CHW & LTHW Installation - R1 - Method of Statement
CHW & LTHW Installation - R1 - Method of Statement
CHW & LTHW Installation - R1 - Method of Statement
Contractor
4800000206/000 -Stage 4B – Method of Statement of Chilled Water and Low Temperature Hot Water Pipes
Subject Installation
Drawing
Specification no. N/A N/A Date 14-July-2024
reference
Architectural Civil/ Structural Facade
Discipline
Electrical Other (please specify):
Contractor Authorized
Signature
representative
QA/QC Manager’s
Date
name
Signature
Classification | Internal
Signature
Received by Contractor
Name Date
Signature
Classification | Internal
METHOD STATEMENT
Document history
4800000206/000 - Stage 4B - Method Statement for Chilled Water and Low
Revision code
Temperature Hot Description
Water Pipes Installation
of changes Purpose of issue Date
13-216100-4800000206-NAP-MEC-MST-000001REV01, Jul-2024
Classification | Internal
Document approval
METHOD
STATEMENT FOR
CHILLED WATER AND LOW
TEMPRATURE HOT WATER
PIPES INSTALLATION
CONTRACT No.
4800000206/046
Comment Issued
Revision Date By
to Consultant
DOCUMENT APPROVAL
SHEET
Number: 13-211002-4800000206-NAP-MEC-MST-000018
DOCUMENT TYPE: METHOD STATEMENT FOR CHILLED WATER AND LOW TEMPRATURE
HOT WATER PIPES INSTALLATION
Project Commissioning
1 M/S PREPARED BY Yazan AL-Asakryeh
Engineer
Commissioning
2 M/S REVIEWED BY Tarek Alissa
Manager
CONTACT DETAILS
INDEX
1. GENERAL
2. SCOPE/OBJECTIVE/PURPOSE
3. REFERENCE DOCUMENTS/DESIGN
5. RESPONSIBILITIES
6. EQUIPMENT/TOOLS/MATERIALS
11. ATTACHMENTS
1. GENERAL
The method statement for the Chilled Water Pipe and Low Temperature Hot Water Pipe
Installation Procedure in SINDALAH VILLAGE CLUSTER-01 NEOM is controlled and
implemented by NESMA, according to the specifications as well as consultant’s/client
instructions.
2. SCOPE/OBJECTIVE/PURPOSE
This method statement provides guidance for the installation of Chilled Water and Low
Temperature Hot Water Pipes, ensuring full compliance with all relevant project standards,
technical specifications, approved shop drawings, and relevant international codes & to
Establishes minimum guidelines and responsibilities for the Issuing/receiving of work
permits, and for certifying those responsible for implementing the System.
This method statement gives guidelines contained herein to ensure that the job execution
complies with the requirement of the Specifications and the authorities concerned and
serves the intended purpose to satisfactory level. And to ensure the installation and testing
are in compliance with the specifications, standards, and project-specific requirements.
This procedure is applicable to all Chilled Water and Low Temperature Hot Water Pipes
installation activities, including components such as Pumps, Chillers, FAHU, AHU and FCU
connections, valves, identification, supports, etc.
3. REFERENCE DOCUMENTS/DESIGN
3.1 Approved Shop Drawings
3.1.1 13-211002-4800000206-NAP-MEC-DRG-196405-01
3.1.2 13-211002-4800000206-NAP-MEC-DRG-196402-01
3.1.3 13-211002-4800000206-NAP-MEC-DRG-196408-01
3.1.4 13-211002-4800000206-NAP-MEC-DRG-196411-01
3.2 NEOM Project Specification 13-211002-4200000002-RAM-MECSPC-000002 / Div. 23
3.2.1 23 0500 General Provisions for HVAC Works
3.2.2 23 0516 Expansion Fittings and Loops for HVAC Piping
3.2.3 23 0517 Sleeves and Sleeve Seals for HVAC Piping
2.3.4 23 0518 Escutcheons for HVAC Piping
3.2.5 23 0519 Meters and Gauges for HVAC Piping
3.2.6 23 0523 General-Duty Valves for HVAC Piping
3.2.7 23 0553 Mechanical Identification
3.2.8 23 2113 Hydronic Piping
3.2.9 23 2114 Hydronic Specialties
3.2.10 23 0529 Hangers & Supports for HVAC Piping & Equipment
3.2.11 23 0548 Vibration & Seismic Controls for HVAC Piping & Equipment
3.3 Manufacturer’s Recommendations
Comply with specific recommendations from the manufacturer's literature and other
requirements/specifications mentioned.
