Professional Documents
Culture Documents
MSRA FF
MSRA FF
MSRA FF
AIRPORT
Prepared
QA/QC Engineer
Verified
Project Manager
Approved
Project Manager
Name Signature Date
Revision Log
Descriptio
Statu
Version Date n of
s
Review
Issued For
00
Approval
PAGE 1 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
Table of Contents
1 INTRODUCTION........................................................................................................................2
1.1 Purpose of the Document..................................................................................................2
1.2 Definitions..........................................................................................................................3
2 REFERENCE..............................................................................................................................3
3 SITE CLEARANCE AND PLANNING.............................................................................................3
4 TRAFFIC MANAGEMENT...........................................................................................................4
5 PRE-CONSTRUCTION SAFETY MEETINGS...................................................................................4
6 OPERATING PROCEDURE..........................................................................................................4
7 PROCEDURE.............................................................................................................................5
7.1 General Requirements.......................................................................................................5
7.2 SEQUENCE OF WORK.........................................................................................................5
8 EQUIPMENT’S / TOOLS...........................................................................................................10
9 MANPOWER..........................................................................................................................10
10 DETAILED CONSTRUCTION PROCEDURE WITH RESPONSIBILITY..............................................10
10.1 Project Manager..............................................................................................................11
10.2 Safety Officer...................................................................................................................11
10.3 Site Engineer....................................................................................................................11
10.4 Foremen...........................................................................................................................11
11 TRAINING / COMPETENCIES...................................................................................................12
12 HEALTH, SAFETY, WELFARE & ENVIRONMENT........................................................................12
12.1 Risk Assessment and Hazard Analysis..............................................................................12
12.2 Health Safety and Environment Induction Training.........................................................13
12.3 Pre-Task Briefings.............................................................................................................13
12.4 Toolbox Talk.....................................................................................................................13
12.5 Emergency Management.................................................................................................13
12.6 Protective & Safety Equipment........................................................................................14
13 QUALITY.................................................................................................................................14
14 ATTACHMENT........................................................................................................................14
PAGE 2 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
1 INTRODUCTION
1.1 Purpose of the Document
This method statement serves to outline the steps and actions that required for the Installation, pressure
testing and flushing of Sprinkler System and Fire Suppression System in the project as per the
Specifications and the approved shop drawings.
This activity should be performed with strict compliance and implementation of Safety Requirements &
executed in accordance with the contract requirements, hazards are analysed, safety procedures
implemented all quality assurance/control activities are conducted in a systematic manner, works
inspected and compiling with relevant specification, Legislation, Standard and Codes of Practice etc.
The execution statement explains the methodologies used for the implementation of various activities
and sub activities involved in this contract for a better and efficient performance in a professional
manner with high degree of quality and safety.
1.2 Definitions
MST - Method Statement
CL - Check List
RA - Risk Assessment
2 REFERENCE
Project specification
B.O.Q / finishes/Division
PAGE 3 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
Required levels are to be confirmed and verified by Site Surveyor and Site Engineer before
commencing the work
It is the responsibility of the Site Engineer to ensure that any preceding activity is completed
Refer to approved Baseline schedule for the duration of piping works will be followed
4 TRAFFIC MANAGEMENT
Other than some special cases no special traffic management plan is required
Special cases can be identified on individual bases and related actions can be taken accordingly
Safety awareness meetings will be conducted every working day morning/every other day to brief
the workforce in the safety prevention measures
The equipment check for safety shall be recorded/ documented during the daily Safety Awareness
Meeting. Traffic safety will be discussed to emphasise these meetings
Each worker will be instructed to follow specific safety requirements related to his trade
They will be required to follow installed safety signs, observe barricades and use opens
Contractor Safety will perform hazard risk analysis by identifying all steps, hazards identified in those
steps, with a focus on the relationship between the work task, the tools, and the work environment
After identifying uncontrolled hazards; Contractor will take steps to eliminate or reduce them to an
acceptable risk level
General contractual safety, health, and environmental requirements. Roles of the contractor,
subcontractors, authority representatives and all project workers
Specific details of the work to be performed along with the use of personal protective equipment
Emergency procedure
PAGE 4 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
6 OPERATING PROCEDURE
Site investigation has to be carried out to develop safety precautions and measures prior to the
commencement of the work
After such investigation, relevant sign boards will be displayed and barricades will be installed where
and as necessary, such as but not limited to the following: Advanced signs e.g. “Work Area” signs will
be placed the activity zones or fall hazard zone on around the area
After completion of the work, safety cones and barricades have to be removed accordingly
Site work shall be done as per the ongoing safety procedures being implemented on site
All throughout the duration of work, the required supervision shall be considered to ensure
completion of the activity in a safe and orderly manner
7 PROCEDURE
7.1 General Requirements
All necessary registers, method statement, risk assessment, health and safety plan etc will be kept
on site under the control of the Site Supervisor and can be inspected at any time. All accidents are to
be reported to and entered in the site accident book.
