HIGHER COLLEGE OF TECHNOLOGY

FACULTY OF ENGINEERING

______________________________________________________________________________

Work Placement Final Report

EGN X806
______________________________________________________________________________

Student Name Mariam Saeed Almemari


Student ID H00370639
Program BCVET
CRN Work Placement 1 (202130_3007)
College Mentor Dr. Ahmed

Company Name MIRAL


Supervisor Name Eng. Eion Kally
Supervisor position Eng. Khulood
WP start and end Date 30/ Mat – 8-Jul

Student Signature: Supervisor Signature:

X X

Date: 26/ JUN/ 2022 Date: DD/ JUN/ 2022

1|Page
Table of Contents

Table of Contents...................................................................................................................................2
Company Information.................................................................................................................................3
Health and Safety:......................................................................................................................................6
Work Details:............................................................................................................................................10
SeaWorld Project...................................................................................................................................12
Cost control...........................................................................................................................................19
Feedback:..................................................................................................................................................21
References................................................................................................................................................23
THANK YOU LETTER..............................................................................................................................24

Company Information
1.1:

2|Page
Miral, which means "gazelle" in Arabic, was founded in May 2011, and symbolizes agility and
embraces our principles

Miral Asset Management is an Abu Dhabi-based real estate development, management, and
investment company responsible for the development and management of Yas Island. .. We are
engaged in the real estate service industry and have 6 subsidiaries, affiliates, and affiliates. This
company is classified as a state-owned enterprise (SOE). In addition, through its wholly-owned
subsidiary Farah Experiences Warner Bros. World Abu Dhabi, Ferrari World, Yas Waterworld,
and the planned SeaWorld Abu Dhabi.

They hope to contribute to the capital's long-term development as a sustainable, diverse, and
globally integrated economy through our revolutionary and innovative projects.
They will continue to work with smart real estate partners, investors, and top brands from across
the world to realize this ambition.

Miral Mission: our primary goal is inspired by a dedication to Abu Dhabi's continuing
expansion, and we've played a significant part in the emirate's Economic Vision 2030 by
supporting the rapid evolution of the leisure and entertainment sector.
We hope to contribute to the capital's long-term development as a sustainable, diversified, and
globally interconnected economy through our revolutionary and innovative projects.
Key Real Continue to contribute to this goal in collaboration with

1.2 & 1.3:

3|Page
4|Page
Miral oversees managing significant leisure, recreational, and cultural attractions, as well as the
development of substantial real estate parcels on Yas Island and Abu Dhabi that will house
thriving communities with year-round recreational and leisure amenities.

1.4:

I worked in four Departments is:


 Human Resource Department
 Sea World Abu Dhabi Site Office (SWAD)
 Project services Department, Project Control team.
 Project Delivery Department

1.5:

I was working with many teams:


 HR. Intasr in Human Resource Department
 Sea World with Dir. Eoin and Eng. Khulood (Supervisors).
 Project services Department, Project Control team With
 Project Delivery Department with

5|Page
1.6:

The main aim of Miral company is how they can improve you as an engineer in your personality,

skills, and knowledge. They provided to the trainer in their work placement how to deal with the

work as engineer internal or external.

As engineers, we design, construct, analyze, build, and maintain machines, engines, and

structures.

The Internal work as an engineer is to design all the projects using AutoCAD 2D and 3D.

….. they have the cost which we learn in economics and applied the quantity surveying, project

management,

External work is when the engineer visits the site and checks on the health and safety of the

workers and construction materials, how everything goes with the workers, also the structure of

the building.

Health and Safety:


2.1: Company health and safety profile

Yas Marina Management is committed to providing and maintaining a safe and healthy
environment for all its employees and to protecting the safety of visitors, tenants, contractors,
neighbors, a guest at our facilities, and all other persons affected by our business operations.

 In recognition of the company's vision to create destinations that unite people and places
through unique immersive and exciting experiences the Yas Marina accepts:

 Ultimate responsibility to lead the company in providing for the occupational


health, safety, and environment (OSHE) to protect people and the environment of
the UAE from adverse impacts.
 All company development and decisions will adequately reflect the OHSE,
people’s welfare, and the environmental requirements as outlined in this OHSE
policy.
 The need to actively encourage support and participation in OHSE and
improvement from employees and our project delivery teams to achieve OHSE
excellence.

