Professional Documents
Culture Documents
Diversion Headworks (Lecture Slides) (1)
Diversion Headworks (Lecture Slides) (1)
5.Diversion Headworks
The works, which are constructed at the head of the canal, in order to divert the river water towards the canal, so
as to ensure a regulated continuous supply of silt-free water with a certain minimum head into the canal, are
known as Diversion Head Works.
Weir and Barrage : If the major part or the entire ponding of water on the upstream side of the obstruction is
achieved by a raised crest and a smaller part of it is achieved by the shutters, then this barrier is known as a weir
.On the other hand, if most of the ponding is done by gates and a smaller part of it is done by the raised crest,
then the barrier is known as a Barrage.
If most of the ponding or the entire ponding is done by a permanent raised crest, as in a weir, then the afflux
caused during high floods is quite high. On the other hand, if most of the ponding is done by gates, as in a
barrage, then the gates can be opened during high floods and the afflux (i.e. rise in HFL near the site) will be nil
or minimum. Hence, a barrage, gives less afflux and a better control upon the river flow, because the inflow and
outflow can be controlled to a much greater extent by suitable manipulations of its gates.
5.1 Component parts of Weir/Barrage : A diversion headwork ( or weir) usually consists of the following components.
(1)Weir ( or barrage) proper
(2) Under sluice
(3) Divide wall
(4) Fish ladder
(5) Canal head regulator
(6) Silt excluder, silt ejector
(7) River training works: guide banks, marginal bunds
(i) Masonry weirs with vertical drop: A typical cross-section of such a weir is shown in Figure . This type of a weir.
consists of a horizontal floor and a masonry crest with vertical or nearly vertical downstream face .The raised masonry
crest does the maximum ponding of water, but a part of it, is usually, done by shutters at the top of the crest. The shutters
can be dropped down during floods, so as to reduce the afflux by increasing the waterway opening. This type of weir was
used in all the old head-works and is particularly suitable for hard clay and consolidated gravel foundations. However,
this type of weir is becoming obsolete and even the old constructions are being replaced by the new modern concrete.
(ii) Rock-fill weirs with sloping aprons : Such a weir is also called - 'Dry Stone Slope Weir'. A typical cross-section of
such a weir is shown in Fig. It is the simplest type of construction, and is suitable for fine sandy foundations like those in
alluvial areas. Such a weir requires huge quantities of stone and is economical only when stone is easily available.
However, with the development of concrete glacis weirs, this type of weirs is also becoming obsolete.
(iii) Concrete weirs with sloping glacis: Weirs of this type are of recent origin and their design is based on modern
concepts of sub-surface flow (ie.Khosla's Theory). A typical cross-section of such a weir is shown in Figure below. Sheet
piles of sufficient depths are driven at the ends of upstream and downstream floor. Sometimes, an inter-mediate pile line
is also provided. The hydraulic jump is formed on the downstream sloping glacis , so as to dissipate the energy of
flowing water.
(2) Under sluice : A comparatively less turbulent pocket of water is created near the canal head regulator by constructing
under-sluice portion of the weir. A divide wall separates the main weir portion from the under since partition of the weir. The
crest of the under sluice portion of the weir is kept at a lower level than the crest of the normal portion of the weir. Normally,
the crest level of the under-sluices is kept equal to the deepest bed level of the river during non-monsoon season; whereas, the
crest level of the weir" is kept higher by about 1 to 1.5 m.
As the crest of the under-sluice pocket is at a low level, a deep channel develops towards this pocket, which helps in bringing
low dry weather discharge towards this pocket, thereby, ensuring easy diversion of water into the canal through the canal head
regulator. They should be able to dispose of 10 to 15% of the high flood discharge during severe floods.
The crest level of the canal head regulator is also kept higher than the crest level of the under-sluices, so that only silt free water
is admitted into the canal through the head sluices. Silt gets deposited over the under-sluice floor, and may be periodically
removed over the crest of the under-sluices and towards the downstream side of the river by opening these gate-controlled
openings (under-sluices).
