just

Type of work before


ER,O&M Field intervention work followup template
(Supervision/C Site Departur
orrective Condition e
Maintenance/P on Arrival Departure Total stay (Results/ Recommendati
reventive Arrival Date (Problems Date from duration Achievem on for future
No. Region/Zone Location Specific Location Site ID Maintenance/S to the site identified) the site on the site ents) Detail activities done work
upport/On Job
Training)
gebi, hulul land for new sites Land
1 ER Dire Dawa mojo new site requisition 13/3/2024 new site 14/3/2024 2days new site requisition

land for new sites Land


2 ER Dire Dawa karamile new site requisition 14/3/2024 new site 15/3/2024 1days new site requisition

Port submmittedjemal ahmed Oracle Id :- 9962 Signature: Date:- 19/3/2024


port approved: Fassil Werkiye Oracle id:- 7995 Signature:- Date:- 19/3/2024