CT - Dammam Stimulation
Date: From 19-Apr-24 to 21-Apr-24
R-725
Pumping Service
End of Well Report
SOR No./29562
CT – Dammam Stimulation Program
OiLTECH
SIU-CTS-ROO-C-60032
Contents
1. EXECUTIVE SUMMARY:.................................................................................................................3
1.1 HS&E INCIDENTS:.................................................................................................................3
1.2 OBJECTIVE:...........................................................................................................................3
1.3 WELL HISTORY AND OBJECTIVE:.............................................Error! Bookmark not defined.
1.4 INTERVENTION OUTCOME:..................................................................................................3
1.5 MANAGEMENT OF CHANGE / DISPENSATION:.....................................................................5
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES...............................................5
2. INTERVENTION INFORMATION:....................................................................................................5
2.1 INTERVENTION DATA:..........................................................................................................5
2.2 DAILY OPERATIONS SUMMARY:...........................................................................................7
2.3 Well Schematic:....................................................................................................................8
2.4 BHA DETAILS:..........................................................................Error! Bookmark not defined.
2.5 CHEMICAL (MATERIAL) CONSUMPTION:............................................................................10
1. EXECUTIVE SUMMARY:
1.1 HS&E INCIDENTS:
There were zero HSE incidents during this intervention.
1.2 OBJECTIVE:
The program aims to improve the injectivity of Dammam wells by stimulating the open hole
using an HCl acid system to dissolve and bypass any damage present.
Achieved Comments
Objective
(Yes/No) (Why objective not achieved?)
Main Objective Yes
Lifting N/A
Other N/A
19-Apr-24:
- The Permit to Work (PTW) was printed out, and the team is waiting for the OAA to isolate the well.
- Continued rigging up and conducted the weekly pressure test for BOP (LP 300- HP 5000 Psi) along with the
Pull Test CT Connector (16 K).
- Completed BOP and Pull tests, confirming all systems are in good condition and ready for operations.
20-Apr-24:
- Executed pressure tests for all equipment ( Inlet FB line, DS, US, SSV) for 5 minutes each, following
the Standard Operating Procedure (SOP).
- The well was opened, and initial shut-in pressures were recorded.
- A pre-job injectivity test was performed, starting at a rate of 1 bpm and increasing to a maximum
of 4 bpm.
- The test concluded with a maximum tubing pressure (TBG) of 274 psi and annular pressure (A
Ann) of 298 psi at 4 bpm.
Acid Treatment:
- In two separate passes, acid was pumped downhole through the CT:
- Pass 1: CT was lowered to a specific depth (HUD-1 meters) while continuously pumping acid at 2.5bpm.
- Pass 2: CT injection was stopped at the same depth, then retrieved to 570 meters while continuing acid
pumping.
- During the acid treatment, circulation pressure reached 4850 psi for the first pass and 4900 psi for the second
pass. A total of 127+27 barrels of acid were used.
Well Shut-In:
19-Apr-24:
Start pumping brine (Final-injectivity test), (TBG Shut-in= 138 psi), (Ann A Shut-in= 50psi),
Received instruction from ROO WSC to commence rig down the equipment.
OT crew held a TBT with all crew members for flushing and rig down.
Continue R/D and move to next well
F
Fig: 1 per-injectivity test
N/A
1.6 OTHER SERVICES INVLOVED IN ACHIEVING SOR OBJECTIVES
Date Service Service provider Details/Comments
2. INTERVENTION INFORMATION:
2.1 INTERVENTION DATA:
Wellbore Clearance Fish left in hole:
Depth OD: Details of BHA left in hole: Depth OD
HUD 789.6 m
EOT 563m 4.5”
Depth ID:
Restriction 3.95
Perforating Details
Reservoir Top Bottom Thickness Gun type Gun SPF Double Perfs
size
N/A N/A
Stimulation Details
Stimulation Type Fluid type Rate Pressure Comment
Acid Stimulation (15%HCl) +10%MS) 2.5 bpm 4900
Logging Details
Logging Type Bottom Top Interpretation summary (Comment)
Wellhead Pressures
As Found: As Left: Flowing Parameters:
Well Status: Shut-in Shut-in
THP 0 psi 138psi Choke size N/A S.G water N/A
A Ann 50 psi 50psi USP N/A Salinity N/A
N/A
B Ann 207N/A 0 psi DSP S.G oil --
18-Mar-24 Continue Rig up and Pressure Test, CT purge , RIH for acid pumping
The well was opened with specific pressures and total acid volume was pumped
19-Mar-24
Rig Down and start mobilize the equipment then PTW closed