Professional Documents
Culture Documents
Transformer basic to transformer modelling in ETAP
Transformer basic to transformer modelling in ETAP
Transformer basic to transformer modelling in ETAP
What is Transformer?
A static piece of apparatus with two or more windings which, by electromagnetic induction,
transforms a system of alternating voltage and current into another system of voltage and
current usually of different values at the same frequency for the purpose of the transmitting
electrical power.
146
Applications of Transformer:
Transformer is used to suppress few harmonics ( Balanced 3rd order and multiple of 3rd
order Harmonics)
Unit ratio or Lightning transformer is used to limit the short circuit current
Cathodic protection
147
Standards used for transformer (Load flow study):
TRANSFORMER
IEC 60076 (PART -12) LOADING GUIDE FOR DRY TYPE TRANSFORMER
Equivalent Circuit diagram for the ideal transformer:
ETAP is not modelled of no load losses during no load condition but modelled of load losses
148
Im – Magnetising current to create the losses in the transformer
1) Liquid Immersed
2) Dry Type
1) AIR NATURAL
2) AIR FORCED
149
ETAP ( TRANSFORMER COOLING TYPE OPTIONS):
Sub Type
150
Class and the Temp. Rise (65 degree)
151
Liquid Imerssed Transformer:
Liquid – cooled (oil – filled) transformers use oil as the cooling and insulating medium. They
are commonly used in high – voltage power transmission and distribution systems, as well as
in industrial and commercial applications, where a high power rating and increased efficiency
is required. So, not all transformers are oil filled. The choice of cooling medium depends on
152
Oil filled transformers are generally more efficient and have a higher power density than the
dry type transformers. They are commonly used in the high voltage power transmission and
Dry type transformers are simpler and safer, as they do not contain the flammable oil. They
are typically used in low voltage and medium voltage applications. Where the risk of fire is
minimal and where the required power rating is lower. They are also easier and less expensive
153
TRANSFORMER MODELLING IN ETAP SOFTWARE:
154
In the above picture shows that the two winding transformer editor by click the two winding
155
In the above picture shows that rating option of the transformer editor. Enter the primary and
secondary voltages in KV and also enter the rated MVA for the transformer. Choose the
Altitude and Ambient temperature so thus the ETAP will calculated the derated % and derated
MVA value. Choose the type of transformer, subtype, class from the transformer nameplate.
156
Altitude 1400 m and Ambient temperature is 30 degree; Derated MVA is 4.612 MVA and the
derated % is 7.8%
157
.Altitude is 1000m and Ambient temperature is 31 degree. Derated MVA is 4.95MVA and the
derated % is (1%).
158
Altitude is 1200m, Ambient temperature is 31 degree. Derated MVA is 4.754 and the derated
% is (4.9%).
159
Derated MVA and percentage is calculated by Excel sheeth: (Altitude derating)
160
161
In the below picture shows that; transformer impedance value has to be set by click the typical
Z and X/R ratio, orelse to find out the X/R ratio by manual calculation when the transformer
162
Transformer rating, load losses and impedance % is given in the transformer nameplate. To
Formula:
X = (Sqrt(Z^2) –( R^2))
163
Transformer tap changer:
A tap changer is a mechanism in transformers which allows for variable turn ratios to be
selected in distinct steps. This is done by connecting to a number of access points known as
taps along either the primary or secondary winding. Tap changing occurs when there is any
164
Steps = ( 11275 – 11000 ) = 2.5%
165
De energisation tap changer: Grid voltage fluctuates at 105%
166
In the above picture shows that there is 105% grid voltage fluctuates so the receiving end
In the above figure shows that to change the voltage percentage as 100% to 105% in the
loading and generation category and also in the power grid editor in the rating option.
167
The below figure shows that transformer tap change as 0% to 5% at 11.55KV to regulate the
168
ETAP RESULTS AFTER TAP CHANGE
169
De energisation tap changer: Grid voltage fluctuates at 103%
170
171
In the above two pictures shows that grid voltage fluctuates at 103% but the tap at 0% of 11
The above figure shows that to change the grid voltage in the power grid editor in rating as
100 to 103%
172
The below figure shows that to set the grid voltage in the rating as 103% in the loading and
generation category.
173
ETAP RESULTS AFTER TAP CHANGE:
174
In the above two figure shows that transformer tap is changes from 0 to 2.5% at 11.33KV to
175
Grid voltage fluctuates at 98%
176
Taping at 0% as 11KV but the grid voltage fluctuates at 98% so thus the receiving end voltage
is also decreases.
177
Tap change from 0% to -2.5% at 10.725KV so thus the receiving end voltage is changes from
178
Grid voltage fluctuates to 95%
179
Grid voltage fluctuates to 95%
180
Grid voltage fluctuiates at 95% but the tappings at 0& of 11KV. Receiving end voltage is
decreases
181
Tapping is change from 0% to -5% at 10.45KV. The receiving end voltage is changes from
182
On Load Tap Changing Transformer:
To click the secondary LTC AVR to regulate the bus voltages at the receiving end when the
voltage fluctuation takes place at the grid voltage. So thus the tap changes takes place at the
higher voltage side as primary winding when the voltage fluctuation taakes place.
183
Voltage control is set to as 100% at the receiving end to automatically control the voltages
184
11 KV at 0% tapping and receiving end voltage is nearly to 100%
185
105% Grid voltage fluctuation : AVR Voltage control as 100% receiving end voltage
186
95% Grid voltage fluctuation : AVR Voltage control as 100% receiving end voltage
187
98% Grid voltage fluctuation : AVR Voltage control as 100% receiving end voltage
Important Note: Tranaformer tap changer takes place only in the high voltage winding side
because of when tap changer takes place in the transformer thus current sparks takes place.
188
Grounding option:
189
TRANSFORMER PARALLELING
Its significance is that when one transformer fails, other transformers running in parallel can
190
Vector group are same in both the transformer
191
Change the vector group in the grounding; other details are same in both the transformer;
192
193
Apply transformer phase shift is essential:
194
INPUT PARAMETERS TO THE TRANSFORMER: (LOAD FLOW STUDY)
Rated MVA
Transformer Impedance %
Category of tapping
195