Professional Documents
Culture Documents
Critical Risk Protocol Audit
Critical Risk Protocol Audit
Go to >>>
Front Page
Scoring Guide
Score Table and Graphs
Guideline and Checklist
CRP – 1 Risk and Change Management
CRP – 2 Design, Construction and Commissioning
CRP – 3 Emergency Preparedness, Response and Crisis Management
CRP – 4 Management of Subcontractors, Contractors, Service Providers and Visitors
CRP – 5 Plant and Equipment Specifications, Integrity and Maintenance
CRP – 6 Mobile Vehicle and Pedestrian Interaction
CRP – 7 Mobile Vehicle, Plant and Equipment Operation
CRP – 8 Hazardous Materials Management
CRP – 9 Ground Control and Geotechnical Matters
CRP – 10 Electrical Safeguard
CRP – 11 Isolation of Energy Sources
CRP – 12 Working at Height
CRP – 13 Permits to Work
CRP – 14 Fitness for Work
CRP – 15 Lifting Operations
CRP – 16 Explosives
Library Ref: G-649
Revision Date: 12-Jul-10 Critical Risk Protocol Audit
Audit Detail:
Audit Dates:
Auditor Name(s): Andy McDonald
Audit Reference:
Legislative References:
Project / Site / Location Detail:
Project Code: C692
Project Title: Goldfields TNC
Project Location (eg. State): Western Australia
Project Completion Status %: 98%
Est Project Completion Date: 8/31/2011
Client: Main Roads Western Australia
Contract Reference: 04/00
Resources:
Project Manager: Lars Rasmussen
General Manager:
Project Safety Representative: Minke Kersten
Project Environment Representative: Andrew Milovanovic
State / Division Safety Representative:
State / Division Environment Representative:
National Safety Representative:
National Environment Representative:
Audit Contributors:
List persons and their positions who have contributed to the outcome of this audit.
Name: Job Title:
Meeting Attendees
Entry Meeting Exit Meeting
Relevant to:
Business Unit: All Document Owner: EGM HSEQ
Page 2 of 60
Division(s): All Change Control: Level 1
Site: All
Department: All
Library Ref: G-649
Revision Date: 12-Jul-10 Critical Risk Protocol Audit
All assessment and audit types shall be subject to a conformance based rating and ranking system, which shall provide
an indication as to the HSEQ ‘conformance or non-conformance' of critical requirements of a project and subsequently
the Business Unit.
The following definitions shall be used to ‘rate’ the audit or self assessment:
Conformance – To have fulfilled the requirement.
Non-conformance – A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and
major non-conformance and therefore determine the severity of that non-conformance.
Observation – Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been
substantially met but the implementation could be improved to provide better assurance of continuing compliance).
Opportunity for improvement – A system / process improvement that will benefit the system, operations or process
being audited and is generally applied to a conformity, therefore the conformity is still rated.
Score 2 – Conformance
Note: Where an OFI is provided during the course of the assessment/audit the rating against that criteria is still applied
(ie. If an OFI is applied to a conformity, then that conformity would still attract a score of ‘2’, regardless of the fact that an
OFI is recommended).
RANKING DESCRIPTION
Low < 49% There is strong, practical evidence that the risks and/or the root
causes of system failures still exist in their operation.
Moderate 50 -74% Particular work groups, jobs and/or tasks are exposed to risks or
they are not to an acceptable standard.
High 75 - 90% The site has good systems that are aligned with their risk profile,
and these systems are practical, sustainable and effective. Some
refinements and improvements are still required.
Excellent > 90% The site has systems that can be described as excellent being well
established and implemented.
Relevant to:
Document Owner: EGM HSEQ
Business Unit: All
Change Control: Level 1
Page 3 of 60
Division(s): All
Site: All
Department: All
Library Ref: G-649
Revision Date: 12-Jul-10 Critical Risk Protocol Audit
Assessment Table
CRP Rating
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
CRP – 4 Management of Subcontractors, Contractors, Service
CRP – 1 Risk and Change Management
CRP – 16 Explosives
CRP – 14 Fitness for Work
CRP – 6 Mobile Vehicle and Pedestrian Interaction
tenance
CRP – 16 Explosives
CRP – 14 Fitness for Work
CRP – 6 Mobile Vehicle and Pedestrian Interaction
tenance
Critical Risk Protocols (CRP's) have been developed to outline minimum requirements for the
management of critical risk activities within the organisation. The CRP's (G-367) form a key part of the
way in which we manage safety, health and environment within the operational environment, which
have the potential to adversely affect the safety and health of people, including employees,
contactractors, visitors, the public and damage to the environment.
Use of this audit tool is reliant upon the Auditor being familiar with the Macmahon Occupational Health
and Safety Management System and its' requirements (including that of the CRP's G-367), relevant
legislation, standards, codes of practice and guidelines applicable to the location of operations.
The aim of conducting a CRP audit is to determine:
- What activities are high risk to the operation?
- What risks will have considerable impact?
- Are controls in line with that documented and are they appropriate to prevent an incident
recurrence?
- Can you track the flow of data evidence from one source to another? That is, close the loop
from the beginning of the operation to the end of the operation such that the continuous
improvement loop.
- Can you track data to ensure that all elements of our 'Total Safety Culture' are covered?
The audit shall be conducted by firstly checking that sufficient documentation is in place to meet criteria
and secondly to ensure that it is sufficiently implemented by looking/ observing/ interviewing/ testing
etc.
- Documented Assessment - records that assist to determine the level of implementation
- Observational Assessment - What's actually happening in the field? What did you see? Were they
complying with written requirements? Are they doing what they say they do?
Pre-audit
Auditor to review outcomes of previous audits and site incidents plus site management plans and risk
registers with a view to identify which CRP's are most critical for the operation.
Auditor to have an understanding of legislation, codes of practice, standards and guidelines which are
applicable to the operation.
Auditor to have an understanding of local requirements (where applicable to CRP's) such as
emergency processes, potential environmental conditions etc
Auditor to ascertain any site entry requirements suh as permits, inductions, approvals and
authorisations.
Relevant to:
Business Unit: All Document Owner: EGM HSEQ
Page 5 of 60
Division(s): All Change Control: Level 1
Site: All
Department: All
Library Ref: G-649
Revision Date: 12-Jul-2010 Critical Risk Protocol Audit
Audit Checklist
Identify areas of interest and corresponding CRP's to be used for auditing.
CRP Area of Interest
Relevant to:
Business Unit: All Document Owner: EGM HSEQ
Page 6 of 60
Division(s): All Change Control: Level 1
Site: All
Department: All
Critical Risk Protocol Audit
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Risk registers; JSEA's; Take 5; evidence of assessment and prioritisation is available; controlls are observed; the continuous improvement loop exists following the identification of a hazard or risk (ie.
Changes/controls are fed back into registers, procedures etc); evidence of communication is available (ie. there is an understanding of the change amongst personnel); how is feedback managed?
Key Doc Refs G-042 Risk Management Policy; G-205 Quarterly Project Managers Risk-Based Safety Review Procedure; G-426 Hazard Identification, Assessment and Control Guideline; G-429 HSEQ Change
Management Procedure; G-495 Health, Safety and Environment Risk Management Procedure; Legislative and regulatory requirements for health and safety; NOHSC:1016 (2005) National Standard
for Construction Work; National Standard for Licensing Persons Performing High Risk Work; AS/NZS 4801 Occupational health and safety management systems - Specification With Guidance For
Use; AS/NZS 14001 Environmental management systems - Requirements with guidance for use
772431297.xls Page 7 of 60
CRP1
CRP 1: Risk and Change Management Critical Risk Protocol Audit
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assess Rating
Rating
1.4 Control measures are established for all identified hazards in
accordance with the ‘hierarchy of controls’ and are
documented.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 8 of 60
CRP1
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Meeting minutes; documented design reviews; document history (ie. plans/drawings) can be tracked; permits and authorisations are in place for commission / decommission; technical standards / legal
requirements are referenced; observation of site and activities being conducted demonstrates safety design processes that have been used to reduce risk.
Key Doc Refs G-429 Change Management Procedure; C-161 Design Management Procedure; Legislative and regulatory requirements for health and safety; AS/NZS 4801 Occupational Health and Safety
Management Systems - Specification With Guidance For Use; NOHSC:1016 (2005) National Standard for Construction Work; Guidance on the Principles of Safe Design for Work; Relevant building
codes
772431297.xls Page 9 of 60
CRP2
CRP 2: Design, Construction and Commissioning
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
2.4 Records of all design reviews and subsequent risk
assessments whereby safety design risks are identified are
maintained and are available.