(3) Divide wall : The ‘divide wall' is a masonry or a concrete wall constructed at right angle to the axis of the weir, and
separates the 'weir proper' from the under-sluices’ .The divide wall extends on the upstream side beyond the beginning
of the canal head regulator, and on the downstream side, it extends up to the end of loose protection of the under-sluices
. The top width of divide wall is about 1.5 to 2.5 meters. These walls are founded on wells closely spaced beyond the
pucca floor upto the end. The wells are taken well below the deepest possible scour. Typical cross-section of the divide
wall on pucca floor and beyond the pucca floor are shown in Figure below.
The main functions served by the divide wall are:
(a) It separates the 'under-sluices' from the 'weir proper'. Since the crest level of the under-sluices is lower than that of
the weir proper, the two must be separated, and this is being done by the Divide wall,
(b) It helps in providing a comparatively less turbulent pocket near the canal head regulator, resulting in deposition of
silt in this pocket and, thus, to help in the entry of silt-free water into the canal.
(c) Divide wall may keep the cross-currents, if at all they are formed, away from the weir. Cross-currents lead to
vortices and deep scours, and therefore, prove hazardous to weirs.
(4) Fish ladder : A structure which enables the fish to pass upstream is called a 'fish ladder’. It is a device by which
the flow energy can be dissipated in such a manner as to provide smooth flow at sufficiently low velocity, not
exceeding 3 to 3.5 m/sec. This object is generally accomplished by providing a narrow opening adjacent to the divide
wall and provide suitable baffles or staggering device in it, so as to control the flow velocity.
(5) Canal head regulator : A canal head regulator is provided at the head of the off-taking canal, and serves the
following functions :
(i) It regulates the supply of water entering the canal.
(ii) It controls the entry of silt in the canal.
(iii) It prevents the river floods from entering the canal .
A typical cross-section of a head regulator is shown in Figure. The regulator is generally aligned at right angle to the
weir, but slightly larger angles (between 90° to 110) are now considered preferable for providing smooth entry of water
into the regulator.
Figure : Typical section through a Canal Head Regulator(C.H.R). Figure: Alignment of a Canal Head Regulator.
The water from the under-sluice pocket is made to enter the regulator bays, so as to pass the full supply discharge into
the canal. The maximum height of these gated openings, called head sluices will be equal to the difference of Pond
Level and Crest Level of the regulator . The entry of silt into the canal is controlled by keeping the crest of the head
regulator by about 1.2 to 1.5 metres higher than the crest of the under-sluices. If a Silt-Excluder is provided, the
regulator crest is further raised by about 0.6 to 0.7m .
(6) Silt excluder, silt ejector : The entry of silt into a canal, which takes off from a Head-Works, can be reduced by
constructing certain special works, called silt control works. These works may be classified into the following two
types:
(a) Silt Excluders: Silt excluders are those works which are constructed on the bed of the river, upstream of the head
regulator. The clearer water enters the head regulator and the silted water enters the silt excluder. In this type of
works, the silt is, therefore, removed from the water before it enters the canal.
(b) Silt Ejectors: Silt ejectors, also called silt extractors, are those devices which extract the silt from the canal-water
after the silted water has travelled a certain distance in the off-take canal. These works are, therefore, constructed on the
bed of the canal, and a little distance downstream from the head regulator.
Figure(a): Plan and Section of Silt Excluder Figure(b) : Plan and Section of Silt Ejector
(7) River training works (guide banks, marginal bunds): River training works are required near the weir site in
order to ensure a smooth and an axial flow of water, and thus, to prevent the river from outflanking the works due to a
change in its course. The river training works required on a canal headworks, are:
(i) Guide banks;
(ii) Marginal bunds ; and
(iii) Spurs or groynes.
The guide banks force the river into a restricted channel, and thus, ensuring a smooth and an almost axial flow near the
weir site
Marginal bunds are provided on the upstream side of the works in order to the area from submergence due to rise in
HFL, caused by the afflux. These bunds are, therefore, continued till they join contours higher than the new HFL.
