1.1 Definitions
1.1.1 COMPANY
1.1.2 CONTRACTOR
1.1.3 PROJECT
1.1.4 PROJECT philosophy
1.1.4.1 PART /I/
1.1.4.2 PART / II /
1.1.5 PROJECT priorities
1.1.6 inspector
1.1.6.1 COMPANY inspection
1.1.6.2 CONTRACTOR inspection
1.1.6.3 THIRD party inspection
1.1.7 Shall
1.1.8 Should
1.1.9 Could
1.1.10 Mechanical Completion Certificate (MCC)
1.1.11 Performance tests:
1.1.12 Provisional Acceptance Certificate (PAC)
1.2 Scope
1.3 Engineering
1.4 Procurement
1.4.1 Purchasing
1.4.2 Expediting
1.5 Delivery and transportation
1.6 Construction
1.7 Contract schedule
1.8 Pre-commissioning
1.9 Commissioning
1.10 Documentation
1.11 Warranty/guarantee
Page 1 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
Page 2 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.1 Definitions
The CONTRACTOR’s scope of work includes, but not limited to, the engineering,
procurement, personnel, supervision, inspection, materials, consumable, transportation,
construction , pre-commissioning, commissioning and start up the PROJECT for the
successful execution and timely completion with the all safety and operation requirement of
the” ARAB GAS PIPELINE PROJECT- PHASE I” For Syrian Gas Company.
Within this contract the following definition shall be applied:
1.1.1 COMPANY
The COMPANY means when this word used the:
SYRIAN GAS COMPANY or its authorized representatives performing work
on behalf of SYRIAN GAS COMPANY.
1.1.2 CONTRACTOR
The CONTRACTOR, if any, selected by the COMPANY to perform all the
work of PROJECT and provide all the Equipment/Materials and Services as
described in this RFQ and Scope of Work.
1.1.3 PROJECT
The PROJECT mean when this word used the:
“ARAB GAS PIPE LINE PROJECT- PHASE I “Is defined as engineering,
procurement, construction for all disciplines and activities which include but
not limited to: pipeline installation ,block valve stations installation ,launcher
receiver station, fiscal metering station ( FMS ) and tie-in points with existing
facilities for all required activities but not limited to: civil, survey, soil
investigation, structural,, mechanical, instrumentation, electrical, control,
telecommunication, Cathodic protection ,pre-commissioning ,commissioning ,
start-up activities and utility systems etc in addition to any activity required to
make the system function based on the Turnkey job basis.
Page 3 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
Note:
The advertisement for the execution of PHASE II of the PROJECT from
Rayan to the Syrian/ Turkish border(not included in this project scope) may be
established during the execution of PHASE I.
The PROJECT consists of two PARTS included but not limited to the
following shown in drawing 6000-10-011:
Installing approximately 310 km of “36”API 5L X70 pipeline between
Rayan area and the Syrian /Jordanian border.
ten (10) Block Valve Stations tagged as follow:
BVS 6001: ref to drawing 6000-10-01
BVS 6002: ref to drawing 6000-10-01
BVS 6003: ref to drawing 6000-10-06
BVS 6004: ref to drawing 6000-10-01
BVS 6005: ref to drawing 6000-10-01
BVS 6007: ref to drawing 6000-10-01
BVS 6008: ref to drawing 6000-10-01
BVS 6009: ref to drawing 6000-10-01
BVS 6010: ref to drawing 6000-10-01
BVS 6011: ref to drawing 6000-10-04
One (1) intermediate station (launching and receiving) tagged as follow:
S6006 near BVS 913: ref to drawing 6000-10-03
Launcher at the outlet of Syrian /Jordanian border tagged L6000: ref to
drawing 6000-10-05
Receiver at the Rayan area tagged R6012: ref to drawing 6000-10-04
The Deir Ali scope which include but not limited to the following:
Page 4 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
fiscal metering station ( FMS ) near the Deir Ali area with 3MMSCMD
capacity: ref to drawing 6000-10-12
36 Inch of API 5L X70 pipeline branch with approximately length
14 km equipped with launcher tagged 003L and receiver tagged 003R.
