Weekly report 14-3
Weekly report 14-3
1.Factory central partition block work 10%,, wall & roof sandwich panel installation 100%,
staircase & handrail fixing 100%
2.Labor BLD toilet &kitchen wall tile fixing completed, internal wall stucco completed, roof
waterproofing work completed.
3.Office BLD internal wall stucco completed, tile fixing in progress
4. LPG tank boundary plaster work completed, GAS tank installation in progress
5.Substation all internal civil &MEP work completed, waiting for inspection again
6.Storage block work completed, wall &roof sandwich panel installation 100 %, SOG casting
completed.
7.external manhole cover fixing 40%, curb stone fixing 60%, interlock fixing waiting washed sand
8.Alumium window frame installation 50%
Other
Works