PAPL/EHSMS/CWM REV:00 EFF.

DATE:01/05/2024
PRADHAN ASSOCIATES Pvt. Ltd.
SAFETY INSPECTION CHECKLIST FOR WELDING MACHINE
Name Of Project / Area:
Seriel No / Mark No:
Dates Of Inspection
Date From: Date Upto:
Remarks
Ok/Not Ok/Not Ok/Not Ok/Not Ok/Not Ok/Not
Sl. No. CHECK POINTS Ok Ok Ok Ok Ok Ok
Are arc welding cables completely insulated, flexible type
1
?
Are all exposed portion of the cable protected by suitable
2
rubber & friction type or other equipment insulated?
Are all frame of arc welding machines grounded
3 properly?
Is the fire extinguisher available in the work area with
4
readiness for use?
5 Is the work area free from all inflammable materials?
Electrode Holder & Earthing Clamp are in good
6 condition ?
7 Is welding machine body in good condition?
8 Are all of switches in good condition?
9 Is voltage regulator in good condition?
Are use of nut & bolt to tighten welding & grounding
10 cable?
11 Is the electrode welding holder in good condition?
Is ELCB with 30mA sensitivity available in welding
12 machine?
13 Is body earthing provided on welding machine?
14 Is cable gland available on welding machine?

15 Is welding cable terminated properly in welding holder?

CHECKED BY: