Weekly report

Date JAN- 11, 2024 Name Nafees


Description of this week
1.Factory block work 40%, steel structure main frame 100%
2.Labor BLD toilet tile fixing ,kitchen wall tile completed, internal wall stucco in progress 60%
3.Office BLD toilet partition block work completed, internal wall stucco in progress
4. LBG tank boundary plaster work in progress 10%
5.Substation plaster work completed, internal wall stucco in progress 80%
6.Storage block work 30%, steel structure main frame 100%
7.Guard room internal stucco completed, floor &wall tile fixing completed
8.New tank main structure completed, roof slab deshuttering completed

Plan of next week

1.Factory ,storage sandwich panel suppose to be delivered


2. Labor BLD floor tile fixing start
3. Office BLD wall and floor tile fixing start
4. Substation internal painting work 80%, floor epoxy painting start
5.LPG tank boundary wall plaster work finish
6.New tank internal waterproofing finish

Other
Works