SEQUENCE 2
MOVING PROTECTION FRAME TO WS7 LAND SIDE

OHC 5T OHC 5T OHC 5T

E E

SLING CAP. 17% SLING CAP. 17% SLING CAP. 17%


SHACKLE CAP. 30% SHACKLE CAP. 30% SHACKLE CAP. 30%

D
ELEVATION VIEW D

1 2 1 2
CHOKER CHOKER
OHC 5T LIFTING POINT OHC 5T LIFITING POINT
C C

GROUND 0 11/01/2024 ISSUED FOR CONSTRUCTION LFI REP MR


B B
REV DATE DESCRIPTION DRN CKD APP

REVISIONS

DARWIN PIPELINE DUPLICATION


PROJECT Santos
1 2
CHOKER
OHC 5T LIFTING POINT
PT. PROFAB INDONESIA

A A
PLAN VIEW
PLET PROTECTION FRAME
LIFTING ARRANGEMENT DRAWING

JN1503-JSA-PF-01 02 NTS 0