Three tie-in with existing gas net work facilities as following:
With the 18 inch Omar pipeline via two (2) hot taping points up
stream of the BVS 913: ref to drawing 6000-10-03
With the 24 inch Palmyra pipeline via one (1) hot tapping point
upstream of the BVS 4904: ref to drawing 6000-10-02
With Rayan existing manifold: ref to drawing 6000-10-04
Page 5 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.1.5 PART I
To feed the gas from the Arabic gas pipe line at Syrian-/Jordanian border to
the block station BVS-6003
The PART I mean when this word used the: Some or the entire PROJECT
activities which are contained but not limited to this shone in the schematic
drawing (6000-10-09) and described hereunder:
A Pipeline
36 inch API 5L X70 Pipeline between the launcher station L-6000 At the
Syrian-/Jordanian border and the BVS-6003 with approximately length 80 km
with all associated systems and facilities
B Scraper Receiver (R) and Launcher (L)and anchors
L-6000 at the Syrian /Jordanian border
C Block Valve Stations (BVS)
BVS-6001.
BVS-6002.
BVS-6003.
D Deir Ali branch scope which include but not limited to :
1st. Fiscal Metering Station (FMS) near the intended power plant at Deir
Ali.
2nd. pipe line
36 inch API 5L X70 Pipeline between the BVS- 6003 and fiscal metering
station (FMS) beside the intended Power Generation Plant near Deir Ali
with approximately length 14 km with all associated systems.
3rd. Scraper Receiver (R) , Launcher (L) and anchors
L-003 at the beginning of the pipeline branch (from BVS 6003 toward
Deir Ali FMS): ref to drawing 6000-10-07
Page 6 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
R-003 at the end of the pipeline branch (from BVS 6003 toward Deir
Ali FMS): ref to drawing 6000-10-08
E All related piping, materials, equipment, instrumentation, electrical, control and
telecommunication systems, mechanical, civil and cathodic protection system, in
addition to all auxiliary and utility systems like potable water, sewer, etc.
F Any other activity required by safe design and easy operation
1.1.6 PART II
This part to complete the PART /I/ from BVS-6006 to receiver station R-6012
at (Rayan)
PART II include but not limited to this shown in the schematic drawing
6000-10-010 and described hereunder:
A Pipeline
36 inch API 5L X70 Pipeline between the BVS-6003 with approximately
length 230 km with all associated systems
B Block Valve Stations (BVS)
BVS-6004
BVS-6005
BVS-6007
BVS-6008
BVS-6009
BVS-6010
BVS-6011 near the BVS 4904
C Intermediate station
The intermediate station or pigging station tagged S-6006 consist of receiver
and launcher tagged R-6006 and L-6006.
D Scraper Receiver (R) , Launcher (L)and anchors
R-6006 which consider as a part of the intermediate station S-6006 near
BVS 913
L-6006 which consider as a part of the intermediate station S-6006 near
BVS 913
R-6012@ Rayan area
Page 7 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
Page 8 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.1.8 inspector
1.1.8.1 COMPANY Inspection
The inspector(any person authorized to act on owner’s behalf for all maters
related for Quality Control, Testing and Acceptance of the Work described in
the Scope of Work ).
Inspector shall at all times have access to the construction or fabrication or test
work wherever it is in preparation or in progress.
Page 9 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
They will have the right to reject materials or workmanship, which are defective
and require correction.
inspector will decide any questions which may arise as to the quality and
acceptability of construction or fabrication or test work performed or material
used and as to the rate of progress of the work, and will decide all questions
which may arise as to the interpretation of the specification and drawings.
COMPANY’s inspector has authority to stop the construction or fabrication or
test work whenever, in his opinion, such stoppage may be necessary to ensure its
proper execution.
Note:
Inspection shall not relieve CONTRACTOR from any duties, obligations,
responsibilities or liabilities under this Contract.
Page 10 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
The CONTRACTOR organization chart inspection team shall include but not
limited to the following:
Material inspectors
Pipe line and piping inspectors
welding inspectors
NDT inspectors
coating, painting and insulation inspectors
hydro testing inspectors
civil (building ,foundation and steel structural ) inspectors
Instruments/ control inspectors.
Electrical inspectors
Cathodic protection inspectors.
Telecom inspectors
Page 11 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
The CONTRACTOR shall advise the COMPANY six (6) weeks at least in
advance for any shop-testing schedule of critical equipment in order for the
COMPANY to assign their authorized representative to witness such test.
Page 12 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
The CONTRACTOR will be responsible for the new Facilities until the
Certificate of Provisional Acceptance (PAC) has been signed and issued by
COMPANY.
Page 13 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.2 Scope
The omission of any essential provision here from, cannot be construed to relieve the
CONTRACTOR from any duty or obligation, necessary for the complete
installation of the facilities to be ready for use and safe and easy operation as a
complete system in safe conditions.
