Professional Documents
Culture Documents
Cost Estimation Proxy Models for Economic Evaluations in Petroleum Projects A Case Study from the Onshore Gas Field in the Southern Coastal Tanzania Basin
Cost Estimation Proxy Models for Economic Evaluations in Petroleum Projects A Case Study from the Onshore Gas Field in the Southern Coastal Tanzania Basin
OPEN ACCESS articles distributed under Creative Commons University of Dar es Salaam
Attribution Licence [CC BY-ND] ISSN 1821-536X (print); ISSN 2619-8789 (electronic)
Websites: https://ajol.org/tjet; https://tjet.udsm.ac.tz https://doi.org/10.52339/tjet.v42i4.867
Fulmence Stanslaus Kaborogo†, Masolwa Benjamin Lazaro, and Emily Barnabas Kiswaka
Department of Petroleum Science and Engineering, School of Mines and Geosciences, University
of Dar es Salaam, Tanzania, P. O. Box 35131, Dar es Salaam
†
Correspondence author: fkaborogo@udsm.ac.tz or fulmencekaborogo5@gmail.com
ABSTRACT
Keywords: Economic evaluation, proxy model, field costs, sensitivity analysis, multivariable
regression analysis.
56 Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023
F. S. Kaborogo et. al., (2023), https://doi.org/10.52339/tjet.v42i4.867
capture the first-order effect of the field 2019; Seward, 1922,) believed to have
design features under the study of project generated significant hydrocarbons along
cost figures. However, one should be the coast (Mvile et al., 2021). The Permo-
mindful that the generation of these proxy Triassic tectonic regime was followed by
models involved a set of simplifications. the Jurassic-Cretaceous extensional
For instance, Diana (2020) and Stanko tectonics that culminated at the complete
(2020) assumed all wells drilled in a separation of Madagascar from East Africa
specific period had the same costs per well; (Thompson et al., 2019; Nicholas et al.,
their model estimation approach neglected 2007). This time period also recorded at
the variability of the well’s costs with depth least two transgressive-regressive cycles
and number of casing (Nc) strings. On the and episodic gravity flows that supplied
other hand, Nunes (2017) and Silva (2018) sediments to the deeper basinal areas
proxy equations are only suitable for (Mvile et al. 2021). One of the regressive
numerical optimization schemes or analysis events was associated with widespread
of uncertainty where the input is varied erosion of previously deposited sediments.
several times in an iterative process. The This erosional event is reflected by the
current work presents a method of Albian unconformity (Figure 2; Mvile et
developing proxy models for the estimation al., 2021). The Miocene extensional
of the costs for petroleum projects based on tectonics and post Miocene extensional
actual data retrieved from three wells tectonics and strike slip faulting (Nicholas
(Figure 1) penetrating different reservoir et al., 2007; Kent et al., 1971) followed old
zones/intervals of an onshore gas field structural grains and formed several
located in the southern coastal Tanzania offshore depocenters. The strike slip
basin. faulting is believed to have created several
structural traps. These structural traps
Study area: location, geology, and contain significant gas accumulations in the
petroleum system offshore Tanzania basin (Sansom, 2018).
The studied gas field is within the Ruvuma
Basin of the southern coastal Tanzania
basin. The datasets used are based on wells
P, Q and R whose locations are shown by
the green dots (Figure 1). Projection of this
map is based on WGS 1984 UTM 37S.
Development of the area has been mostly
influenced by extensional tectonics and
strike slip faulting (Thompson et al., 2019;
Nicholas et al., 2007; Kapilima, 2003; Kent
et al. 1971). Tectonically, basin
development began during the Permo-
Triassic following an extensional tectonic
regime that initiated fragmentation of the
Gondwana landmasses (Thompson et al.,
2019). During this time period, the coastal
Tanzania basin documented continental
sedimentation that caused deposition of the Figure 1: Location map of the study area.
Karoo organic-rich sediments (Magohe,
58 Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023
F. S. Kaborogo et. al., (2023), https://doi.org/10.52339/tjet.v42i4.867
The Miocene and post-Miocene commonly called reservoir zones thus the
extensional tectonics were also linked to studied gas field is known to produce from
several transgressive-regressive cycles different zones/intervals capped by thick
linked to variability in deposits grain-sizes. shale layers (Figure 3). Fonnesu et al.