2.6 There is evidence to suggest that the potential for high risk
activities, such as working at height or those activities subject
to permitted systems, use of plant and machinery or
hazardous substances have been identified as a part of the
design risk assessment process and the need to perform these
activities has either been eliminated, engineered out or
substituted for a lower risk process as far as reasonably
practicable.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 10 of 60
CRP2
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Personnel understand their role in an emergency; plans and other equipment are observed, are current and are in good condition around the site; first aid equipment and services are appropriate;
personnel are trained in first aid, emergency response and crisis management (ie. Project Manager). Review incidents and work areas to determine if appropriate first aid / emergency response is
adequate. In the case of crisis management, links back to corporate offices for notification, media statements, legal (etc) must be observed or identified.
Key Doc Refs G-407 Emergency Crisis Management Plan; G-540 Emergency Preparedness and Response Procedure; Legislative and regulatory requirements for health and safety; NOHSC:1016 (2005) National
Standard for Construction Work; Codes of Practice in each state of Australia for the provision of first aid services and facilities; Guidance Note, Preparing for Emergency Evacuations at the Workplace
772431297.xls Page 11 of 60
CRP3
CRP 3: Emergency Preparedness, Response and Crisis Management
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
3.5 Emergency response arrangements are communicated to all
personnel, including visitors.
772431297.xls Page 12 of 60
CRP3
CRP 3: Emergency Preparedness, Response and Crisis Management
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
3.13 Personnel can demonstrate an understanding of not only the
site emergency procedure but also that of the Crisis
Management Plan requirements.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 13 of 60
CRP3
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Employment and management of subcontractors follows a strict evaluation (ie. subcontractor evaluation records) and checking process and that they are observed to be working to and participating in
Macmahon requirements. JSEA's or similar are present and being used at the job site. The process for incident reporting and emergency management is understood etc. There is a process to ensure
that HSEQ plan requirements or other operating or construction instructions / plans / drawings are understood.
Key Doc Refs G-533 Subcontractor Evaluation Questionnaire; G-534 Subcontractor Evaluation - Inspection Visit; G-535 Subcontractor Employee Questionnaire; G-536 Subcontractor Performance Feedback; C-108
Construction HSEQ Management of Subcontractors and Suppliers Procedure
772431297.xls Page 14 of 60
CRP4
CRP 4: Management of Subcontractors, Contractors, Service Providers and Visitors
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
4.5 There is evidence that the subcontractor / contractor has
access to any pertinent instructions, plans or other documents
to complete the job safely and without risk to themselves,
others, equipment or the environment.
4.10 At the time of audit, all visitiors had signed into the visitors
book.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 15 of 60
CRP4
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Evidence that equipment complies with Macmahon specifications, standards and legislative requirements (ie. plant registration, sign off on purchases, approvals from plant manager, approval of
modifications from manufacturer etc) and/or appropriate controls are in place to reduce risks/hazards associated with equipment that does not meet requirements. All equipment and parts are fit for
purpose. Maintenance and pre-checks are completed, including that of hire plant and equipment. Safe working / operating instructions are available.
Key Doc Refs P-313 Build Specification 3 Process Procedure; Legislative and regulatory requirements for health and safety; NOHSC: 1010 (1994) National Standard for Plant; Australian, New Zealand and
international standards applicable to plant and equipment type; Manufacturer manuals
772431297.xls Page 16 of 60
CRP5
CRP 5: Plant and Equipment Specifications, Integrity and Maintenance
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
5.5 There is evidence that all hire equipment, including plant and
light vehicles and that of subcontractors entering site, is
inspected upon arrival and/or prior to work start.
5.9 There are records to show that personnel are trained and
competent in the operation of plant and equipment and these
records are available on site.
772431297.xls Page 17 of 60
CRP5
CRP 5: Plant and Equipment Specifications, Integrity and Maintenance
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
2.13 Electrical cables are adequately supported and do not appear
to be damaged.
2.17 Fixed plant has platforms and walkways that are provided for
maintenance and/or cleaning purposes - guards, railings and
kickboards must be fitted, the platform/walkway is free of trip
hazards and is no less than 600mm in width.
2.19 Inclined walkways have cleats installed or are fitted with a non-
slip type material.
2.20 Steps and ladders are secure and are in good condition and
are slip resistant.