6|Page
 To be informed and alert to relevant OSHE risk management issues and changes
to UAE Federal Legislation, Abu Dhabi Municipality, and marine-related
regulations.

 The Yas Marina Board is committed to:

 Preventing the incidence of personal injury, Occupational illness, and


environmental incidents by working with our project teams and partners to create
a proactive OSHE culture and incident-free environment at all our operational
locations, minimizing the loss caused by near misses, and fire and our everyday
activities.
 Providing training, instruction, information, and supervision to maintain the
competency of our employees at all levels of Yas Marina through competent HSE
professionals.
 Ensuring adequate resources and funding are available to implement OSHE and
that our department leadership has appropriate OSHE operational accountabilities.
 Setting and reviewing OSHE objectives, targets, and reporting metrics, with
relevant KPIs including appropriate OSHE responsibilities in the manager's
personal objectives and performance reviews.
 Encouraging and supporting manager's employees and project teams in their
resolution of a safety issue to promote continuous OSHE improvement
 Liaising with our facility management teams and tenants to help them support Our
OSHE culture and goals.

The Yas Marina Board expects all Yas Marina employees to recognize their duty to support our
safety culture and co-operate with its OHSE management system requirements, by working
safely, preventing others from being exposed to
unnecessary risk, and taking action where needed. Our employees should commit to caution
being exercised during their work at any Yas Marina operational location and to immediately act
on any unsafe situations.
The Yas Marina Board, through the company management, will ensure that our employees,
tenants, site, and visitors do not experience any unsafe conditions. We welcome the initiative of
Yas Marina employees and others to improve OSHA standards. This policy, safety objectives
and KPIs will be formally reviewed annually, or after a significant change.

7|Page
2.2: Health and Safety training they attended at the company

2.3

8|Page
Miral Company is responsible for establishing and developing the foundations, rules,
and procedures for occupational safety and health at their workplace, identifying
occupational hazards at work sites and methods to mitigate them, providing
occupational safety and health requirements and tools, and monitoring their use, as well
as preparing documents and reports specialized in work results.

HAZAR ACTION
SL RISK PROOF
DESCRIPTION TAKEN

Emergency exit
The emergency exit lights should be
1 low
light not working. operational
every time.

Materials should
be removed;
Poor Housekeeping
proper
2 - This may create a Medium
housekeeping
fire hazard.
should be
carried out.

Materials should
be removed;
Poor Housekeeping-
proper
3 Fire cabinet stored Medium
housekeeping
unsafely
should be
carried out.

9|Page
Informed to
Electrical socket
6 concern site in Medium
open condition.
charge

The waste bin


Waste bin full and should be
overflowing the emptied, and
items and poor unwanted
housekeeping materials should
11 Medium
(materials and be removed,
carboards) and this proper
may create a fire housekeeping
hazard. should be
carried out.

Mural painting work Scaffolding


- Working on the Should be
scaffold without inspected by
12 PPEs and safety Competent Medium
harness Person and
Scaffold is not proper PPEs
inspected properly. should be used.

Work Details:
3.1
Week Department/ Proposed training content
number Section
1 Human  HR induction about MIRAL company, the different departments.
Resource  HSE induction, BCM induction about the detailed structure and the company rules and
Department regulations.
 Site Visit to see the different assets (Etihad Arena & Yas Marina).
 Construction sites visit the construction site where she will be placed as a civil engineer.
 visited the construction site of the new project

2 Sea World  Visit SWAD site Office, where the intern will continue the work placement.
Abu Dhabi Site  Introduce to the Project delivery team (project management, design and cost consultants)
Office (SWAD)  Join Project Service department, introduce to the department responsibilities and objective.

3 Project  Introduce to the project control team, understand how to Prepare, update & monitor the
services Detailed Master Program for projects.
Department,  Gain basic understanding on Miral Control Procedure of the LDC & GC Baseline Program.
Project Control  Gain a basic idea on Controlling Progress Reporting process for ongoing projects.
team.
 Understand the basic of reporting in the project, Providing Management with Progress Status
Reports on regular basis.

