Professional Documents
Culture Documents
Work Permit CCSPC
Work Permit CCSPC
Page 1 of 4
AREA/DEPARTMENT: CONTRACTOR:
TYPE OF WORK:
Others:
WORK PERMIT CCSPC-WP-01
Page 1 of 4
NO FOREMAN/LEADMAN/SUPERVISOR - NO WORK!
WORK PERMIT REVALIDATION
Page 1 of 4
I have personally checked that the traffic management plan including installation of RECOMMENDED SAFETY MEASURES
safety barriers and road signs: O Use of lighting (type )
O has complied with the safe traffic requirement in preventing vehicle accident and O Use of PPE (type )
protection of the personnel working and within the vicinity of permitted area O Traffic re-routing
O may not be sufficient enough and shall be provided with additional precautions O Signages and barricades
O is not safe to perform assigned task O Standby Assistance (for rescue operation)
O
BY: NOTED BY: O
SCAFFOLDING CERTIFICATE
Erected scaffolding was personally checked by me and certify that it is: RECOMMENDED SAFETY MEASURES
O Safe to use and perform specified job O Secure drop zone
O Safe to use and perform specified job following recommended safety measures O Use of FBH w/ double lanyard
O Not safe to perform specified job O Securely tied tools
O BP monitoring to personnel working @ ht.
O Daily inspection of scaffold
BY: NOTED BY: O Standby Assistance
O Rope, harnesses and/or wristlets
SCAFFOLD INSPECTOR / DATE PROJECT MANAGER / DATE O Others
(Signature over Printed Name) (Signature over Printed Name)
LIFTING CERTIFICATE
We conducted pre-use inspection I personally verified area of All required certificates Pre-lift meeting was conducted
of our equipment, tools, and lifting/ loading/ unloading and (operator, rigger & crane), and Lifting plan was established.
materials to be use and certify certify that working environment including JHA were submitted. After discussion with all
that: from ground to overhead is: Alcohol test before lifting was personnel concerned I certify
O Safe lifting activity can be O Safe to perform lifting activity also done and I certify that: that:
done O Safe to perform lifting activity O Safe lifting activity can be O Safe lifting activity can be
O Safe lifting activity can only following recommended safety done done
be done following recommended measures O Safe lifting activity can only be O Safe lifting activity can be
safety measures O Not safe to perform specified done following recommended done following recommended
O Lifting activity is not safe. job safety measures safety measures
O Lifting activity is not safe O Lifting activity is not safe
BY: BY:
CRANE OPERATOR / RIGGER PROJECT SUPERVISOR BY: BY:
(Signature over Printed Name) Signature over Printed Name) EHS Officer PROJECT MANAGER
(Signature over Printed Name) (Signature over Printed Name)
O O
O O
WORK PERMIT CCSPC-WP-01
Page 1 of 4
ELECTRICAL CERTIFICATE
Machine, Tools, Equipment and/or / Facility was personally checked and tested by me RECOMMENDED SAFETY MEASURES
and certify that it is: O Isolate electrical energy using LOTO
O Safe to use and/or perform specified job O Isolate electrical energy using rubber insulator
O Safe to use and/or perform specified job following recommended safety measures O Use of multi-tester
O Not safe to perform specified job O Daily inspection of tools
O BP monitoring to personnel working @ ht.
BY: NOTED BY: O Buddy system
O Others
ELECTRICAL INSPECTOR / DATE PROJECT MANAGER / DATE O
(Signature over Printed Name) (Signature over Printed Name)
EXCAVATION CERTIFICATE
I have checked the site/studied the layout drawing and certify that the excavation: RECOMMENDED SAFETY MEASURES
O can be carried out without risk of damage to any underground services O Use of lighting (type )
O can be carried out provided that additional precautions are taken to prevent damage O Use of PPE (type )
to the equipment /services O Gas Testing
O is not safe to perform excavation O Shoring
BY: NOTED BY: O Signages and barricades
O Standby Assistance (for rescue operation)
CONSTRUCTION/ELECT’L SUPV. / DATE PROJECT MANAGER / DATE O
Signature over Printed Name) (Signature over Printed Name)