Periods of active fault movements and (2020) and Sansom (2018) interpreted
rapid sea level fall caused slope failures that equivalent shale layers to be drift deposits
triggered downslope movement of the stepping onto the channelized sand bodies
previously deposited sediments to form forming the reservoir rocks of the offshore
slides, slumps, debrites, and turbidites units southern Tanzania. Occurrence of
of the coastal Tanzania basin (Figure 3). In channelized systems over the whole
some places, these slope failures generated stratigraphy (Figure 3) may explain
energetic sediment gravity flows that turbidites deposition and distribution of
interacted with bottom currents to lay down unconformities in the area. The Cretaceous-
well-sorted sand bodies with high net-to- Miocene stratigraphy of the Ruvuma Basin
gross ratios (Fonnesu et al., 2020). These is dissected by several faults (Figure 3).
sand bodies occur in the Cretaceous and The reservoir intervals (marked by green
Paleocene-Miocene intervals (Sansom, solid lines) are enclosed by thick shaly/drift
2018) and are forming most of the deposits (bounded by red dashed lines)
petroleum reservoirs of the coastal which form key seal rocks of the area. This
Tanzania basin. Overall, the stratigraphy of configuration has caused the reservoir
the study area is dominated by shaly intervals of the study area to be subdivided
successions enclosing thin sand bodies with into different zones separated by thick
reservoir potential (Figure 2). Occurrence shales. Black solid lines are the faults that
of paleo-channels is shown to be common dissect the Cretaceous-Miocene strata.
in the Cretaceous-Holocene stratigraphy. Similar faults have been interpreted to form
These palaeo-channels may explain hydrocarbons migration pathways from
presence of several unconformities in the deep buried source intervals to shallow
area. In this area, these thin sand bodies are
Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023 59
Cost Estimation Proxy Models for Economic Evaluations in Petroleum Projects: A Case Study
from the Onshore Gas Field in the Southern Coastal Tanzania Basin
Figure 3: A seismic section showing the depositional configuration of the Cretaceous and
Paleocene-Miocene reservoir intervals of the study area.
60 Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023
F. S. Kaborogo et. al., (2023), https://doi.org/10.52339/tjet.v42i4.867
The QUE$TOR software was used to value of the maximum amount of gas (in
estimate the cost figures for each case, in MMscf/d) that can be accommodated from
which the location of each case was the wellhead to the processing facility
assigned to be an onshore project with gas through the manifold facility. The
being the main product. An in-built percentage changes in CAPEX, OPEX, and
procurement strategy and oilfield units of DRILLEX from the base case were
measure were used. Field characteristics calculated and presented on Tornado
were fed as shown in Table 1. The effect of graphs.
the gathering system on CAPEX, OPEX
and DRILLEX was evaluated by using the
Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023 61
Cost Estimation Proxy Models for Economic Evaluations in Petroleum Projects: A Case Study
from the Onshore Gas Field in the Southern Coastal Tanzania Basin
62 Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023
F. S. Kaborogo et. al., (2023), https://doi.org/10.52339/tjet.v42i4.867
Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023 63
Cost Estimation Proxy Models for Economic Evaluations in Petroleum Projects: A Case Study
from the Onshore Gas Field in the Southern Coastal Tanzania Basin
Gathering
system
Processing
facilities
Number of
wells
Production
capacity
Gathering
system
Processing
facilities
Number of
wells
Production
capacity
Model A B C
1. A + B(Depth) + C(Ncasing ) 21.403 0.002 0.003
The DRILLEX regression results (Table 6) equations presenting the seven models.
can be summarized by using seven (7) Equation (1) presents the selected
64 Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023
F. S. Kaborogo et. al., (2023), https://doi.org/10.52339/tjet.v42i4.867
Gathering
system
Processing
facilities
Number of wells
Production
capacity
-20% -10% 0% 10% 20%
40%… 40%… Change in OPEX
Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023 65
Cost Estimation Proxy Models for Economic Evaluations in Petroleum Projects: A Case Study
from the Onshore Gas Field in the Southern Coastal Tanzania Basin
Table 7: Relative error between commercial software and proxy models cost estimates
Compared to the current proxy cost models the cost proxy models available so far are
by González, 2020; Stanko, 2020; for offshore petroleum fields.
Kuznetsov et al., 2011; and Shereih, 2016;
the models developed in this study have CONCLUSION AND
considered the variability of DRILLEX RECOMMENDATIONS
with depth and number of the casing. The
Based on the analysis of input data from the
previous studies made unrealistic
three wells of the onshore gas field of the
simplifications and assumptions whereby
southern coastal Tanzania basin, the
uniform costs were assumed for all drilled
following were revealed:
wells, an assumption that might not be
• The developed proxy models may
always true. Similarly, recent OPEX model
serve as reliable cost-estimating tools
developed by RPS (2019) neglects the
because they produce cost estimates
significant contribution of the number of
that are generally 5% less than
on-stream wells. The model considers only
commercial cost estimates
the cumulative production. According to
RPS (2019), this is an unrealistic as the • DRILLEX is strongly affected by the
operating costs normally increase with number of wells to be drilled in the
number of on-stream wells. The models field
developed in this study include the costs of • OPEX is strongly affected by gas
operating each on-stream well to capture production capacity and the number
the real cost of operating a particular field of producing wells in the field
for a given production capacity and other • CAPEX is strongly affected by the
parameters such as depth and casing capacity of the processing facilities
numbers. For example, the wells P [depth = and the number of wells in the field
2012 m and casings = 4] and Q [depth • CAPEX and OPEX are modeled as
=2788 m and casings = 5] give significant linear functions of their affecting
cost differences which when neglected parameters while DRILLEX for a
during project evaluation might affect single onshore vertical well is
future project decisions. Therefore, this modeled as a nonlinear function
work presents reliable proxy models for the (power function) of the well depth
estimation of the costs for petroleum and number of casings. However,
projects when it comes to the onshore gas DRILLEX is linearly affected by the
field. One should be mindful that most of number of wells
66 Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023
F. S. Kaborogo et. al., (2023), https://doi.org/10.52339/tjet.v42i4.867
For the purpose of increasing the accuracy González D., Stanko M. and Hoffmann A.