772431297.xls Page 18 of 60
CRP5
CRP 5: Plant and Equipment Specifications, Integrity and Maintenance
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
2.21 There is evidence that pressure vessels are inspected,
maintained and stored appropriately.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 19 of 60
CRP5
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Hazards associated with the movement of plant, equipment and pedestrians are assessed, reviewed and monitored. Traffic management plans are developed and managed, as appropriate.
Key Doc Refs C-067 Safety in Traffic Management Procedure; C-056 Construction Traffic management Policy; M-UG-065 Underground Traffic Control Procedure; M-SF-013 Driving Rules on Mine Sites Procedure;
M-UG-065 Underground Traffic Control Procedure; Legislative and regulatory requirements for traffic management, health and safety; Australian and New Zealand Standards 1742 series, 1906 series
and 1158 series; AS 3845-1999 Road Safety Barrier Systems; Codes of Practice in each state of Australia for traffic management
772431297.xls Page 20 of 60
CRP6
CRP 6: Mobile Vehicle and Pedestrian Interaction
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
6.4 As far as practicable, pedestrian pathways are separated /
fenced off from any roadway.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 22 of 60
CRP6
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Persons operating light vehicles, plant or other equipment are appropriately licenced; trainers are appropriately qualified; hazards associated with operations, such as the location of underground
services, are identified and risks reduced to as low as reasonably practicable; site rules are evident; communications between vehicle and equipment operators are applied; equipment is fit for purpose
and a maintenance regime is in place; safe operating procedures are in place.
Key Doc Refs G-556 Training and Development Policy; Legislative and regulatory requirements for health and safety; NOHSC:1006 (2001) National Occupational Health and Safety Certification Standard for Users
and Operators of Industrial Equipment 2004; Equipment operational manuals
772431297.xls Page 23 of 60
CRP7
CRP 7: Mobile Vehicle, Plant and Equipment Operation
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
7.5 Training has been provided in hazard identification,
assessment and control.
7.8 Traffic movement plans have been developed and local traffic
management controls have been established.
7.9 Warning devices are fitted to mobile plant and equipment and
in good working order.
7.10 Above ground and under ground services have been identified
to prevent inadvertent contact.
772431297.xls Page 24 of 60
CRP7
CRP 7: Mobile Vehicle, Plant and Equipment Operation
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
7.13 A plant risk assessment has been carried out on all items of
plant and safe operating instructions produced which includes
maintenance, service and inspection details.
7.14 Procedures are available for the operation of all plant and
equipment.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 25 of 60
CRP7
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Hazardous materials/chemical registers, MSDS and health risk assessments are available and understood by persons using those hazardous materials. Appropriate PPE, storage requirements,
signage, spill containment and ventilation is available, as appropriate, for each identified hazardous material. Systems are in place to prevent risk to personnel, damage to equipment or the
environment.
Key Doc Refs G-504 Control of Hazardous Substance Procedure; Legislative and regulatory requirements for health, safety and the environment; NOHSC:2012(1994) National Code of Practice for the Labelling of
Workplace Substances; NOHSC:2007 (1994) National Code of Practice for the Control of Workplace Hazardous Substances; NOHSC:10005 (1999) List of Designated Hazardous Substances
8.3 Personnel are aware of health risks associated with the use or
exposure to hazardous materials.
772431297.xls Page 26 of 60
CRP8
CRP 8: Hazardous Materials Management
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
8.5 Appropriate PPE for the handling of hazardous substances is
available and worn.
8.6 Appropriate areas / cabinets are provided for the storage and
segregation of hazardous materials and signage and
placarding is evident.
772431297.xls Page 27 of 60
CRP8
CRP 8: Hazardous Materials Management
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
8.13 The location of all underground services (including pressurised
gas pipelines) have been located prior to excavation.
772431297.xls Page 28 of 60
CRP8
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide The principal sources of geotechnical risk in surface mines are pit wall stability, ore and waste stockpile slope stability and tailing storage facilities. An additional source of risk in some operations
arises from the need to mine through old underground workings. Prior to commencing the audit it is essential to determine precisely who has responsibility and control of geotechnical matters and
whether or not the client uses 'in-house' expertise or employs a consultant. This audit is confined to establishing that a plan exists, is implemented and its application is actively monitored.
Geotechnical engineering is a very specialised topic and no attempt should be made by a HSEQ auditor to traverse any technical issues or to make any findings in relation to them.
