Professional Documents
Culture Documents
Work Method Statement for SITC&HO of complete FAPA System (2) (2)
Work Method Statement for SITC&HO of complete FAPA System (2) (2)
Work Method Statement for SITC&HO of complete FAPA System (2) (2)
Page 1 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
Page 2 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
INDEX
S. No. DESCRIPTION
1 PURPOSE
2 SCOPE
3 REFERENCES
4 ROLES & RESPONSIBIITY
5 SAFETY REQUIREMENTS
6 TOOLS & EQUIPMENTS
7 MATERIAL
7.1 Material Specification
7.2 Material Handling & storage
8 WORK PROCEDURE
13 ANNEXURES
Page 3 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
1. PURPOSE
The purpose of this method statement is to describe the procedure for installation of
FAS Panel at Godrej GCR, Gurugram project as per the requirements of the project
contract specification & relevant standards.
This method statement will ensure that all related activities are executed in compliance
of the project specification requirements, safety & Quality measures are implemented
throughout the progress of works.
2. SCOPE
This method statement covers the Supply, Installation, Testing Commissioning and
Handing Over of Complete FAPA System in accordance with the Technical
Specification and as per approved TDS without any deviation for complete project
wherever work has been specified as per drawings.
3. REFERENCES
• Project BOQ
• Project Technical Specifications
• Approved GFC & Shop Drawings
• Relevant codes and Standards
• Project Quality Plan
• Project EHS Plan and Risk assessment
SECTION • To ensure that the works are carried out according to the provisions of
IN- contract.
CHARGE • To ensure that all the equipment’s, tools, and tackles required to execute
the works according to approved construction Schedule are available in
good condition and provide any additional equipment that might be
required.
• To ensure all the equipment’s / vehicles are handled by skilled operators.
• To provide all necessary support to his execution team and ensure that
the works are carried out as per the approved Method
Statements/procedures.
Page 4 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
Page 5 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
5. SAFETY REQUIREMENTS
• Proper Access & Egress will be ensured before and till the completion of work. Work
areas will not be obstructed.
• Safety clearance (Permit to Work) to be obtained prior to commencement of works.
• Proper illumination to be maintained at work area during work as per illumination plan.
• All workmen will wear proper Personal Protective Equipment (PPEs) like safety
helmets, gumboots/safety shoes, reflective jackets etc. and also wear job specific PPEs
as per requirement.
• Safe procedure for unloading, shifting, stacking, transportation, erection should be
explained to crew before start of work
• Scaffolds will be properly erected and verified by the authorized scaffold inspector.
• Material handling will be done in proper manner and as per procedure.
• Inspection of all electrical equipment to be done.
• All safety control measures to implemented as per relevant HIRA.
• Workers will carefully operate the hand tools and machinery with proper care and
safety.
• Routine Inspection to be done by site engineer/supervisor to ensure working conditions
before commencing of works.
• Measuring Tape
• Water leveler
• Hammer
• Screwdriver
• Drill Machine
• Spanner
• Cutting Pliers
• Multimeter
• Bolt nuts and washer
• Ladders/Scaffolding
Page 6 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
7. MATERIALS
• All materials (FAS Panel & PA rack) will be as per BOQ, Project
Specification & approved TDS of the project.
• Material of approved make/manufacturer to be used.
Page 7 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
8. WORK PROCEDURE
• Site Supervisor will carry out a site survey and mark the point of Panel, as per approved
shop drawings. If there are any discrepancies or difficulties in executing the work, these
will be brought to the notice of Project Engineer for corrective action.
• Arrange necessary scaffolding as per the requirement.
• Make the termination of Power from Input of the Panel.
• Check for Voltage, Earthing and UPS supply.
• Check for Loop card connections.
• Check for Cables terminations inside the Panel
• Check for cable dressing inside Panel is properly done
• Check for Cable tagging
• Site Supervisor will carry out a site survey and mark the point of Rack, as per
approved drawings. If there are any discrepancies or difficulties in executing the
work,these will be brought to the notice of Project Engineer for corrective action
• Secure the chassis to the rack. Make sure that air can circulate freely Inside the
chassis for adequate ventilation. Do not cover or block the vent of Amplifier rack
• Install relay Module For zone controlling as per requirements
• Check for cable Termination in relay Module and Amplifier.
• Install the Amplifier inside the rack.
• Cable termination done inside rack in Amplifier.
• Check the cable tagging and Device Tagging.
Page 8 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
• All Installation work will be carried out under controlled supervision at all stages.
• All Inspection & testing will be as per approved Inspection Test plan.
• All material to be inspected by quality engineer and MIR (Material Inspection Request)
record for same will be maintained.
• All work to be carried out as per approved drawings.
• Regular process checks for the work to be done.
• All works shall be inspected for conformance to specification.
10 INSPECTION
• All Inspection & testing shall be as per approved Inspection Test plan.
• All record shall be maintained as per project specification.
11 TRAINING
Page 9 of 10
GODREJ GCR
MHPL Commercial Development, Gurugram
METHOD STATEMENT FOR SITC & HO OF
COMPLETE FAPA SYSTEM
Document No. GCR-GB-ELE-MST-0005
12 HOUSEKEEPING
• Anticipated Risk & Control Measures to execute the activity shall be as per: EHS Risk
Assessment Matrix (refer attachment).
14 ANNEXURES
Page 10 of 10