Professional Documents
Culture Documents
HVAC Duct Installation - R1 - Method of Statement
HVAC Duct Installation - R1 - Method of Statement
Contractor
Drawing
Specification no. N/A N/A Date 13-July-2024
reference
Architectural Civil/ Structural Facade
Discipline
Electrical Other (please specify):
Contractor Authorized
Signature
representative
QA/QC Manager’s
Date
name
Signature
Classification | Internal
Signature
Received by Contractor
Name Date
Signature
Classification | Internal
METHOD STATEMENT
Document history
4800000206/000 - Stage 4B - Method Statement for HVAC Duct Installation
Revision code Description of changes Purpose of issue Date
Document approval
METHOD
STATEMENT FOR
HVAC DUCT
INSTALLATION
CONTRACT No.
4800000206/046
Comment Issued
Revision Date By
to Consultant
DOCUMENT APPROVAL
SHEET
Number: 13-211002-4800000206-NAP-MEC-MST-000017
Project Commissioning
1 M/S PREPARED BY Yazan AL-Asakryeh
Engineer
Commissioning
2 M/S REVIEWED BY Tarek Alissa
Manager
CONTACT DETAILS
INDEX
1. GENERAL
2. SCOPE/OBJECTIVE/PURPOSE
3. REFERENCE DOCUMENTS/DESIGN
5. RESPONSIBILITIES
6. EQUIPMENT/TOOLS/MATERIALS
11. ATTACHMENTS
1. GENERAL
The method statement for HVAC Duct Installation Procedure in SINDALAH VILLAGE
CLUSTER-01 NEOM is controlled and implemented by NESMA, according to the
specifications as well as consultant’s/client instructions.
2. SCOPE/OBJECTIVE/PURPOSE
This method statement provides the guidance to be followed to be for all hand. The
Installation of HVAC Duct Work, ensuring full compliance to all relevant project standards,
technical specification, approved shop drawings and relevant international code & to
Establishes minimum guidelines and responsibilities for the Issuing/receiving of work
permits, and for certifying those responsible for implementing the System.
This method statement gives guidelines contained herein to ensure that the job execution
complies with the requirement of the Specifications and the authorities concerned and
serves the intended purpose to satisfactory level. And to ensure the installation and testing
are in compliance with the specifications, standards, and project-specific requirements.
This procedure is applicable to all HVAC ductwork installation activities, including
components such as AHU and FCU connections, flexible ducts, sleeves, identification,
supports, etc.
This method statement applies to the installation of HVAC Supply, Return, Fresh Air, and
Extract ducts, including dampers, fire dampers, motorized dampers, access doors, and all
duct accessories.
3. REFERENCE DOCUMENTS/DESIGN
3.1 Approved Shop Drawings.
3.1.1 13-211002-4800000206-NAP-MEC-DRG-196403-01
3.1.2 13-211002-4800000206-NAP-MEC-DRG-196404-01
3.1.3 13-211002-4800000206-NAP-MEC-DRG-196400-01
3.1.4 13-211002-4800000206-NAP-MEC-DRG-196401-01
3.1.5 13-211002-4800000206-NAP-MEC-DRG-196406-01
3.1.6 13-211002-4800000206-NAP-MEC-DRG-196407-01
3.1.7 13-211002-4800000206-NAP-MEC-DRG-196409-01
3.1.8 13-211002-4800000206-NAP-MEC-DRG-196410-01
3.2 NEOM Project Specification 13-211002-4200000002-RAM-MECSPC-000002 / Div. 23
3.2.1 23 3100 Duct Work
3.2.2 23 0500 General Provisions for HVAC Works
3.2.3 23 3300 Air Duct Accessories
3.2.4 23 0548 Vibration & Seismic Controls for HVAC Piping & Equipment
5. RESPONSIBILITIES
5.1 Project Manager:
NESMA Project Manager has the responsibility for ensuring that the works are performed
and shall report directly to the Contracts Manager. He will attend all weekly site meetings.
NESMA Construction Manager has the overall responsibility for ensuring that NESMA
complies with all the requirements of this Method Statement / Quality Control Procedure.
Construction Manager will nominate a Senior Site Engineer to supervise and coordinate all
the activities of NESMA on site.
5.4 QA / QC Manager:
NESMA QA/QC Manager will check/Involve a strict internal quality control and inspection to
ensure that the work is executed fully in accordance with the requirements of the contract
specifications and drawings.
5.7 Surveyor:
NESMA Surveyor under the direction of the nominated Site Engineer has the responsibility
to establish the main reference and levels to check the same at regular intervals.
6. EQUIPMENT/TOOLS/ MATERIALS;
- Screwdrivers, wrenches, pliers, hammers
- Drill, reciprocating saw, impact driver
- Tape measure, spirit level, chalk line, laser level
- Tin snips, duct knife, hole cutter
- Rivet gun, screws, stapler
- Soldering iron, heat gun, crimping tools
- Safety goggles, gloves, dust mask, ear protection
- Ladder, scaffolding, hand truck
- Duct tape, mastic sealant, caulking gun
8.1 Storage
8.1.1 When off-loading, the ducts shall be carefully lowered to ensure no damage to edges
or duct surfaces.
8.1.2 All ducts shall be stored properly to safeguard them from any abrasions and damages.
8.1.3 All delivered ducts will be stacked and covered to protect from dust etc.
8.1.4 VCD, motorized dampers, etc., shall be stored in enclosed areas as per manufacturer’s
recommendations.
8.2 Pre-Works
9.15 Inspection
9.15.1 The QA/QC department shall inspect the completed installations and offer the same
for consultant’s inspection.
9.15.2 Upon completion of the works and final fix items are installed, the consultant’s
engineer shall be invited for final inspection and certification.
11. ATTACHEMENTS
11.1 Duct Pre-Installing Checklist
11.2 Duct Installing Checklist
11.3 Risk Assessment