3.4 NEOM-NPR-STD-001_01.00 Projects Health and Safety Assurance Standard.
5. RESPONSIBILITIES
5.1 Project Manager
Responsible for ensuring that the works are performed according to specifications and
reports directly to the Contracts Manager. Will attend all weekly site meetings.
NESMA Site Engineers nominated by NESMA’s Construction Manager has the responsibility
to supervise and coordinate all the site activities of NESMA.
NESMA Site Engineers have the responsibility to ensure that the work is fully coordinated
with other on a day to day basis. NESMA Site Engineer have the responsibilities for
organizing and supervising the transportation of the materials to in co-ordination with the
other departments to ensure that the hoists, cranes and the platforms are efficiently
allocated and utilized. NESMA Site Engineers will also ensure that approved and agreed
safety practices and procedures are fully implemented.
5.4 QA / QC Manager
NESMA QA/QC Manager will check/Involve a strict internal quality control and inspection to
ensure that the work is executed fully in accordance with the requirements of the contract
specifications and drawings.
certificates, routine checks of the equipment’s and getting the approval before the
commencement for using and participating to the regular safety meetings.
5.7 Surveyor
NESMA Surveyor under the direction of the nominated Site Engineer has the responsibility
to establish the main reference and levels to check the same at regular intervals.
6. EQUIPMENT/TOOLS/MATERIALS
- Pipe wrenches, pliers, hammers
- Drill, reciprocating saw, impact driver
- Tape measure, spirit level, chalk line, laser level
- Pipe cutters, threading machine, hole cutter
- Welding equipment, soldering iron, crimping tools
- Safety goggles, gloves, dust mask, ear protection
- Ladder, scaffolding, hand truck
- Pipe insulation, mastic sealant, caulking gun
7.1.5 Site Engineer / Supervisor also ensures that all tools and equipment’s are available are
in good and safe working condition.
7.1.6 NESMA QA/QC Engineer/inspector shall check all the installation activity as per the
Inspection Check list.
7.1.7 Inspection Request shall be prepared by NESMA Engineer and will be submitted to the
consultant for inspection and approval.
7.1.8 Contractor is responsible for all installation activities and for getting the work
inspected /approved by AECOM / NEOM Representative.
7.1.9 Required power supply, Cable connection and disconnection, Equipment shift
arranged by Nesma.
7.1.10 CHW & LTHW Pipes shall be installed as per approved shop drawing and site
condition and made of Black Steel, except where specifically stated otherwise or as
indicated on the approved shop drawings.
7.1.11 All CHW & LTHW Pipework shall be coordinated with other services to ensure access
to execute the works.
7.1.12 Consideration to the sequence in which the work shall proceed is necessary.
8.1 Storage
8.1.1 Carefully lower pipes to prevent damage during off-loading.
8.1.2 Store pipes properly to prevent abrasions and damages.
8.1.3 Stack and cover delivered pipes for protection from dust.
8.1.4 Store valves, fittings, etc., in enclosed areas per manufacturer’s recommendations.
8.2 Pre-Works
8.2.1 Prefabricate pipework in an off-site facility by an approved fabricator.
8.2.2 The fabrication shall be carried out in a neat and workmanlike manner, with all internal
and external surfaces free from projections and sharp edges.
8.2.3 The Pipework fabricator shall prepare manufacturing drawings from the approved shop
drawings, showing detailed dimensions for the different composite parts, such as elbows,
branches, Tees, Reducers, etc.
8.2.4 Conduct a site survey to mark the pipe routing and support locations as per the
approved drawings.
8.2.5 Coordinate the piping layout with other services to ensure no clashes and minimal
bends/offsets.
8.2.6 Ensure that there is sufficient clearance around pipes for insulation and cladding
applications.
8.2.7 Clean and apply primer or red oxide to all seamless black steel pipes before
installation to prevent corrosion.
8.2.8 Fabricate pipe sections from approved materials per project specifications.
9.2 Coordination
9.2.1 Coordinate with Civil & Electrical for services interfaces.
9.5 Testing
9.5.1 Submit an inspection request for the chilled water piping installation to the consultant..
9.5.2 Follow safety protocols during testing.
9.5.3 Record and report test results for approval.
11. ATTACHEMENTS
11.1 Chilled Water and Low Temperature Hot Water Pipes Pre-Installing Checklist
11.2 Chilled Water and Low Temperature Hot Water Pipes Installing Checklist
11.3 Risk Assessment
Rev. No.:……………………………
SUBCONTRACTOR CONTRACTOR √ Page : 1 of 1
11.1 Chilled Water and Low Temperature Hot Water Pipes Pre-Installing Checklist
11.2 Chilled Water and Low Temperature Hot Water Pipes Installing Checklist