50
78.00 - M2
78.00 M3 TOTAL - M2 TOTAL

FLUX Design Lab


NO L/W/D QTY DESCRIPITION NO L/W/D QTY DESCRIPITION
B) Foundation columns B. SUPER STRUCTURE
0.25 C1 1. CONCRETE WORK
1.50 1.1, Reinforced concrete of class C-25.
- M2 A) In elevation columns.
- M2 TOTAL C1
C) Grade beam 8 0.2
AXIS: A,C 0.2
2 12 3.3
2 0.2 1.06
9.60 M
2

AXIS: 1,7,9 1.06 M3 TOTAL


4 6
2 0.2 B) Intermidate beams @+ 3.6 & +4.8
9.60 M
2

19.20 M2 TOTAL 2 12.00


2.4, Reinforcement bars. 0.20
0.20
A) Ø 8 mm Deformed bar 0.96 M³

130.82 4 6.00
130.82 Kg. TOTAL 0.20
0.20
B) Ø 10 mm Deformed bar 0.96 M³
0.00 B) In Top tie beams @ +8
0.00 Kg. TOTAL
AXIS: 1,7
C) Ø 12 mm Deformed bar 0 25.40
131.42 0.40
131.42 Kg. TOTAL 0.40
- M³
D) Ø 14 mm Deformed bar AXIS: A,K
0 60.80
0.00 0.40
0.00 Kg. TOTAL 0.40
- M³
E) Ø 16 mm Deformed bar 1.92 M3 TOTAL
0.00 1.2, Form work
0.00 Kg. TOTAL 8 0.25 A) In elevation columns.
4 3.3
26.40 M
2
F) Ø 20 mm Deformed bar
0.00
0.00 Kg. TOTAL 26.40 M2 TOTAL
g) Ø 24 mm Deformed bar B) Intermidate beams @+ 3.6 & +4.8
0.00
0.00 Kg. TOTAL 2 12.00
3. Masonary 0.60
14.40 M
2
below NGL
2 36.00 2 6.00
0.5 0.60
7.20 M
2
1
36.00 M3 TOTAL B) In Top tie beams @ +8
Above NGL 0 25.40
2 36.00 1.20
0.5 - M2
0.6 21.60 M3 TOTAL 0 60.40
1.20
- M
2

21.60 M2 TOTAL
NO L/W/D QTY DESCRIPITION NO L/W/D QTY DESCRIPITION
1.3, Reinforcement bars.
A) Ø 8 mm Deformed bar
164.35
164.35 Kg. TOTAL

B) Ø 10 mm Deformed bar
0.00
- Kg. TOTAL

C) Ø 12 mm Deformed bar
131.42
131.42 Kg. TOTAL

D) Ø 14 mm Deformed bar
260.93
260.93 Kg. TOTAL

E) Ø 16 mm Deformed bar
0.00
- Kg. TOTAL
F) Ø 20 mm Deformed bar
0.00
- Kg. TOTAL
F) Ø 20 mm Deformed bar
0.00
- Kg. TOTAL
2. BLOCK WORK
2.1, 20*20*40cm thick concrete block
2 12
4.7 112.80 M2

3 6
4.3 77.40 M2

-2 1.5 deduction of window


1.5 -4.50 M2
deduction of doors
-3 2
2.75 -16.50 M2

169.20 M2 TOTAL
4. METAL WORK
3 2 4.1 metal Doors
2.75
16.5 M2
16.5 M2 TOTAL
4.2 metal windows

2 1.5
1.5
4.50 M2
4.50 M2 TOTAL
5. STEEL WORK

4
0 No

FLUX Design Lab


NO L/W/D QTY DESCRIPITION NO L/W/D QTY DESCRIPITION
5.2 A. Plate 300*300*12 6. ROOFING WORK
40 6.1 G-30
0 No 1 12.80
6.40
0 No 81.92 M
2