Key Doc Refs M-UG-188 Underground Cardinal Rules Standard; Code of Practice, Surface Rock Support for Underground Mines, Department of Mines and Petroleum; Guideline, Geotechnical Considerations in
Open Pit Mines, Department of Mines and Petroleum; Guideline, Geotechnical Considerations in Underground Mines, Department of Mines and Petroleum
9.3 The mine has both short and long term production schedules
that take into account the likely geotechnical impacts which
may have an adverse affect on safety. Intent: To verify that
the mine design takes into account the excavation exposure
time, personnel access, and time dependent performance etc.
when considering geotechnical designs.
772431297.xls Page 29 of 60
CRP9
CRP 9: Ground Control and Geotechnical Matters
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
9.4 The boundaries of water filled hazards have been accurately
determined and a safe working distance specified according to
the ground conditions and the mine plan. Intent: To verify that
the mine has adequately considered the hazard of working
near large bodies of ground water where the open pit
encroaches onto abandoned and flooded workings.
9.5 Internal water drainage strategies exist for open pits, waste
dumps and haul roads. Intent: To verify that the mine has
implemented suitable drainage measures that minimise
erosion of important structures and pooling of large bodies of
water in critical areas (e.g. at the crest of batter slopes or the
toe of waste dumps). These drainage control structures need
to be applicable for storm events.
9.7 Are all relevant contractors fully conversant with the plan and
does it guide their activities. Intent: To verify that the plan has
been fully communicated to those whose functions it affects
and that it is understood by them. Verification; Contractor
project manager, Mobile Plant, Drill and Blast and Process
superintendents and supervisors.
9.8 The GCMP has a review period and is signed off by relevant
management bodies each time a modification is made to that
document. Intent: To verify that the GCMP is a "living
document" and includes input from personnel responsible for
key areas of mining that impact on geotechnical performance.
9.9 All relevant personnel understand their roles within this site
GCMP. Intent: To verify that mine management has in place a
working methodology that describes the overall responsibilities
of personnel in the mine with respect to geotechnical
considerations and lists the systems and design strategies
available for each component of geotechnical management
and that the relevant workforce possess the basic knowledge
required.
772431297.xls Page 30 of 60
CRP9
CRP 9: Ground Control and Geotechnical Matters
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
9.11 Where underground workings or natural voids exist, the mine
has developed formal safe working practices for mining
through voids that are formally approved and implemented.
Intent: To verify that SWP and design criteria for minimal floor
thickness exist to minimise exposure to the hazards
associated with working on top of open voids.
9.16 SWP’s are available for drilling and blasting operations. Intent:
To ensure that blasts are conducted as per the design
guidelines
772431297.xls Page 31 of 60
CRP9
CRP 9: Ground Control and Geotechnical Matters
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
9.17 Where applicable, the impact of blasting on nearby structures
e.g. tailings storage facilities or water diversion structures has
been adequately assessed and taken into consideration when
designing all forms of blast. Intent: To ensure that the mine
has taken measures to ensure that blasts will not destabilise
nearby important or hazardous structures over time.
772431297.xls Page 32 of 60
CRP9
CRP 9: Ground Control and Geotechnical Matters
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 33 of 60
CRP9
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Equipment is fit for purpose; isolation and tagging of equipment is evident; access to electrical boards or completion of electrical work is only completed by appropriately licensed and qualified
personnel. Processes are in place to ensure that: all electrical services are de-energised prior to severing; working under or near overhead powerlines or digging near underground services are risk
assessed. Plans / diagrams are available of all electrical services.
Key Doc Refs C-071 Construction Electrical Safety Procedure; M-021 Consideration Prior to Live Electrical Work; M-030 Testing and Commissioning of Electrical Work Checklist; M-039 Electrical Design and
Calculations Work Instruction; M-UG-041 Underground Electrical Equipment Installation Requirements Work Instruction; M-UG-153 High Voltage Electrical Work (General Requirements) Work
Instruction; Legislative and regulatory requirements for electrical safety; Australian and New Zealand Standards 3000 series; AS/NZS 3012:2003 Electrical Installations – Construction and Demolition
Sites; Various state Codes of Practice relating to electrical work for mining and construction
772431297.xls Page 34 of 60
CRP10
CRP 10: Electrical Safeguard
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
10.4 Faulty, unfit or unsafe equipment is tagged 'Out of Service'.
772431297.xls Page 35 of 60
CRP10
CRP 10: Electrical Safeguard
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
10.12 There is a process and a physical check in place to determine
that an electrical service has a zero energy state, thereby
ensuring that all electrical services are de-energised prior to
severing, which is not limited to relying on drawings and
permits alone.