and reliability range of the developed proxy (2020). Decision support method for the
models, the following can be done: early-phase design of offshore
• Proxy models need to be modified as hydrocarbon fields using model-based
optimization, Journal of Petroleum
more data becomes available. In this
Exploration and Production
paper, the proxy models were Technology., 10(4), 1473-1495.
developed using few amounts of data González D. (2020). Methodologies to
since most of the data were not determine cost-effective development
readily available from the field strategies for offshore fields during
• Stochastic methods like Monte Carlo early-phase studies using proxy models
simulation or Latin Hypercube have and optimization, PhD thesis, Norwegian
to be performed so as to be able to University of Science and Technology,
incorporate parameters that can Department of Geoscience and
quantify the cost estimation Petroleum.
IHS. (2016). Quick Start Guide Que$tor.
uncertainties. This will make the
Online source. Available online at
proxy models more reliable https://cdn.ihs.com/www/questor/Quick-
Generally, the proxy models developed in Start-Guide.pdf. Retrieved on 1st
this article should be used with caution and November 2022.
if adequate data will later be available, the Kapilima S. (2003). Tectonic and sedimentary
same methodology can be used to update evolution of the coastal basin of Tanzania
the models so as to minimize their during the Mesozoic times. Tanzania
estimation error. Journal of Science., 29, 1-16.
Karlik C.W. (1991). Parametric estimating of
ACKNOWLEDGEMENT oil and gas production facilities capital
costs worldwide. In SPE Hydrocarbon
The authors of this work are thankful to the Economics and Evaluation Symposium,
staff of the Department of Petroleum OnePetro.
Science and Engineering of the University Kent P. E., Hunt J. A. and Johnstone D. W.
of Dar es Salaam for their individual (1971). The Geology and Geophysics of
contributions that improved the presented Coastal Tanzania. Institute of Geological
results. Sciences, Geophysical Papers., 6, 1-101.
Kuznetsov M., Sevastyanova K., Tarasov P.,
Zilber V. and Nekhaev S. (2011). Capital
REFERENCES Costs Estimation Method for Arctic
Melo R. and Accioly S. (2016). Cost Offshore Oil Projects. In SPE Arctic and
Estimating Relationships in Onshore Extreme Environments Conference and
Drilling Projects. Cadernos do IME- Exhibition, OnePetro.
Série Estatística., 40, 34. Magohe S. (2019). Preliminary palynology of
Fonnesu M., Palermo D., Galbiati M., the Karoo equivalent Tanga beds, coastal
Marchesinia M., Bonamini E. and Tanzania: insights on preservation, age
Bendias D. (2020). A new world-class and depositional environments. Tanzan
deep-water play-type, deposited by the Journal of Science., 45, 392–404.
syndepositional interaction of turbidity Mian M.A. (2011). Project Economics and
flows and bottom currents: The giant Decision Analysis, Volume 1:
Eocene Coral Field in northern Deterministic Models. PennWell Corp.
Mozambique. Marine and Petroleum Mvile B.N., Kiswaka E.B., Osinowo O.O.,
Geology., 111, 179-201. Marobhe I.M., Olayinka A.I. and Mshiu
Fuhrmann A., Kane I.A., Clare M.A., Ferguson E.E. (2021). Cretaceous–Quaternary
R.A., Schomacker. E., Bonamini E. and seismic stratigraphy of the Tanga
Contreras F.A. (2020). Hybrid turbidite- offshore Basin in Tanzania and its
drift channel complexes: An integrated petroleum potential. Journal of
multiscale model. Geological Society of Petroleum Exploration and Production
America., 48. Technology., 1, 20.
Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023 67
Cost Estimation Proxy Models for Economic Evaluations in Petroleum Projects: A Case Study
from the Onshore Gas Field in the Southern Coastal Tanzania Basin
68 Tanzania Journal of Engineering and Technology (Tanz. J. Engrg. Technol.), Vol. 42 (No. 4), Dec. 2023