Pending List
Pending List
AAAC cable connection with plinth earthing cables and pending due to unavailability of
pg clams.jumper cables between plinths pending due to unavailability of unarmoured
61 cables.
62 TT side cable plug in pending.
63 At and MDB side cable plug in pending.
64 fire system nozzles infringing with cable trays. To be rectified.
65 FTS zoning and tagging pending.
66 cross bonding cable whole work pending.
67 fts system integration with HVAC system pending
68 earth pits is broken and value marking pending.
69 integration with lt panels pending
70 liu installation pending.
71 cable tagging pending at viaduct and few control cable tagging pending.
72 cables to MET inside ass tss tagging pending.
73 cable tray vertical droppers earthing pending
74 all glands and spare gland holes to be sealed to prevent entry of rodents.
75 grp , smoke detectors smoke tests and alarm pending
76 Fire bucket nomenclature should be identical at per bucket position.
77 Traction transformer tap no 07 adjustment problem.
78 scratch mark inside traction transformer core base. It should be paint properly
79 Chair support installation is pending at viaduct.
80 LBS02 cable plug in is pending at viaduct.
81 GIS panel door lock and key should be proper.
82 ASS and TSS light installed but termination is pending to commissioning.
83 LBT Gap fitting work is pending
84 Fire alarm is panel along with connection is pending.
85 VRF unit network connectivity is pending
86 Cable tray dropping pending near the G-C grid, lift area.
87 First aid room and clearance room switch and socket is pending.
88 Ventilation of ASS pending due to cut out opening.
89 Cable tray is pending for ventilation Fan equipment.
90 Light installation is pending in lockers room, due to false celling clearance.
91 ITD Light installation is pending at SCR room.
92 Viaduct DB installation is pending. Civil team to be done niche for DB location.
93 2 nos of additional panel installation is pending,
94 Extra jockey pump room cable tray and cable laying with termination is pending.
95 LBT lighting installation is pending at entry side.
96 Copper pipe insulation is pending at EFO room
97 RCBO and cable laying is pending at concourse level and Platform level for signages
98 Control module is pending for all the lifts
99 Pump room piping and automation system yet to be complete.
100 Lighting and Cable tray installation to be done.
101 Jackson DG installation and related works are pendings
102 Tre not installed as device not available
103 DC 240 sqmm negative termination pending at rail side.
Internal cable dressing , trefoil clamp installation, phase identification of 33kv cables
104 pending
105 Rectifier body and bus duct chamber electrical isolation rectification pending.
106 Ritwik All viaduct cables (ac and dc)both dressing , tagging pending.
107 EPDM work is pending
AAAC cable connection with plinth earthing cables and pending due to unavailability of
pg clams.jumper cables between plinths pending due to unavailability of unarmoured
108 cables.
109 Surge arrestor cable plugin pending at ritwik ghatak.
110 TT side cable plug in pending.
111 At and MDB side cable plug in pending.
112 Ets body earthing pending.
113 Fire suppersion systeminstallation in at and traction transformer in progress.
114 Armour earthing of cables at gis end pending.
115 Siemens Fire system nozzles infringing with cable trays. To be rectified.
116 Fire suppersion system zoning and tagging pending.
117 Cross bonding cable whole work pending.
118 fts system integration with HVAC system pending
119 earth pits value marking pending
120 rectifier cable entry gland plate installation pending
121 hscb room dc panels base insulation sheet fixing pending.
122 integration with lt panels pending
123 liu(light interface unit) installation pending.
124 dummy plug installation at spare gis panels pending
125 cable tagging pending at viaduct and few control cable tagging pending.
126 cables to MET inside ass tss tagging pending.
127 Cable tray vertical droppers earthing pending
128 several nutbolts of rectifier and hscb panels missing.
129 all glands and spare gland holes to be sealed to prevent entry of rodents.
130 GRP , smoke detectors smoke tests and alarm pending