A supply of spare hard hats, overalls, gloves, goggles, masks, hand gloves, face visors (when burning
equipment is used) etc will be stored on Site.
At all times the appointed team will ensure a high standard of Health and Safety is carried out at all
times on site.
All operatives on site must wear full PPE in accordance with HSE requirements including safety
boots, hard hats and a high visibility vets or coat and LEP (Light Eye Protection) as standard.
Adequate segregation of pedestrians and vehicular traffic will be maintained at all times.
Existing facilities, which are within the construction site radius considered to obstruct any work
activities, will be removed, or be provided with protection against damage, dust and dirt.
PAGE 5 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
PAGE 6 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
Coupling installation
1. Groove the pipe ends according to the manufacturer’s specification, project specification and
consultant's approval
2. Pipe must be free from indentations, projections or roll marks on exterior from the ends to the
groove, to assure a leak tight seat for the gasket.
3. Place gasket over pipe ends, being sure gasket lip does not overhang pipe end
4. Align and bring 2 pipe ends together and slide gasket into position centred between the grooves on
each pipe .No portion of the gasket should extending to the groove on either pipe.
5. Loosely assemble all segments leaving one nut and bolt off to allow for "swing-over" feature.
6. With 1 nut and 1 bolt removed, use the “swing-over" feature to position housings over gasket and
into the grooves on both pipes.
7. Insert the remaining bolt to allow easy tightening of the nut .Be sure track head engages into
housing recess.
8. Tighten nuts alternately and equally maintaining metal-to-metal contact at the angle bolt pads.
9. Tighten securely to assure a rigid joint.
PAGE 7 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
6. Make sure that the locating collar is in the out let hole by rocking the upper housing in the hole.
7. Insert bolt in its hole and finger tighten both nuts .Be certain oval-neck of bolt engages recess in
housing. Make sure that the locating collar is in the outlet hole and the positioning lugs are properly
aligned.
8. Tighten bolt nuts uniformly until the upper housing is in complete surface contact in the gasket
pocket area and the assembly is rigid.
Testing of pipework
1. Installation of the pipe work shall be approved from the consultant prior to proceed with testing of
pipe work.
2. Valid calibration certificate shall be available for carrying out the pressure test.
3. Necessary safety permits shall be obtained from the concerned prior to start the pressure test.
4. Use ambient temperature water and clean water for testing purpose.
5. While filling system, use vents installed at high points of system to release air and use
drains installed at low points for complete draining of test liquid.
6. All piping are subjected to working pressure shall be hydrostatically tested @ 16 bar for 2 Hours.
7. After hydrostatic test pressure has been applied for at least 10mins, examine piping, joints, and
connections for leakage.
8. In case of leakage: Eliminate leaks by tightening, repairing, or replacing components and repeat
hydrostatic test until there are no leaks.
