Professional Documents
Culture Documents
2011TuinierTechno-economicevaluationofcryogenicCO2captureAcomparisonwithabsorptionandmembranetechnology
2011TuinierTechno-economicevaluationofcryogenicCO2captureAcomparisonwithabsorptionandmembranetechnology
net/publication/251704370
CITATIONS READS
139 1,447
3 authors, including:
SEE PROFILE
All content following this page was uploaded by M. Van Sint Annaland on 02 March 2021.
a r t i c l e i n f o a b s t r a c t
Article history: A techno-economic evaluation of a novel cryogenic post-combustion CO2 capture technology is presented
Received 8 November 2010 in this work. The process concept is based on the periodic operation of cryogenically cooled packed beds.
Received in revised form 27 August 2011 A process cycle consists of three consecutive steps: a cooling, capture and recovery step. The bed is first
Accepted 29 August 2011
cooled down to temperatures below −120 ◦ C during the cooling step, possibly using cold energy released
Available online 29 September 2011
during the evaporation of LNG. Flue gas is fed to the refrigerated packed bed during the capture step. The
flue gas will be cooled down and components as H2 O and CO2 will condense and desublimate respectively
Keywords:
at the packing surface, while permanent gases such as N2 will pass through the bed without undergoing
Post-combustion CO2
Capture
any phase change. In a final recovery step the stored components will be recovered from the bed by
Cryogenic recycling CO2 for CO2 recovery and air for H2 O recovery. A basic process design focusing on the CO2 /N2
Techno-economic evaluation separation for a 600 MW coal fired power plant is given in this work and the CO2 avoidance costs are
calculated. The influence of several process parameters is investigated, lower initial bed temperatures
and higher CO2 concentrations in the feed result in more efficient use of the bed volume. The pressure
drop over the system plays an important role in the process economics, due to the high flow rates required
in the process. The cryogenic concept is compared to two competing technologies: amine absorption and
membrane separation. The results show that the preferred technology highly depends on assumptions
related to the availability of utilities.
© 2011 Elsevier Ltd. All rights reserved.
1. Introduction dependent on the scale and the CO2 concentration in the flue gas.
Merkel et al. (2010) evaluated a process based on CO2 capture using
In the transition from fossil fuels to sustainable energy, CO2 cap- membranes and calculated CO2 capture costs of $39/ton CO2 . In a
ture and storage (CCS) could be necessary in order to reach CO2 report by McKinsey & Company (2008) the development of costs
emission reduction targets. From the available methods of CO2 cap- for CCS (including storage costs) is analyzed over the next twenty
ture, post-combustion is the only method that can be retrofitted years. They expect that early demonstration projects will operate
to existing plants. Amine scrubbing is the most studied technol- at 60–90 D/ton, but that costs could come down to 30–45 D/ton in
ogy; other technologies of particular interest are membranes and 2030, a price level, which is expected to make CCS economically
adsorption. Several economic studies of CO2 capture methods have self-sustaining.
been published in literature. Resulting costs vary strongly, as they More research is required to bring down the costs. Although
are highly influenced by the system boundaries such as the CO2 many studies focus on reducing operational costs, e.g. by finding
source and therefore inlet concentration, whether or not transport novel more efficient solvents for amine scrubbing, it is at least
and storage is included, the level of maturity and cost measures as important to reduce the capital costs in order to reduce CO2
and assumptions. For example, the optimized costs in a study by avoidance costs (Schach et al., 2010).
Abu-Zahra et al. (2007) to CO2 capture by 30% MEA absorption Cryogenic CO2 capture is not included in most (economical)
from a 600 MW bituminous coal-fired power plant have been esti- comparison studies, as it has been considered as an unrealistic can-
mated at 33 D/ton CO2 avoided. On the other hand, in a study didate for post-combustion CO2 capture. In the first place due to
by van Straelen et al. (2010) to CO2 capture from a refinery also expected high cooling costs, but also because it has been consid-
using 30% MEA, costs of 90–120 D/ton CO2 avoided were reported, ered as a gas–liquid separation (Ebner and Ritter, 2009). In order to
be able to carry out the CO2 removal from flue gases as a gas–liquid
separation, it is necessary to compress the gas to pressures above
∗ Corresponding author. Tel.: +31 40 247 2241; fax: +31 40 247 5833. the triple point of CO2 , which is at 5.2 bar and −56.6 ◦ C for pure CO2 .
