PROJECT: CONTIGUOUS PROJECT

LOCATION: New Clark City


SUBJECT: WEEKLY MONITORING REPORT FOR EQUIPMENT AND DIESEL

Date Poured Location Segment/Station

ROAD 5 Segment F-G


8-Jun-22
ROAD 4B Road 4B

ROAD 5 Sta. 0+720 to Sta. 0+760


10-Jun-22
ROAD 5 Sta. 0+680 to Sta. 0+700

ROAD 5 Sta. 0+700 to Sta. 0+720


11-Jun-22
ROAD 5 Segment F-G

13-Jun-22 ROAD 4B Segment E-F

ROAD 5 Lean concrete


15-Jun-22
ROAD 4B Segment E-F

16-Jun-22 ROAD 5 Lean concrete

ROAD 5 ELECTRICAL DUCT BANK

17-Jun-22 ROAD 5 Sta. 0+740 to 0+760

ROAD 5 Sta. 0+740 to 0+760

18-Jun-22 ROAD 5 Sta. 0+760 to 0+780

22-Jun-22 ROAD 5 Sta. 0+745 to 0+766

23-Jun-22 ROAD 5 Electrical duct bank

Road 2A Segment B-C


24-Jun-22
ROAD 5 Segment F-G

28-Jun-22 ROAD 2A Segment B-C

ROAD 5 Segment F-G


29-Jun-22
ROAD 2A Segment B-C
29-Jun-22
ROAD 2A Segment B-C

ROAD 5 Segment F-G


30-Jun-22
ROAD 5 Segment F-G

2-Jul-22 ROAD 5 Segment F-G

ROAD 5 Segment F-G


5-Jul-22
ROAD 5 Segment F-G

9-Jul-22 ROAD 5 Segment F-G

11-Jul-22 ROAD 2A Segment B-C

12-Jul-22 ROAD 5 Segment F-G

13-Jul-22 ROAD 5 Segment F-G

ROAD 5 Segment F-G


14-Jul-22
ROAD 5 Segment F-G

ROAD 5 Segment F-G

15-Jul-22 ROAD 5 Segment F-G

ROAD 5 Segment F-G

ROAD 5 Segment F-G


16-Jul-22
ROAD 5 Segment F-G

19-Jul-22 ROAD 5 Segment F-G

NCC SCTEX ACCESS ROAD Segment G-H


20-Jul-22
ROAD 5 Segment F-G

22-Jul-22 ROAD 5 Segment F-G

NCC SCTEX ACCESS ROAD Segment G-H

23-Jul-22 ROAD 5 Segment F-G

ROAD 4B Segment E-F

25-Jul-22 ROAD 5 Segment F-G


25-Jul-22 ROAD 5 Segment F-G

ROAD 5 Segment F-G


26-Jul-22
NCC SCTEX ACCESS ROAD Segment G-H

28-Jul-22 ROAD 5 Segment F-G

ROAD 5 Segment F-G


29-Jul-22
NCC SCTEX ACCESS ROAD Segment G-H

ROAD 5 Segment F-G

30-Jul-22 NCC SCTEX ACCESS ROAD Segment G-H

ROAD 5 Segment F-G

ROAD 4B Segment E-F


1-Aug-22
NCC SCTEX ACCESS ROAD Segment G-H

ROAD 5 Segment F-G


2-Aug-22
ROAD 5 Sta. 1+255 to Sta. 1+300
AND DIESEL

Actual Volume
Work Description Specifications
(cu.m)

Lean Concrete 3/4 8.0 3000psi - 28 days

Median PCCP G1 20.0 3500psi - 28 days

RCBC Sog 3/4 7.0 3000psi - 28 days

RCBC Wall 3/4 22.0 3000psi - 28 days

RCBC Wall 3/4 10.0 3000psi - 28 days

Median Curb 3/4 17.0 3000psi - 28 days

Manhole Lean Concrete 3/4 3.0 3000psi - 28 days

Lean concrete 3/4 8.0 3000psi - 28 days

Median PCCP G1 36.0 3500psi - 28 days

Lean Concrete 3/4 10.0 3000psi - 28 days

Electrical Duct Bank 3/4 40.0 3000psi - 28 days

RCBC Wall 3/4 8.0 3000psi - 28 days

RCBC Sog 3/4 6.0 3000psi - 28 days

RCBC Wall 3/4 8.0 3000psi - 28 days

RCBC Top slab 3/4 17.0 3000psi - 28 days

Electrical Duct Bank 3/4 24.0 3000psi - 28 days

Electrical Duct Bank 3/4 70.0 3000psi - 28days

Pedestal 3/4 13.0 3000psi - 28days

Electrical Duct Bank 3/4 64.0 3000psi - 28days

Pedestal 3/4 7.0 3000psi - 28days

Electrical Duct Bank 3/4 24.0 3000psi - 28days


Electrical Duct Bank 3/4 24.0 3000psi - 28days

Electrical Duct Bank 3/4 32.0 3000psi - 28days

RCBC Top slab 3/4 17.0 3000psi - 28days

Pedestal 3/4 8.0 3000psi - 28days

Electrical Duct Bank 3/4 25.0 3000psi - 28days

RCBC Top slab 3/4 15.0 3000psi - 28days

RCBC Top slab 3/4 42.0 3000psi - 28days

Electrical Duct Bank 3/4 16.0 3000psi - 28days

Electrical Manhole Wall 3/4 14.0 3000psi - 28days

RCBC Wall 3/4 16.0 3000psi - 28days

RCBC Lean concrete 3/4 10.0 3000psi - 28days

Electrical Duct Bank 3/4 46.0 3000psi - 28days

Electrical Duct Bank 3/4 20.0 3000psi - 28days

RCBC Wall 3/4 16.0 3000psi - 28days

Median Curb 3/4 8.0 3000psi - 28days

RCBC Top slab 3/4 17.0 3000psi - 28days

Median Curb 3/4 7.0 3000psi - 28days

RCBC Lean concrete 3/4 9.0 3000psi - 28days

Electrical Duct Bank 3/4 56.0 3000psi - 28days

Median Curb 3/4 14.0 3000psi - 28days

RCBC Wall 3/4 15.0 3000psi - 28days

Electrical Duct Bank 3/4 53.0 3000psi - 28days

RCBC Wall 3/4 9.0 3000psi - 28days

Median Curb 3/4 17.0 3000psi - 28days

RCBC Top slab 3/4 10.0 3000psi - 28days


RCBC Top slab 3/4 10.0 3000psi - 28days

RCBC Wall 3/4 20.0 3000psi - 28days

Electrical Duct Bank 3/4 80.0 3000psi - 28days

RCBC Wall 3/4 18.0 3000psi - 28days

RCBC Wall 3/4 16.0 3000psi - 28days

Electrical Duct Bank 3/8 8.0 3000psi - 28days

RCBC Wall 3/4 26.0 3000psi - 28days

Electrical Duct Bank 3/4 30.0 3000psi - 28days

Electrical Duct Bank 3/4 20.0 3000psi - 28days

RCBC Lean concrete 3/4 9.0 2000psi - 28days

Duct bank Lean concrete 3/4 8.0 1500psi - 28days

RCBC Wall 3/4 24.0 3000psi - 28days

Electrical Duct Bank 3/4 20.0 3000psi - 28days