PAGE 8 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
9. Inspection shall be offered to Consultant/Engineer to witness and approve the pressure testing along
with test reports and valid calibration certificates.
10. Consider tolerance limit/Variance for the pressure test±5% of applied pressure.
11. On completion of successful pressure test, the water shall be drained through the drain provisions
provided at in pipe work to the designated drainage network/disposal areas
Sprinkler installation
1. All sprinklers will be installed according to the approved shop drawings and NFPA standards.
2. Check for the proper model, style, orifice size and temperature rating prior to installation.
3. Install sprinklers after the piping is in place to avoid mechanical damage, replace any damaged units
4. Special key wrenches must be used to provide proper leverage when tightening the sprinkler to
avoid slipping.
8 EQUIPMENT’S / TOOLS
Threading machine
Grooving machine
Hole saw cutter , chop saw cutter
Wrenches and spanners
General hand tools
9 MANPOWER
Project Manager
Site Engineer
Safety Officer
Foremen/Work Supervisor
Skilled and unskilled labours
PAGE 9 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
PAGE 10 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
10.4 Foremen
Ensure the works are progressed in the sequence as agreed with the Project Manager
Liaise with the Project Manager and Site Engineer for the allocation of the work force, ensuring
adequate manpower is available
Liaise with the Site Engineer to ensure all the required plant / materials are available to construct the
works
Full time supervision shall be required to ensure the works are carried out in accordance to
specifications, quality and approved drawings
11 TRAINING / COMPETENCIES
The Project Quality Team will ensure that proper quality trainings and workshops will be provided to the
project team continuously as per the training schedules approved by the Project Manager.
In addition to that, regular quality toolbox talks shall be delivered by project quality team to discuss and
elaborate the construction processes for each site activity. The training schedules and toolbox tools will
depend on the project stage and its current issues.
PAGE 11 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
Surface encumbrances
Falling loads - Materials falling onto people
Vehicular traffic - People being struck by plant
Undermining of nearby structures
Access/egress
Hazardous atmospheres
Accidents to members of the public
It is the responsibility of supervisors to make sure that those carrying out the work are instructed and
trained to do so using the control measures identified in the risk assessment. They should directly supervise
those with the least experience until they are deemed to be competent to carry out the work unsupervised.
Those carrying out the work must co-operate with their supervisor by following the instructions they have
been given.
PAGE 12 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
Toolbox talks will be recorded in traceable forms, which will include information on date, time, duration,
details of the topic, and signed attendance.
Hard Hat
Appropriate Eye protection
Safety boots
Safety gloves
High visibility Coveralls and/or Jacket
Ear protection if ambient sound exceeds 80dB
Dust mask
Sun protection
13 QUALITY
Drawings, MS and ITP shall be approved prior starting the work.
When the Foreman considers that the work is ready to be inspected, he informs the Site Engineer. The Site
Engineer then comes to control the works on site and reviews all the items mentioned in the Inspection and
Test Plan (ITP).
At this point, if the Site Engineer spots any deviation, he requests the production team to rectify the work.
As soon as he ensured that the work is satisfactory, he makes Inspection and Testing Request (ITR) including
the check sheets, drawings etc. and gives it to the QA/QC team. The ITR and check sheets shall be submitted
in advance, which will facilitate the Quality Team to inform the Engineer.
The Senior Quality personnel organizes its team and assigns the proper Inspector to carry out the inspection.
If necessary, the Senior Quality personnel highlights the sensitive points of the inspection to his subordinates
before inspection.
The inspection on site is implemented by the QA/QC Inspector together with Engineer’s Representative. At
the end of the inspection, the QA/QC inspector checks that all the persons concerned have signed the
Inspection Check List.
PAGE 13 OF 14
METHOD STATEMENT FOR INSTALLATION PRESSURE TESTING AND FLUSHING OF BASEMENT SPEINKLER PIPES
14 ATTACHMENT
Appendix A - Risk Assessment
PAGE 14 OF 14