Marginal bunds are nothing but earthen embankments, protected by groynes , wherever needed. They are designed on
the principles of design of earthen dams or dikes.
Figure(a) : Guide Banks(Plan) Figure(b): Guide Banks(Sections) Figure(c) : Marginal bunds(Section) Figure(d) : Spurs or Groynes
Photo view of Barrage (Bagmati Irrigation project)
Fig(b): Eastern side canal head regulator Fig(c):Undersluice Fig(d) Western side canal head regulator
(ii) Safety against uplift pressure: The ordinates of the H.G. line above the bottom of the floor represent the residual
uplift water head at each point. Say for example , if at any point, the ordinate of H.G. line above the bottom of the floor
is 1 m, then 1 m head of water will act as uplift at that point. If h' metres is this ordinate, then water pressure equal to h'
metres will act at this point, and has to be counter balanced by the weight of the floor of thickness say t.
i.e, Uplift pressure = γw h' where γw is the unit wt. of water .
Downward pressure = (γw . G.) t where G is the specific gravity of the floor material.
For equilibrium γw . h' = γw . G. t
h' = G.t
Subtracting t on both sides, we get
(h' - t)= (G.t-t) =t(G-1)
or, t=(h' -t)/(G-1) ------(a) where (h' -t) = h is the ordinate of the H.G. line above the top of the floor. (G-1) is
the submerged specific gravity of the floor material. Hence, the thickness of the floor can be easily determined by
using the above equation (a).This is generally increased by 33%, so as to allow a suitable factor of safety.
Lane's Weighted Creep Theory :Lane, on the basis of his analysis carried out on about 200 dams all over the world,
specified that the horizontal creep is less effective in reducing uplift than the vertical creep. He, therefore , suggested a
weightage factor of 1/3 for the horizontal creep, as against 1.0 for the vertical creep.
Thus in Fig. 11.1, the total Lane's creep length (L) is given by
To ensure safety against piping, according to this theory, the creep length Ll must not be less than C1HL, where HL is the
head causing flow, and C1 is Lane's creep coefficient given in table 11.2.
Lane's theory was an improvement over Bligh's theory, but however, was purely empirical without any rational basis, and
hence, is generally not adopted in any designs. Bligh's theory, though is still used (even after the invention of modern
Khosla's theory), but Lane's theory is practically nowhere used, and is having only a theoretical importance.
Example-1: Fig. below shows the section of a hydraulic structure founded on sand. Calculate the average
hydraulic gradient. Also, find the uplift pressures at prints 6,12 and 18 m from the u/s end of the floor and find
the thickness of the floor at these points taking ϼ=2.24.
Khosla's Theory and Concept of Flow Nets: Many of the important hydraulic structures, such as weirs and
barrages, were designed on the basis of Bligh's theory between the period 1910 to 1925. In 1926-27 the upper Chenab
canal syphons, designed on Bligh's theory, started posing undermining troubles. Investigations started, which
ultimately lead to Khosla's theory. The main principles of this theory are summarised below:
(1) The seeping water does not creep along the bottom contour of pucca floor as stated by Bligh, but on the other
hand, this water moves along a set of stream-lines as shown in Fig. 11.3. This steady seepage in a vertical plane for a
homogeneous soil can be expressed by Laplacian equation.
(3) Undermining of the floor starts from the downstream end of the d/s pucca floor, and if not checked, it travels
upstream towards the weir wall. The undermining starts only when the exit gradient is unsafe for the subsoil on
which the weir is founded. It is therefore, absolutely necessary to have a reasonably deep vertical cut-off at the
downstream end of the d/s pucca floor to prevent undermining. The depth of this d/s vertical cut off is governed by
two considerations i.e.
(i) maximum depth of scour ; (ii) safe exit gradient.