5.3 RHS
a. 60*60*3 Diagonal 81.92 M2 TOTAL
25 21.50
5.20 2795
2795.0 kg 6.2 G-28 sheet metal gutter.
b. RHS 60*60*3 Vertical 1 12.00
25 7.00 12.00 ml
5.20 910
0 25.40
910.0 kg - ml

c. RHS 80*80*3.5 bottom 12.00 ml. TOTAL


25 13.20
5.20 1716 kg
14 13.00 6.3 PVC Down pipe.
62.56 11385.92 kg 6 3.00
13101.9 d.RHS 80*80*3.5 top 18.00 ml
32 13.40
62.56 26825.728 kg 7. FLOOR AND WALL FINISHING WORK
25 0.00 6.1, Apply 3 coats of plastering
62.56 0 kg 2 169.20
26825.7 338.40
338.40 M2 TOTAL
e. RHS purlins 100*60*2 bottom
14 40.00 6.2 cement screed floor finish
4.80 2688 kg 1 12
2688.0 6
72.00 M2 TOTAL

FLUX Design Lab


SUMMARY FOR SUB STRUCTURE

Length No. of Dia.12


LOCATION TYPE Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)

331.20 0.00 148.00 0.00 0.00 0.00 0.00


TOTAL LENGTH (M) 331.20 0.00 148.00 0.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 130.82 0.00 131.42 0.00 0.00 0.00 0.00 262.25

REINFORCEMENT SCHEDULE
FOUNDATION Reinforcement)

Length No. of Dia.12


LOCATION AXIS Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)
FOUNDATION 2.60 29 40

TOTAL LENGTH (M) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0
REINFORCEMENT SCHEDULE
(FOUNDATION COLUMN Reinforcement)

Length No. of Dia.12


LOCATION AXIS Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)

FOUNDATION COLUMN 6.50 10 40

1.30 65 40

TOTAL LENGTH (M) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
REINFORCEMENT SCHEDULE
(GRADE BEAM Reinforcement)

Length No. of Dia.12


LOCATION AXIS Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)
GRADE BEAM AXIS A,D 12 6.5 4 2 52.00
6.2 4 2
AXIS 1,3,8,11 12 12.0 4 2 96.00
6.3 8 4
8 0.9 62 2 111.60
8 0.9 122 2 219.60

TOTAL LENGTH (M) 331.20 0.00 148.00 0.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 130.82 0.00 131.42 0.00 0.00 0.00 0.00
REINFORCEMENT SCHEDULE
(Mesh Reinforcement)

Length No. of Dia.12


LOCATION AXIS Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)
Ground Floor Mesh 49.00 126 1
21.00 181 1

TOTAL LENGTH (M) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SUMMARY FOR SUPER STRUCTURE

Length No. of Dia.12


LOCATION TYPE Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)

416.07 0.00 148.00 216.00 0.00 0.00 0.00


TOTAL LENGTH (M) 416.07 0.00 148.00 216.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 164.35 0.00 131.42 260.93 0.00 0.00 0.00 556.70

REINFORCEMENT SCHEDULE
(Elevation Columns Reinforcement)

Length No. of Dia.12


LOCATION TYPE Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)
Elevation Columns 1 14 4.50 6 8 216.00
ST 8 1 24 8 194.67
4.00 10 36
1.50 28 36

TOTAL LENGTH (M) 194.67 0.00 0.00 216.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 76.89 0.00 0.00 261.36 0.00 0.00 0.00

REINFORCEMENT SCHEDULE
(BEAM Reinforcement)

Length No. of Dia.12


LOCATION AXIS Dia. (in mm) Dia.8 (mm) Dia.10 (mm) Dia.14 (mm) Dia.16 (mm) Dia.20 (mm) Dia.24 (mm)
(in meter) Bars Elements (mm)
BEAM AXIS 12 6.5 4 2 52.00
6.2 4 2
AXIS 12 12.0 4 2 96.00
6.3 8 4
8 0.9 62 2 111.60
8 0.9 61 2 109.80
TOTAL LENGTH (M) 221.40 0.00 148.00 0.00 0.00 0.00 0.00
UNIT WEIGHT (KG/M) 0.395 0.617 0.888 1.21 1.578 2.469 3.556
TOTAL WEIGHT (KG) 87.45 0.00 131.42 0.00 0.00 0.00 0.00
30.20833
32