4 Project  Introduce to the cost control team.


Service  Gain basic understanding on cost management procedure.
Department,

10 | P a g e
Cost Control  Gain basic idea on payment process.
team  Gain basic idea on cost reporting and forecasting tools.

5 Project  HSE & Worker Welfare:


Delivery o General Safety Awareness
Department o Risk Assessment
o Hazzard Communication and Identification
o Fall Protection
o Fire Safety
o Electrical Safety

6 Project  RC – Structural: Supervision and Site Inspection for RC


Delivery  Concrete Structures
Department  Enabling Works and Shoring
 Foundation
 Structural Design Review

7 Project  General Awareness anput the Construction Activity


Delivery  Technical Submittals & Review
Department  Inspections and Site Concerns
 Document Control and Closing Process

8 Project  Steel Structures


Delivery o Selection of Structural System
Department o Design Review
o Fabrication and Construction Sequence
 Infrastructure
o Roads
o Utilities
o Landscaping (Soft/Hardscape) Works

3.2

 Use a reasonable voice level

 Don’t hold meetings in your/(or anyone else’s) workspace

 Don’ttalk/yellpastyourimmediateneighbor

 Manageringersandnotifications

 Look before you interrupt

 Don’t create unnecessary noise

 Respectothers’concerns

 Respectothers’privacy

3.3 Introduction:

11 | P a g e
This work placement aimed to introduce and familiarize the student with the building
environment in the natural world. To show them how things work in a group on a practical level.
It is time to demonstrate the skills I have shown throughout my educational career, regardless of
what I have studied academically. Learning is a process that lasts a lifetime. This summer, I was
placed at MIRAL Company to familiarize myself with the construction environment and
industry, notably in the United Arab Emirates. It was an eight-week work placement program in
which I was shown, tested, and advised on the nature of construction work and related topics
such as execution, dangers, and safety, among other things.

Work Environment

It was a specific type of employment, such as design office and site supervision. My working
hours were from 9:00 a.m. to 5:00 p.m.
I have two points I work on it:
1. In the office work, I was talking about building drawings and accounting principles like
Project Management and Quantity. I showed a few construction drawings to get an idea of
what the graphics look like after printing and how to properly proofread the construction
project, knowing what infrastructure, soil, site surviving, etc.
2. 2. While the site implementation was more realistic, I noticed the infrastructure, including
how the construction, civil process, and civil facilities were analyzed in a project, SeaWorld,
as I observed the practical application of the working drawings.

SeaWorld Project

Miral engaged AECOM to undertake Lead Design Consultancy services for the SeaWorld Abu
Dhabi (SWAD) project on August 26th, 2018. This report summarizes the progress of the design
up to 100% Stage 4 and the activities undertaken to date, in the formal Stage 4 Progress
Submission Deliverable.

12 | P a g e
SeaWorld San Antonio was one of the first SeaWorld parks ever to open and is heralded as the
largest of the parks. It measures a colossal 416 acres! It's recommended that you need at least
two days to walk around the park and do all the attractions, potentially more in busy periods.

This is a thorough explanation of this enormous project.

Level 1 (Ground):
This level mainly comprises of staff area, back-of-house facilities, and an R4 research center,
and serves as the main guest entry point from parking, luggage scanning, and security check
area. The back-of-house facilities include warehousing for food services, retail, and games,
holding areas for animals as well as MEP plant and equipment rooms. The engineering and park
support service offices are also located at this level.

13 | P a g e
Level 2:
This level is comprised of staff and support areas with a portion allocated to guest spaces which
include exhibition areas, the Sea Lion Stadium, Rays Exhibition area, Tropical Play Climber, and
Animal Care Guest Viewing windows.

Level 3:
This level is the main guest ticket entry, experience, and circulation area of the park with access
to attractions such as the Sea Lion Stadium, Dolphin Stadium, Pearl Dive Stadium, aviary, and
various retail, and Food and Beverage outlets. The level also contains ticket counters, group
sales, luggage scanning, and a security check area.

levels 4 and 5:
These levels include portions of the Endless Ocean and Polar Ocean attractions / Realms, entry
to the upper seating area for the Sea Lion Stadium, dining areas, and MEP rooms. The 'Sea Walk
experience is also accessed from level 5.

