Weekly report

Date MAR- 14, 2024 Name Nafees


Description of this week

1.Factory central partition block work 10%,, wall & roof sandwich panel installation 100%,
staircase & handrail fixing 100%
2.Labor BLD toilet &kitchen wall tile fixing completed, internal wall stucco completed, roof
waterproofing work completed.
3.Office BLD internal wall stucco completed, tile fixing in progress
4. LPG tank boundary plaster work completed, GAS tank installation in progress
5.Substation all internal civil &MEP work completed, waiting for inspection again
6.Storage block work completed, wall &roof sandwich panel installation 100 %, SOG casting
completed.
7.external manhole cover fixing 40%, curb stone fixing 60%, interlock fixing waiting washed sand
8.Alumium window frame installation 50%

Plan of next week

1.Factory all steel structure team work finish


2. Labor BLD floor tile fixing finish
3. Office BLD wall and floor tile fixing finish
4. Substation repairing finish, consultant inspection finish
5.External service backfilling 95%, manhole cover 90%, interlock 10%
6.Storage all steel structure team work finish

Other
Works