The CONTRACTOR shall take full responsibility for all work associated with interfaces
with existing COMPANY and Third Party Facilities, such as electrical connections,
pipeline and piping connections, cathodic protection, fiber optic telecommunications and
control cable connections etc.
This shall include the site visits to the owners of the existing facilities in order to
investigate exact location and type of existing facilities, obtaining of approvals, permits,
permission for locating and methods of interfacing, ensuring compatibility between new
work and existing facilities, installation of all systems/facilities to ensure a safe, operable
interface and any remedial action necessary to return the existing facilities to its original
condition.
The COMPANY should render assistance wherever possible and if required to accelerate
the job within the contract’s terms, conditions and obligation without any time/cost
impact to the COMPANY.
The CONTRACTOR shall keep the COMPANY fully aware of all interface
discussions, activities and progress.
Interfaced parties shall also be kept fully informed of the planning and operations within
those areas that affect them.
Page 14 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.3 Engineering
The CONTRACTOR shall have the expertise in the design and preparation of
equipment specifications, data sheets, calculations, requisitions, detailed pipeline
alignment sheets, CADD drafting, computer process simulations and technical bid
evaluation and all engineering requirements may be necessary to safe design and easy
operable PROJECT
(For more details see section 2- Engineering Scope).
1.4 Procurement
All material and equipment/instruments supplied for the “ARAB GAS PIPELINE
PROJECT PHASE /I/” shall be suitable for the PROJECT conditions (environmental,
site and gas composite) as defined in the “EXHIBIT-G, Data Reference and Contract’s
General Specification”.
1.4.1 Purchasing
The CONTRACTOR shall purchase or otherwise provide all materials,
equipment, supplies required for the installation and timely completion of
the PROJECT.
Line pipe , valves , actuator ,line break ,DCS system , telecom
system ,online chromatograph ,orifice flow meter ,instruments and its
accessories to be supplied by the CONTRACTOR shall be new /unused
and purchased according to the company vendor list only
Other Equipment, materials and Construction supplies shall be purchased
from the first class and good known vendor/manufacturers included in the
approved vendors/manufacturers List which will be issued prior to the
contract signing in accordance with specifications and requirements of the
contract.
The COMPANY has the right to reject any materials or equipment supplied
or intended to be supplied from any vendors/manufacturers are not in the
approved list without any increase in the contract prices or change in the
PROJECT time schedule.
Page 15 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.4.2 Expediting
The CONTRACTOR shall perform all the expediting required for all
their material purchases and shall ensure that the vendors/manufacturers
and or sub CONTRACTOR(s) comply with the PROJECT
specifications, and no delay will affect the COMPANY time schedule.
Page 16 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.6 Construction
The CONTRACTOR shall have the expertise in the construction of facilities and
installation of equipment to perform all construction works to complete the PROJECT
as per contract specification and requirement
(For more details, see section 3-Construction scope).
CONTRACTOR shall provide a detailed and complete schedule indicating activity start
and completion times. This schedule will conform to the milestone dates of
COMPANY’s Schedule.
The schedule shall address for each PART individually of the project as a minimum
the following:
Basic/Detail design complete
Purchase orders issue
vendor selection
Mobilisation
Various Construction activities according to the COMPANY requirements
and priorities
Page 17 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.8 Pre-Commissioning
The CONTRACTOR shall have the expertise in the pre-commissioning and all activities
associated to the bringing the constructed facilities into such stat as will permit
introduction of process media and commissioning of the PROJECT as per contract
specification and requirement
Pre-commissioning shall include, all activities associated with bringing the constructed
PROJECT into such a state as will permit introduction of process media and
commissioning of the facilities.
Page 18 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
After COMPANY’s satisfaction that all pre-commissioning tests and verifications have
been properly executed and registered, CONTRACTOR will be formally notified of
COMPANY's intention to introduce hydrocarbons.
Page 19 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.9 Commissioning
Commissioning shall be conducted by CONTRACTOR in accordance with the approved
commissioning manual, after CONTRACTOR has demonstrated to COMPANY’s
satisfaction that, all pre-commissioning activities have been successfully completed.
CONTRACTOR remains responsible for the correct and safe operation of the facilities
during commissioning.
All modifications required for safe operation shall be registed as blue marked up drawing
to be considered on the final as built drawings
During the initial start up and commissioning of the PROJECT or parts thereof,
CONTRACTOR shall make available vendors/manufacturer representative(s) as
defined in the COMPANY approved commissioning procedures or as otherwise
identified and agreed as needed.