Level 5
Roof: As per the current design at the beginning of Work Stage 3, the roof level of the building
includes only Mechanical Penthouses and exhaust fans.

There will be different types and sizes and gender of animals around the world in the sea world
project an example:

14 | P a g e
 Dolphins
 Pacific walrus
 Californian sea lion
 Dugong
 Penguin
 Sharks

The steel frame in Sea World is 5m high and it was composed of linear steel elements bolted
together.
The steel members have approximately 0.25m diameters.
Steel frame buildings are metal structures, consisting, Steel beams and vertical columns, welded
together in a rectangular grid to support the floors, walls, and roofs of buildings. Steel frame
structures are used to form the 'skeletal frame' which a building is then constructed around.
Steel frame construction is steadily increasing its market share in the construction
and civil engineering sector. Steel frame construction is a good option for a
diversity of projects for many reasons, including:
 Durability- The components included makes steel sustain more structural weight and last
longer than the wooden ones.
 Sustainability- once it is made, it can be used forever.

 Faster Build Time- steel parts are prefabricated, there are already follow the
respective code standards and dimensions. Therefore, your engineers do not have to
worry about the quality of each piece.
 Lightweight - the density of steel with the density of wood, steel is heavier.
 Eco-Friendly- completely recycled the materials.
 Easy Fabrication- Steel parts are easily fabricated in a variety of shapes and sizes.
 Hybrids with Other Building Materials many construction companies offer hybrid steel
and wood buildings which take advantage of the insulation properties of steel and wood.

15 | P a g e
PRE-CAST REINFORCED CONCRETE STRUCTURES. The bolted joint connections helped
the frame to act as a monolithic structure so that the moments are transferred with no risks down
to the bottom members.

The reinforcement of concrete is often accomplished with the use of steel reinforcement bars or
rebars, but it can also be done by using additional concrete passively. Reinforced concrete is
used for construction on a large scale, such as bridges, dams, piers, tall buildings, and stadiums.
Below are the Different Types of Reinforced Concrete:

• [1] REINFORCED CEMENT CONCRETE (RCC)

• [2] REINFORCED BRICK CONCRETE (RBC)

• [3] FIBRE REINFORCED CONCRETE (FRC)

• [4] PRESTRESSED CONCRETE

16 | P a g e
The cement is stored on top of the wood because the adhesive should be protected from water.
The material is important to minimize the risks of potentially life-threatening incidents.

Below are points to keep in mind when storing cement –

 Keep cement in a dry, leak-proof, and moisture-proof environment.

 Doors and windows must be kept closed.

 Bags must be stacked on a wooden plank or on a strong tarpaulin at 6 inches above the
ground.

Store Cement Bags On A Wooden Plank At 6 Inches Above The Ground

 Bags must be stacked at least one foot away from the walls.

 The width of the stack must not be more than the length of 4 bags or 3 meters.

17 | P a g e
 The height of the stack should not be more than 10 bags.

 Bags must be kept close to each other to prevent the circulation of air.

 Cover the cement with tarpaulins or plastic sheets in monsoons or when it is required
to be stored for a longer time.

 HDPE and paper bags must be stored separately.

 Do not use hooks to lift cement bags.

 Always use cement in the first-in, first-out method.

Cost control
The Project cost plan includes the schedule of costs to be incurred during the project and the
associated estimates. These are the expenses that are anticipated to be incurred when project
activities are finished. The cost plan is created after the resource plan and activity schedule
because they feed into it. The project manager is aware of the specifics of the project as a
consequence of the project planning activities, allowing for the project budget to be refined.
Examples of Cost Control:
 Renegotiating contracts with more favorable terms.
 Getting more competitive bids from different vendors.
 Improving product quality to reduce rework and scrap.
 Reducing the number of items carried in inventory.
 Reducing employee expenses with better expense management.
 Accounts payable outsourcing.

18 | P a g e
3.4
One of the problems I encountered when training at Miral was that the engineers explained
and worked on specialty materials that I hadn't taken yet (Project Management and Quantity).
In this case, I told the engineers about this, and they helped and showed me new information
and a simplified explanation about those two materials.
Their information will help me next semester when I take Project Management and Quantity.