10.13 All actions resulting from previous electrical incidents (eg. both
from the site being audited and from other sites) are in place.
772431297.xls Page 36 of 60
CRP10
CRP 10: Electrical Safeguard
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
10.19 VRD's are installed on welders.
10.20 Care and use of 9" grinders on site must comply with written
procedures.
10.21 Single line diagrams are controlled, remain current and identify
equipment details, electrical protection discrimination curves
and cable ratings.
10.25 Circuit breakers for sub circuits emanating from main and
distribution boards are adequately identified at their origin.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 38 of 60
CRP10
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Lockout / tagout processes are evident; risks associated with energy sources are managed and permanent isolation points are evident on all plant and equipment.
Key Doc Refs M-105 Mining Isolation and Tagging Procedure; C-202 Construction Isolation and Tagging Procedure; Legislative and regulatory requirements for health and safety; AS 4024.1 - 2006 Safeguarding of
Machinery; AS/NZS 4836 – Safe Working on Low-voltage Electrical Equipment; Codes of Practice in each State of Australia relating to high risk functions; Guidance Note, Commission for Occupational
Safety and Health, Isolation of Plant
11.2 All potential energy sources have been identified (eg. Check
maintenance, equipment operation, plant and vehicle
operation, lifting operations etc). For example: A risk
assessment must be conducted to identify all energy sources
and may refer to electrical, pneumatic, hydraulic, stored
energy such as batteries, fuels, gravity, springs, heat referring
to steam and hot water, gases under pressure and radiation.
Additionally, other hazards identified as a result of exposure to
an energy source shall be considered (eg. falls, burns,
asphyxiation, impact, contact with hazardous substances or
chemicals, drowning etc).
772431297.xls Page 39 of 60
CRP11
CRP 11: Isolation of Energy Sources
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
11.4 Plant and equipment are shown to have a permanent isolation
point fitted.
11.6 Tags and locks (where applicable) are available and easily
accessible on site. As a minimum, personal danger tags, out
of service tags, information tags, testing and adjusting tags,
equipment isolation tags and/or locks shall be implemented.
11.9 Tags have been filled out correctly with all appropriate detail.
772431297.xls Page 40 of 60
CRP11
CRP 11: Isolation of Energy Sources
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
11.12 Where there is a requirement under legislation, lock box tags
and locks are implemented.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 41 of 60
CRP11
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide There is a process in place for the management of risk associated with working at height and that these are reduced to ALARP through the hierarchy of controls. Workers are observed to be working
safely at height. All equipment used to reduce the risks of working at height are regularly inspected (certified, where required), listed on a register and maintenance documented. Persons working at
height (and using any associated equipment) are appropriately licenced and/or trained.
Key Doc Refs C-064 Work Permits Procedure; C-074 Construction Working at Heights Procedure; Legislative and regulatory requirements for health and safety; National Standard for Licensing Persons Performing
High Risk Work; Australian and New Zealand Standards 1891 and 1892 series; AS 1657:1992 Fixed platforms, walkways, stairways, and ladders - Design, construction and installation; AS/NZS 4576-
1995 Guidelines for Scaffolding; AS 2250.10 Cranes – Safe Use – Elevating Work Platforms; AS 1418.10 Cranes (Including Hoists and Winches) – Elevating Work Platforms; Code of Practice,
Prevention of Falls at Workplaces; Compliance Code, Prevention of Falls in General Construction
772431297.xls Page 42 of 60
CRP12
CRP 12: Working at Height
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
12.4 Risks associated with work at height have been assessed and
mitigated prior to work being undertaken. This may include
checking workplace surfaces (eg. open holes), levels,
structures, evenness of ground, housekeeping, movement of
plant and equipment, proximity to unsafe areas etc.
12.7 Fall prevention strategies and permits are in place where there
is a risk of a person falling more than two metres from a safe
ground level.
12.8 Fall restraint and protection equipment has been provided (eg.
static lines, sala blocks etc) where it is impracticable to employ
fixed fall protection measures.
12.9 Fall arrest equipment is only used in conjunction with other fall
prevention devices.
772431297.xls Page 43 of 60
CRP12
CRP 12: Working at Height
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
12.11 Attachment points are installed by suitably qualified persons
and are regularly inspected.
12.14 Safe access and egress from work areas, including access
ladders which extend 1m past the work platform, are observed.
