Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Mechanical Department Weekly Work Planning(14 July to 18 July)

Sl No. Work Details Responsible Engineer Remarks

1. V-100 nozzle cutting completed except LG point


2. V-101 nozzle cutting completed except LG point
1 SWS plant structure & vessel-tower fabrication follow-up Arabinda & Sadman
3. V-102 welding ongoing

2 10000 BPD plant equipment(Vessel) modelling & PV Elite analysis 3 out of 11


3 Store Rack drawing finalization with supplier and technical communication follow up
4 LPG pump house to filling station pipe line fabrication work Follow-up
5 10000 BPD plant open drain-closed drain material procurement follow up
Sadman
6 Power House-2 generator erection & commissioning project planning & schedule update
7 New Power-house electrical support work (fabrication drawing updating).
8 Day tank diesel line routing layout drawing for approval
9 Tank farm area pipeline fabrication supervision and planning
10 10,000 BPD plant fabrication & installation schedule detailing as per manpower
11 10,000 BPD plant procurement(local & foreign) follow-up and technical communication
12 Other foreign procurement follow-up
13 10,000 BPD plant precurement master file updating
14 10,000 BPD plant 2D layout drawing for 1st floor and 2nd floor
15 Commercial 2D/3D layout revision as per their feedback to get duty benefit
16 C-7001 technical communication follow-up Keron
17 New hot oil heater technical communication with SBMC
18 10,000 BPD plant exchanger revised GA check and approval KK sheet approved, revised GA received last Thursday
19 10,000 BPD plant heater files check and feedback to Heatec Feedback sent, waiting for response
20 10,000 BPD plant pump feedback check and approve remaining pump GAs Sundyne Pump Items received last Friday(Sulzer completed)
21 Local CFU Diesel pump location confirmation with process department to procure new one
Process department support needed
22 Flare area pump permanent base and pit location confirmation with process department
23 10000 BPD plant equipment positon finalization in layout of Tower 03 out of 06
10000 BPD plant equipment modelling of Aerocooler
24 10000 BPD plant equipment modelling of Pump Arabinda
25 New LPG vessel Pipe line erection work follow up
28 Ship maintenance look after
29 10000 BPD plant structure and OD-CD fabrication follow-up Keron & Sadman
30 Rotating items stock checking Kaisar
31 Contractors bill checking Arabinda & Sadman
32 Padma Meghna, Jamuna pipline survey and drawing preparation Surveyor Zelan
33 Rotating work list
34 Work Details Man power
35 H-301 blower fan maintenance work Aziz 70% complete
36 Cooling tower pump inter-change( spx to deepblue) Waiting for manpower Waiting for manpower.
37 Reformer-2 oil h-2 compressor dismental for scraping Jashim, Puloq Start on Sunday
38 Agitator motor installation work Jashim Waiting for approval.
39 Mechanical items house kepping work. Bela, Mijan 30%
40 Flare pump ready work. 4set completed, 2set running Aziz 80%
41 Development work list Group Nos
42 SWS Vessel, Gusset Make, shell plate preparation, Saddle making
43 SWS Structure top bottom base plate cutting drilling, Gusset making
44 SWS Platform, railing making
45 SWS Ladder making 3
46 Old gate valve, fittings segregating for counting
47 Old Flare pipe line cutting and open
48 Old Flare Structure cutting and open 3
49 Flare fire water line making 1
50 Dyke-1 water flushing line, cooling line tie inn
51 Dyke -5 Fire, Foam line Fabrication & Fitting
52 Dyke -5 Beam Make for Tank Farm Pipe line Support fitting
4
53 Dyke-5 Tank 6" pipe line fabrication
54 Tank to tank Circulation line Fabrication as instructed
55 fire line around Dyke-5
56 New Exchanger Tube Bundle Make for RF-2 1
57 New Gate Make for Store and pocket gate, MCC Door Making 1
58 H-3001 to E-6015 Supply and return 6'' pipe line fabrication 2
59 RF-2 to CMX BT Tower 2" Line fabrication 1

You might also like