While designing a weir, downstream cutoff from the maximum scoured depth considerations is, first of all,
provided, and checked for exit gradient. If a safe value of exit gradient is not obtained, then the depth of cutoff is
increased.
Khosla's method of independent variables for determination of pressures and exit gradient for seepage below
a weir or a barrage : For designing hydraulic structures such as weirs or barrages on pervious foundations, Khosla
has evolved a simple, quick and an accurate approach, called Method of Independent Variables. Mathematical
solutions of flownets for these simple standard profiles have been presented in the form of equations given in Fig.
11.5. and curves given in Plate 11.1, which can be used for determining the percentage pressures at the various key
points. The simple profiles which are most useful are :
(i) A straight horizontal floor of negligible thickness with a sheet pile line on the u/s end and d/s end [Fig. 11.5 (a)
and (b)].
(ii) A straight horizontal floor depressed below the bed but without any vertical cut-offs [Fig. 11.5 (C)].
(iii) A straight horizontal floor of negligible thickness with a sheet pile line at some intermediate point [Fig. 11.5 (d)).
The key points are the junctions of the floor and the pile lines on either side, and the bottom point of the pile line, and
the bottom corners in the case of a depressed floor. The percentage pressures at these key points for the simple forms
into which the complex profile has been broken is valid for the complex profile itself, if corrected for
(a) correction for the mutual interference of piles ;(b) correction for thickness of floor ;(c) correction for the slope of
the floor.
The uplift pressures must be kept as low as possible consistent with the safety at the exilt, so as to keep the floor
thickness to the minimum.
It is obvious from equation (11.4), that if d=0; GE is infinite. Hence, it becomes essential that a vertical cutoff at
the downstream end must be provided
Khosla’s Curves
Example-1: Determine the percentage pressures at various key points in Fig. 11.8. Also determine the exit gradient and
plot the hydraulic gradient line for pond level on u/s and no flow on d/s.
5.3 Design of sloping glacies weir bay (crest,length & thickness of impervious floor)
Sloping glacis weir is a weir of later origin consisting of upstream glacis of slope varying from 1:1 to 2:1 (ii) flat
crest of 2 to 3 m width with falling shutters, (iii) down stream glacis of slope varying from 3:1 to 5:1 and (iv)
horizontal apron or cistern of adequate length, along with cut off, block protection, inverted filter and launching
aprons, as shown in Figure below. The main advantage of a sloping glacis weir is that hydraulic jump is formed
on the d/s sloping glacis to dissipate the energy of overflowing water
Elements of hydraulic jump
Usually, in any hydraulic jump, the following eight variables are involved : Ef1 , V1, y1 , Ef2, V2, y2, q and HL.
These variables are related by six independent equations ,as given below :
Hence, if any two variables are known, the remaining six can be worked
out by using these six equations, mathematically. The mathematical solution
is complicated and to avoid large scale calculations, Blench has given some
curves by taking q and HL as known variables (as in actual problem, the
discharge intensity q and the drop in the total energy level HL are generally
known). Blench had given curves, relating HL and Ef, for different values of
q (Plate 10.1). These curves are very useful in determining the location of
the jump on a sloping glacis , as explained below.
Position of the Jump: Let water be passing over the crest of a work (such as a weir, etc.) with a certain head.
Then discharge per unit width = CdH3/2, where H is the head measured from the total energy line to the crest and
Cd is the coefficient of discharge. Knowing H, the level of u/s TEL is known. For the given discharge, the depth
of water on the d/s is known from gauge discharge curves of the channel. This fixes TEL on the d/s. The
difference in the levels of u/s TEL and d/s TEL gives HL. Knowing q and HL, Ef2 can be obtained from Blench
Curves (Plate 10.1). Subtracting Ef2 , from d/s TEL, the level at which the jump will form can be easily obtained
and hence the position of point P is fixed . Knowing Ef2 , Ef1 can also be calculated by using, Ef1 –Ef2 = HL .The
corresponding values of y1, and y2 for the known values of Ef1, and Ef2, can be directly read from the 'Energy of
Flow Curves' given by Montague (Plate 10.2).