3.5

In this experience, I applied my knowledge from college in the MIRAL Company


- Construction Materials

19 | P a g e
- Soil
- Project Management
- Economic
- Strength
- The safety while going to labs

Skills:
- Teamwork
- Solve problem
- Creative Ideas
- Improve my leadership skills
I developed my knowledge in Miral company by visiting the site, doing my knowing expertise,
and seeing how they were applied in the real-life special at a massive project in Abu Dhabi. In
addition, my skills were developed how to be a professional lead and solve problems and deal
with them at the site and how to motivate the employees

3.6
Miral Company is full of people who are more motivated and productive due to the feeling of
appreciation and support they receive from Miral Company and the fact that Miral Company
provides them with all the resources they require. Miral is also an employee management tool
that recognizes and supports employees' growth and development.
The goal for Miral company is to develop business with high business potential energy in all
organizational members.
1- Understand the reason for the employee's poor performance
2- Motivating Employees
3- Organizing
4- Understand employee requirements
5- Improving employee morale
6- Treating employees as if they were family

20 | P a g e
7- They give every employee the right to give his opinion.
8- Encouraging continuous communication between employees
9- Staff training and promotion
10- Better deal with unexpected situations
Today's business environment is all about constant change. This change not only brings
challenges (to the workforce), but if handled properly, it also opens up opportunities previously
unexpected.

Feedback:
4.1
 I see that Miral Company adheres to their work very beautifully and works with
happiness and pride, characterized by the development of the city of Yas in an
impressive, beautiful, and befitting manner for Abu Dhabi.
 Development from the level of the country's economy.
 Curiosity and curiosity.
4.2
 They feel proud of their work and have a positive spirit when they accomplish in
their work groups. And their vision to insist on achieving collective success.
 Their work is always global, which is the pride of this company and differentiates it
from other companies.

4.3

 The knowledge and the skill for the college is the teamwork at processing the job in
addition to taking each other opinions and Checking with the team.

4.4

• Improve employee skills according to technological changes.


• Employees require little learning time to achieve acceptable work standards.
• Help with work problems.
• Giving employees direction to get to know their organization more.
• Meet human resource planning needs. Improve employee skills through
technological changes.
• Employees require little learning time to achieve acceptable work standards.
• Help with work problems.

21 | P a g e
4.5
I'm extremely happy to work with the Miral company; it was a pleasant experience, and I've
learned a lot from them. As I previously stated, the company's culture, which includes a
"upbeat attitude, the polite treatment of the workers, and their sense of duty," encourages
me to work there. In addition, I gained a better understanding of the nature of work and
workplace problems.

4.6

References
1. MIRALL STAFF
2. HR. INSTAR
3. HR. NOOR
4. DIR. EOIN
5. ENG. KHULOOD
6. ENG. SALEM
7. DIR. HEND
8. ENG. RIJU
9. MIRAL PRIVATE BOOK
10. https://miral.ae
11. Structure report
12. Desing report

22 | P a g e
THANK YOU LETTER

From:

Mariam Almemari
Abu Dhabi, AlSamha
Date: 26/Jun / 2022

To,

Hr. Intasr, Hr. Noor, Dir. Eoin, Dir. Hend, Eng. Khulood, Eng. Salem, Eng. Riju
Miral Company
Yas Island
Abu Dhabi

,Dear Miral company

I am writing this letter to extend my warm thanks to you for hosting my internship for a period of
two months. These two months have been a period of great learning and valuable experience for
me and I hope that I was also able to add some value to your company with my work.

Although I studied every aspect of Civil Engineering for my BCVET, working for you helped
me grasp the practical part of the subject. Applying my academic understanding of civil law has
improved because of our work together.

It has been a good opportunity for me to learn, and I will be able to use this knowledge to my
advantage in the future. And I hope I may land a job with a reputable company like Miral
Company.

The unique relationships I have developed with my team over the past few months will be
missed, as will the entire team. Reuniting with this fantastic company in the future would be
wonderful.

Thanking you.
Yours sincerely,
Mariam Almemari