CONTRACTOR is required to attend daily commissioning meetings at which
COMPANY’s authorized representative(s) will require detailed briefings from
CONTRACTOR as to which systems will undergo commissioning.
CONTRACTOR is advised that all interfaces between the existing Palmyra 24” pipeline
at BVS 4904 or between 18” Omar pipe line at BVS 913 or the Rayan existing
manifold or the interfacing with the gas co-ordination center and facilities shall be fully
identified and discussed with COMPANY's authorized representative(s) and other parties
like AFPC for BVS 913 .
Page 20 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
CONTRACTOR shall fully define the possible effects of his commissioning activities
on the existing process, instrumentation and electrical systems.
Page 21 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
CONTRACTOR remains responsible for the correct and safe operation of the facilities
during commissioning.
1.10documentation
Documentation shall be provided by CONTRACTOR as per requirement of schedule
“PEA- PROJECT execution and Administration”, provided in EXHIBIT-F.
1.11Warranty/Guarantee
CONTRACTOR shall warrant/guarantee the equipment and workmanship as per the
requirement of EXHIBIT-K, Warranty of workmanship and Materials.
Page 22 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.12CONTRACTOR Services
1.12.1 Scope of Work
Spare parts, special tools and testing equipment, shall be procured and delivered
by CONTRACTOR to COMPANY’s alrayan yard (12 km east of Homs City)
in accordance with the following provisions.
Page 23 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
The Provisional Acceptance Certificate (PAC) shall not handed over until
two years recommended spar part and material included in EXHIBIT (J)
Available at site
Page 24 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
and using identical materials as used in the original materials and equipment
which the spare parts are intended to replace.
Such spare parts shall be fully interchangeable with the original materials and
equipment or portions thereof without modifications to such spare parts or to the
original materials or equipment.
Contractor's furnishing of spare parts pursuant to this article shall not relieve
CONTRACTOR of its obligations under the “EXHIBIT-K, Warranty of
Workmanship and Materials”.
The nature and quantities of such special tools and testing equipment shall be as
recommended and documented by the vendors/manufacturer of the various
equipment items.
CONTRACTOR shall compile a list of all the special tools and testing
equipment and shall submit it to COMPANY's authorized representative(s) for
approval.
Page 25 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
In fulfilling the requirements of this article CONTRACTOR may elect to construct and
operate an on-site camp.
In this event, the location, layout, construction standards, facilities and operations of
the camp shall be subject to the prior and/or ongoing review and approval of
COMPANY's authorized representative(s).
In the event any medical situation is beyond the capability of the on-site first aid
service, then CONTRACTOR shall transfer the patient to a hospital or other
medical facility as appropriate.
1.13.2 Security
Page 26 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
The purpose of such security service shall be to permit entry to the construction
sites of only those persons authorized by COMPANY, to assist in the prevention
of pilferage of material items, to maintain orderly conduct on the site and to
attend to other schedule and unscheduled security situations.
1.13.3 Sanitation
CONTRACTOR shall furnish all personnel, equipment and supplies to provide
services and maintain adequate sanitary and decent on-site sanitation facilities.
Such facilities shall be provided adjacent to each location where work is being
performed.
Page 27 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
Upon completion of the work, CONTRACTOR shall at its expense remove all
such signboards and cleans up the applicable areas to the satisfaction of
COMPANY's authorized representative(s).
All CONTRACTORs’ costs incurred in the compliance with this article shall
be deemed to be included in the Contract Price and such costs shall not be the
subject of separate payment by COMPANY.
Page 28 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
Page 29 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
Page 30 of 31
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
1-GENERAL SCOPE
1.15drawings
CONTRACTOR shall provide all drawings for all activities of PROJECT.
CONTRACTOR shall keep a set of construction drawings which they will mark-up
reflecting the As-Built Installations and shall submit such drawings red marked to the
COMPANY within fifteen (15) calendar days of job completion as well as, As Built,
drawings in both hard and soft copy to be delivered to COMPANY within one month
from the date of issuing of Mechanical Completion Certificate (MCC).
By "As-Built", it means that the CONTRACTOR has adequately shown or provided
additional sketches, to clearly convey the information for the actual pipeline, piping and
instrumentation configuration etc.
1.16discrepancies
In case a discrepancy arises or exists between codes, standards, drawings and
documents, the most severe shall govern in the following priority:
1.16.1 RFQ tender documents
1.16.2 (AFPC) scopes and specifications
1.16.3 International industry codes and standards
Page 31 of 31