The discharge formulas to be used in the design of a weir or a barrage are;
Step 3. Regime scour depth R=1.35 (q2/f)1/3 = 1.35 (102 /0.9) 1/3 = 6.5 m
Regime velocity = q/ R =10/ 6.5 = 1.54 m/sec.
Velocity head = V2/2g = (1.54)2/2 x 9.81 = 0.12 m.
Step 4. u/s H.F.L. =u/s T.E.L. - Velocity head = 256.25 – 0.12 = 256.13 m.
Level of d/s T.E.L = H.F.L before construction +( V2/2g )= 255.0 +0.12=255.12 m
Afflux = u/s H.F.L. - d/s H.F.L= 256.13 -255.0 =1.13 m
which is very near to the permissible afflux of 1 m.
The d/s H.F.L after retrogression = H.F.L. before construction - bed retrogression = 255.0 - 0.5 = 254.5 m.
d/s T.E.L. after retrogression = Level of d/s T.E.L - bed retrogression = 255.12 – 0.5 = 254.62 m
Loss of head at high flood is
Loss of head (HL) = u/s T.E.L - d/s T.E.L. after retrogression = 256.25 – 254.62 = 1.63 m.
Step 10. Calculations for floor thickness. After calculation of the pressure at various key points and drawing
the H.G. Lines and Plotting the prejump profile for the two flow conditions the Figure below shows the subsoil
H.G. line for the two conditions. The floor is to be designed for the maximum unbalanced head found by
subtracting elevation of water surface profile (or d/s bed level as the case may be) from the elevation of the
corresponding H.G. line.
At the point of formation of hydraulic jump for high flood condition:
Unbalanced head for high flood condition (from Figure below) = 4.0 m
Unbalanced static head for no flow condition =2.56 m
Design head = 4 m
Since the design head is greater for high flood condition, the floor is designed for 2/3rd of this head
=2/3 x4= 2.67 m.
Thickness = h/(G-1) =2.67 /(2.24 – 1) = 2.15 m.
(ii) At the point of formation of hydraulic jump for flow at pond level condition :
Unbalanced head for pond level condition = 2.9 m
2/3 of this head =1.93 m
Unbalanced static head for no flow condition =2.2 m
Design head = 2.2 m
Thickness = h/(G-1) =2.2 /(2.24 – 1) = 1.8 m.
Fig;(a)
(2) An impervious floor of a weir on permeable soil is 16 m long and has sheet piles at both the ends. The
upstream pile is 4 m deep and the downstream pile is 5 m deep. The weir creates a net head of 2.5 m. Neglecting
the thickness of the weir floor, calculate the uplift pressures at the junction of the inner faces of the pile with the
weir floor, by using Khosla's theory.
(3) The concrete floor of a head regulator is level with the channel
bed (except for the short crest hump) and is 13 m long. The floor is
provided with cut off walls at its upstream and downstream ends. The
depth of upstream cutoff is 1.5 m (below the floor level) and that of
the downstream wall is 2.0 m. Using Khosla's theory [see Fig.(b) for
definition, sketch and formula], determine the thickness of the floor at
its mid length and also at its junction with the upstream and downstream
cutoff walls. The floor thickness may not be less than 30 cm anywhere. Fig(b)
The upstream FSL is 1.5 m above the floor level. If the permissible exit gradient is 0.18, is the floor safe against
failure by piping ?
(4) A barrage is to be constructed on a river having a high flood discharge of about 8,100 cumecs, with the given
data as follows: Average bed level of the river= 257.0 m ,High Flood Level (before construction of barrage) =
262.2 m ,Permissible afflux =1.0m ,Pond Level= 260.6 m
Design a suitable head regulator for the following data for the off-taking canal are also given :
Full supply discharge of canal=180 cumecs
Anticipated maximum full supply level of canal = 260.2 m
Bed level of canal= 257.2 m
Safe exit gradient for canal bed material = 1/5.