772431297.xls Page 44 of 60
CRP12
CRP 12: Working at Height
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 45 of 60
CRP12
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Required permits are identified in the site management plans and current/completed permits are have been approved by an appropriate person and records are available. Personnel (including
subcontractors) are observed to be working to permit requirements. Emergency procedures are adequate for work environment. Persons using permits (including subcontractors have been
appropriate trained in permit requirements. All high risk activities generally requiring permits are identified in the risk register and permit requirements have been applied.
Key Doc Refs C-064 Work Permits Procedure; Legislative and regulatory requirements for health, safety and environment; AS/NZS 2865:2001 Safe Working in a Confined Space; AS 1674.1-1997 Safety in Welding
and Allied Processes - Fire precautions; NOHSC:1016 (2005) National Standard for Construction Work
772431297.xls Page 46 of 60
CRP13
CRP 13: Permits to Work
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
13.4 Emergency procedures have been developed and
implemented for all work requiring a permit.
13.6 Each permit must clearly indicate: the location, nature and
scope of the work to be carried out in relation to the plant and
equipment involved; that all hazards are identified and that
appropriate controls are in place prior to work commencing
and that they remain in place during work progress, including
emergency or rescue procedures; informs, where necessary,
the on-coming shift of what work is outstanding, what work has
been done and where work has been carried out; provides,
where necessary, a formal hand over / hand back process to
ensure the work area is safe to return to normal operation
when work is completed; specifies PPE appropriate to the
work; other permits required for the scope of work to be
completed.
13.9 First aid and emergency equipment is available for all permit
activities.
772431297.xls Page 47 of 60
CRP13
CRP 13: Permits to Work
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
13.11 Permits are cancelled upon appropriate/adequate completion
of work and areas have been inspected, deemed safe for
others to return to the area for further works.
Excavation Permit
13.14 Risks associated with any excavation works are assessed and
controlled prior to any activity commencing. This may include
potential emergency situations, appropriate PPE is available,
there is safe access and egress, above ground and
underground services have been identified, other mobile plant
and equipment in the vicinity, potential water sources are
identified and the risk of flooding removed, the safety of
surrounding structures and areas has been assessed etc
13.17 A JSEA (or similar) has been developed and is available at the
site where the work is being conducted.
772431297.xls Page 48 of 60
CRP13
CRP 13: Permits to Work
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
13.18 Risks associated with confined space entry are assessed and
controlled prior to any activity commencing. This may include
extremes of heat and cold, flooding, gases, noise, radiation,
toxic liquies or solides, dusts, oxygen deficiencies / excess, etc
13.23 Fire suppression tools are available for all hot works related
activities.
772431297.xls Page 49 of 60
CRP13
CRP 13: Permits to Work
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
13.26 Flashback arrestors are used.
13.27 All portable equipment used for grinding and other heat or
spark producing operations are RCD protected.
13.29 Spill kits are available to prevent the spread of a spill both on
land and in the water.
13.31 Where appropriate, areas below workers (land and water) are
cleared of other persons and exclusion zones are established.
772431297.xls Page 50 of 60
CRP13
CRP 13: Permits to Work
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
13.32 Vessel movements have been identified.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 51 of 60
CRP13
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide Fitness for work risks are identified and there is an observed process in place for managing associated risks. Drug and alcohol testing is regularly conducted and warnings issued where required;
information on counselling and drug and alcohol awareness information is evident.
Key Doc Refs G-596 Fitness for Work Policy; G-463 Fitness for Work Guideline; G-236 Drug and Alcohol Procedure; G-435 Workers Compensation and Rehabilitation Procedure; G-Operational Workplace
Rehabilitation Guideline; AS3547-1997 – Breath Alcohol Testing Devices for Personal Use; AS4760-2006 – Procedures for Specimen Collection and the Detection and Quantitation of Drugs in Oral
Fluid; AS4308-2008 – Procedures for Specimen Collection and the Detection and Quantitation of Drugs Abuse in Urine
14.2 Risks associated with fitness for work have been identified,
assessed and controlled. Risks may include those associated
with drugs and alcohol, physical fitness (ie. Age, weight,
general health diet, smoking) and mental stress.
772431297.xls Page 52 of 60
CRP14
CRP 14: Fitness for Work
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
14.5 Drug and alcohol testing is conducted at an agreed and
appropriate frequency.Testing will be supported by the
disciplinary process.
