Superhouse Civil Projects

Industry
S.no Projects name Project Description Contractor name Work Progress Start Date End date Reason for delay Remark
Project close due to unavoidable
1 Safety Unit-2 Back side store RS Construction 50% 09-04-2024 08-Jul-24 circumstances
2 Modriba Project Service block Sitcon Infra Pvt Ltd 70% 20-03-2024 03-07-2024 No Architect Involve

Drawing not receive(Fire tank, OHT)


(after ravi sir), Architect not involve in
3 Modriba Project Phase-2 Work Sitcon Infra Pvt Ltd 5% 12-06-2024 30-09-2024 starting, now architect is involve
5 Safety garments Socks department(Renovation Work) RS Construction 15% 08-06-2024 25-07-2024
6 Fashion Footwear Office work Mera Baba Construction Drawing not finalize(Fire authority)
7 Shoe Div Project New building Tag Infotech 65% 29-04-2023 20-08-2024 Decision changing, by Client
8 Rooma Extension of building Tag Infotech 70% 01-01-2024 10-07-2024

Education
S.no Projects name Project Description Contractor name Work Progress Start Date End date Reason for delay Remark
1 Dps Kalyanpur New project(Hostel building) Sumit agarwal 01-06-2024 30-03-2025
Conference room Sumit agarwal 70% 30-06-2024
Conferece room toilet work Sumit agarwal 10% 31-07-2024
Record Room Extension Sumit agarwal 10% 05-07-2024

2 Koyal Enclave Classic construction 20% 15-12-2023 10-02-2025 Project delay due to NGT Struture work
3 Allen tower Abhuday construction 40% 15-05-2024 05-07-2024 fire staircase not decided yet
4 Allenhouse Rooma Abhyuday construction 25-07-2024 HT Line shifting issue Tentative date
Summer vacation work
Front area tile flooring, Room Extension Work,Patching & Ceiling
1 Allen Kids swaroop nagar ,False ceiling AK Construction 25% 07-06-2024 30-06-2024
Toilet Sunken Lakshya India 25% 07-06-2023 28-07-2024
Road work Lakshya India 35% 25-05-2024 30-06-2024
2 Dps Gomtinagar(Old)
Audi work Lakshya India 40% 25-05-2024 20-07-2024
Guard room Lakshya India 70% 02-06-2024 30-06-2024
3 Dps Eldeco Road work Lakshya India 55% 06-06-2024 30-06-2024
Toilet Renovation work Lakshya India 70% 25-05-2024 30-06-2024
Sports complex work Lakshya India 25% 30-04-2024 15-08-2024
4 Dps Jankipuram Toilet renovation work, Painting work Shaktie construction 60% 27-05-2024 30-06-2024
5 Aps Vrindavan Repairing work Lakshya India 15-06-2024 25-06-2024
6 Dps Gomtinagar(New) Repairing work Shaktie construction 15-06-2024 25-06-2024

Note If Work will not completed on time then Penalty should be there(as per instruction of Cmd sir) on Running bills of contractor