E-mail address: m.v.sintannaland@tue.nl (M. van Sint Annaland). Compressing flue gases to these pressures is too energy intensive.
1750-5836/$ – see front matter © 2011 Elsevier Ltd. All rights reserved.
doi:10.1016/j.ijggc.2011.08.013
1560 M.J. Tuinier et al. / International Journal of Greenhouse Gas Control 5 (2011) 1559–1565
An alternative is to cool flue gases to temperatures below the sub- 3. Process evaluation
limation temperature of CO2 at atmospheric pressures, resulting in
CO2 crystal formation, which cannot be easily handled in standard In order to be able to compare our technology with other tech-
process equipment. nologies, a basic design was made for a capture plant treating flue
In our previous work a novel cryogenic capture technology gas typically generated by a 600 MW coal fired power plant, which
based on the dynamic operation of packed beds was demonstrated is often used as a base case in literature studies. The capital and
which is able to capture CO2 at atmospheric pressures (Tuinier operation costs are then estimated and the costs per ton of CO2
et al., 2010, 2011). The aim of the work described in this paper avoided are calculated. This section ends with a parameter study,
is to evaluate this novel process, both on technical aspects and in which the influence of several key parameters on the capture
on economic performance. Furthermore, we will compare the eco- costs is evaluated.
nomics of our technology to other post-combustion technologies,
viz. amine scrubbing and membrane technology, investigating the 3.1. Base case
importance of various process assumptions.
The paper is organized as follows: first our cryogenic process To simplify the comparison, only CO2 capture is taken into
concept is outlined, followed by the description of a base case and account without impurities and H2 O removal. The assumed flue
a calculation of the costs per ton of CO2 emissions avoided. Sub- gas conditions and composition are shown in Table 2. The bed
sequently, a sensitivity analysis of some key process parameters is dimensions and properties for the base case are shown in Table 3.
M.J. Tuinier et al. / International Journal of Greenhouse Gas Control 5 (2011) 1559–1565 1561
Fig. 1. Schematic illustration of the process concept: (a) and (b) during the capture step, (c) and (d) during the recovery step.
The initial bed temperature was set at −150 ◦ C, which results in the recovery step to evaporate previously deposited CO2 . Further-
more than 99.9% CO2 recovery. A breakthrough time (duration of more, it can be observed that during the cooling step not the entire
each step) of 600 s was chosen. The required flow rates, pressures bed has to be cooled down, as the last part of the bed will be cooled
and inlet temperatures are shown in Table 4. The resulting pressure down during the capture step.
drops over the beds (also shown in Table 4) are rather small due to
the nature of the selected packing; a structured monolith. However, 3.2. Costs base case
gas distribution over the beds, piping and valves will cause an addi-
tional pressure drop, therefore a total pressure drop of 100 mbar In order to calculate the CO2 avoidance costs, the capital invest-
is assumed for the capture step and 200 mbar for the cooling and ment costs are first calculated using a conceptual cost estimation
recovery step. During the recovery step, the outgoing CO2 flow has method with an accuracy of 40%. In this method, the main equip-
a temperature of −78 ◦ C and will be partly recycled to the inlet. Due ment costs are estimated. Fig. 3 shows a simplified process scheme
to compression by the recycle blower the inlet temperature during with all main equipment. The costs for blowers, the heat exchanger
the recovery step is therefore −66 ◦ C. The flue gas temperature is and the columns are calculated using correlations reported by
estimated at 150 ◦ C, but will increase in temperature to 162 ◦ C, also Seider et al. (2004) and Loh and Jennifer Lyons (2002) and were
because of compression. The resulting axial temperature and mass updated to costs in 2010 using the Chemical Engineering Plant Cost
deposition profiles are shown in Fig. 2. It can be observed that the Index (CEPCI). The packing costs are calculated using a steel price
heat stored in the bed during the capture step is being used during of $1200/ton steel (market price of $600/ton multiplied with factor
Fig. 2. Simulated axial temperature (a–c) and mass deposition (d–f) profiles for the capture, recovery and cooling step for the base case. Operating conditions and bed
properties can be found in Tables 2–4.