14.6 There is evidence to show that the drug and alcohol testing is
shown to be supported by the disciplinary process.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 53 of 60
CRP14
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide There is a process in place to ensure that risks associated with lifting people or equipment are managed and that associated records are available. Personnel are observed to be conducting lifts safely
and that mechanisms for positive communication are evident. All personnel conducting lifting activities are appropriately trained. All lifting equipment is maintained, is listed on a register and is
regularly inspected.
Key Doc Refs C-092 Crane Lift Plan and Study Procedure; Legislative and regulatory requirements for health and safety; Australian and New Zealand Standards 2550 series, 2359 series and 1418 series
15.3 All lifts are subjected to a risk assessment (ie. JSEA, lift study
etc), which is undertaken prior to the lift and involves
personnel competent in lifting operations. Evidence of a
documented assessment is available, which may include a lift
study/plan, Take 5/Mac 5, JSEA etc
772431297.xls Page 54 of 60
CRP15
CRP 15: Lifting Operations
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
15.4 Heavy or complex lifts or where earth moving equipment is
used for lifting, have a lift procedure, lift plan/study and a
written risk assessment available. The following shall be
covered in documentation: assessment of the load mass and
radius, positioning of the load for lift and the final location of
the load position, lift calculations, the type of equipment that
will be used, use of spotters, rigging requirements and the
location of drop zones to ensure protection of workers and
others.
15.5 Where a lift is observed involving a lift study, the lift equipment
is shown to be rigged as per the plan drawing.
15.7 For lifts requiring a lift study and where there is more than one
rigger involved, a rigger has been identified as the rigger in
charge of the lift by the person authorising the lift (generally
the site engineer, Project Manager etc)
15.9 Lifting attachments (ie. chains, hooks, etc.,) are tested and
tagged as certified and records of certification shall be
maintained and current. Certification tags are attached to all
lifting attachments and are current. Equipment, which is not
current, tagged or is damaged has been removed from service
and is clearly identified as being out of service by way of
tagging and/or segregation.
772431297.xls Page 55 of 60
CRP15
CRP 15: Lifting Operations
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
15.11 Classified plant used to conduct lifting activities are registered
and are subjected to maintenance and inspections governing
that plant and category of equipment.
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 56 of 60
CRP15
Critical Risk Protocol Audit Template
Site:
Date:
Auditor(s):
Score '0' Non conformance A non-fulfilment of a requirement. These are defined in terms of minor non-conformance and major non-conformance and therefore
determine the severity of that non-conformance.
Score '1' Observation Isolated or partial deficiency in compliance with requirements (the intent of the criteria has been substantially met but the
implementation could be improved to provide better assurance of continuing compliance).
Score '2' Conformance To have fulfilled the requirement. Also used for OFI's where the audit requirement has been met but there are still opportunities for
improvement.
Note: Where an OFI is identified, it shall attract the same rating as that of the item it is representing.
Guide There is a process in place to ensure that all risks associated with blasting, handling, transporting, storage are managed. Approvals and licences are in place. Personnel are appropriately trained and
are competent to conduct tasks associated with explosives.
Key Doc Refs C-059 Use of Explosives Procedure; M-SF-078 Surface Storage, Magazines & Transportation of Explosives Procedure; M-SF-091 Safe Use and Handling of Explosives; M-UG-188 Underground
Cardinal Rules; M-SF-004 Surface Golden Rules Poster; Legislative and regulatory requirements for Dangerous Goods; Australian Standards 2187 series; Codes of Practice in each state for the
storage and handling of dangerous goods; ADGC, Australian Code for the Transport of Dangerous Goods by Road and Rail; AE Code, Australian Code for the Transport of Explosives by Road and
Rail
772431297.xls Page 57 of 60
CRP16
CRP 16: Explosives
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
16.4 There are controls in place to prevent noise contamination to
workers and the public.
772431297.xls Page 58 of 60
CRP16
CRP 16: Explosives
No. Audit Question Documented Assessment Observational Assessment Self Auditor
Assessme Rating
nt Rating
16.11 Procedures are in place for blast design, initiation, monitoring
and evaluation and misfire treatments to ensure that blast
objectives are met and risks are reduced to as low as
reasonably practicable (ALARP).
Total Rating 0 0
Maximum Score Available 0 0
Percentage #DIV/0! #DIV/0!
772431297.xls Page 60 of 60
CRP16