1562 M.J. Tuinier et al. / International Journal of Greenhouse Gas Control 5 (2011) 1559–1565
Table 1 Table 3
Model equations for the 1-D pseudo homogeneous model. Bed dimensions and properties.
Component mass balances for the gas phase: Diameter [m] 8.5
nc
Length [m] 4.25
∂ωi,g ∂ωi,g ∂ ∂ωi,g
εg g = −g vg + g Deff − ṁi as + ωi,g ṁi as Number of beds [–] 21 (7 per step)
∂t ∂z ∂z ∂z Packing Steel monolith structure
i=1
Component mass balance for the solid phase: Density solids [kg/m3 ] 7750
∂mi Porosity [–] 0.697
= ṁi as
∂t
Total continuity equation for the gas phase:
∂ (εg g ) ∂ (g vg )
nc
=− − ṁi as Table 4
∂t ∂z Process parameters base case.
i=1
Energy balance (gas and solid phase): Capture Recovery Cooling
nc
∂T ∂T ∂ ∂T Tin [◦ C] 162 −66 −150
(εg g Cp,g + s (1 − εg )Cp,s ) = −g vg Cp,g + eff − ṁi as hi
∂t ∂z ∂z ∂z Pin [mbar] 1100 1200 1200
i=1 Flow/bed [kg/s] 91 564 357
Pressure drop over packing:
P packing [mbar] 8.7 44.2 30.1
∂p f 1 14.9 dh,c Total P [mbar] 100 200 200
= −4 g v2g with: f = 1 + 0.0445Re
∂z dh,c 2 Re L
Table 5
two for packing construction). The module costs, including piping, Capital investment costs for the base case.
installation, etc. are then calculated by multiplying the equipment
costs with a Hand factor. When all the module costs are summed Equipment Equipment Hand Module
costs [M$] factor costs [M$]
up, 25% is added for contingencies. The total direct investment is
subsequently calculated and an allocated investment (for storage, Columns for packed bed (21) 0.39 4 32.9
Packing (21) 0.67 4 56.5
utilities and environmental provisions), start up investments and
Flue gas compressor 1.12 2.5 2.8
working capital are added. Finally, the total fixed capital is calcu- CO2 recycle blower 10.09 2.5 25.2
lated, results are shown in Table 5. The operational costs consist N2 cooling blower 10.55 2.5 26.4
of the electricity costs required for the blowers. The CO2 emitted CO2 product compressor 15.09 2.5 37.7
LNG heat exchanger 1.03 4.8 4.9
Contingencies 25% 46.6
Table 2
Total direct investment (TDI) 233
Flue gas conditions and composition.
Total allocated investment 40% of TDI 93
Temperature [◦ C] 150 Start up investment 5% of TDI 12
Pressure [bar] 1.013 Total process investment (TPI) 338
vol.% Flow [kg/s] Working capital 2% of TPI 7
Total 635
M.J. Tuinier et al. / International Journal of Greenhouse Gas Control 5 (2011) 1559–1565 1563
Table 6
Cost evaluation parameters.
Table 7
Operational and total costs for the base case.
Table 8
Capital investment costs for amine scrubbing and membrane technology.
Amine scrubbing
Membranes
maldistribution which is still acceptable is unknown and requires
Equipment Module costs [M$]
more study. To indicate the significance of the pressure drop on Membranes 150
the process performance and economics, two cases with 50% higher Compressors/expanders 100
and lower pressure drops were evaluated. Fig. 6 shows a significant Installation factor (60%) 150
effect on the operational costs, which is explained by higher com- Contingencies 100
pression costs. Also the amount of required LNG changes slightly, Total direct investment 500
which is related to the heat generated by compression. It should Total allocated investment 200
Start up investment 25
be noted that some CO2 bypass might be tolerated, since often 90%
capture is deemed sufficient. Total process investment 725
Working capital 15
4. Comparison with absorption and membrane technology Total fixed capital 740
second option an air sweep is used, which is then fed to the boiler of Total power costs 11.3 36.0
the power plant. Although the second alternative is more efficient Capital charge (20% total fixed capital/year) 33.2 84.9
and looks promising, it will not be taken into account in this study,
Total costs 54.5 120.9
as it will influence the combustion process and might be more
M.J. Tuinier et al. / International Journal of Greenhouse Gas Control 5 (2011) 1559–1565 1565
5. Conclusions