VACUUM EVAPORATOR 2
Activity ID Activity Name At Completion BL Project BL Project Start Finish Variance - BL 2023 2024 2025
Duration Start Finish Project Finish Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Date
OKI2 - VE First Schedule Evaluation 2023-09-22_Current 926 01-Apr-22 25-Feb-25 30-Nov-22 A 13-Jun-25 -107
PROC1000 Tank Farm ETA Site 0 01-Apr-22 10-Jan-24* -649 Tank Farm ETA Site, , 10-Jan-24*
PROC1010 Last Shipment of Tank 0 01-Apr-22 01-Apr-22 25-Apr-24* 25-Apr-24 -755 25-Apr-24, Last Shipment of Tank
PROC1020 Effect Shell 1st Shipment (1E,2B,2A,3,4) ETA site 0 01-Apr-22 20-Dec-23* -629 Effect Shell 1st Shipment (1E,2B,2A,3,4) ETA site, 20-Dec-23*,
PROC1030 Effect Shell 2nd Shipment (1A,1B,1C,1D,5,6,7) ETA Site 0 01-Apr-22 20-Feb-24* -691 Effect Shell 2nd Shipment (1A,1B,1C,1D,5,6,7) ETA Site, 20-Feb-24*,
PROC1040 Pump 1st Shipment ETA Site 0 01-Apr-22 15-Nov-23* -594 Pump 1st Shipment ETA Site, 15-Nov-23*,
PROC1050 Pump 2nd Shipment ETA Site 0 01-Apr-22 15-Dec-23* -624 Pump 2nd Shipment ETA Site, 15-Dec-23*,
PROC1060 Pump 3rd Shipment ETA Site 0 01-Apr-22 15-Mar-24* -715 Pump 3rd Shipment ETA Site, 15-Mar-24*,
PROC1070 Anchor Bolt for Tank farm ETA Site 0 01-Apr-22 25-Nov-23* -603 Anchor Bolt for Tank farm ETA Site, , 25-Nov-23*
PROC1080 CRP Tank ETA Site 0 01-Apr-22 25-Mar-24* -724 CRP Tank ETA Site, , 25-Mar-24*
Milestone 78 11-Aug-23 20-Jan-24 15-Sep-23 A 02-Dec-23 50 02-Dec-23
Engineering Construction Plan 523 30-Nov-22 03-Feb-24 30-Nov-22 A 05-May-24 -92 05-May-24
GEN1010 VE Completion & Acceptance 14 21-Jan-24 03-Feb-24 22-Apr-24 05-May-24 -92 05-May-24, VE Completion & Acceptance
VE Construction 509 30-Nov-22 20-Jan-24 30-Nov-22 A 21-Apr-24 -92 21-Apr-24
VE Tank Construction 420 30-Nov-22 02-Dec-23 30-Nov-22 A 23-Jan-24 -52 23-Jan-24
Effect Area Construction 402 30-Nov-22 25-Aug-23 30-Nov-22 A 05-Jan-24 -133 05-Jan-24
Evap. Eff 5 Construction 287 04-Jan-23 07-Jul-23 04-Jan-23 A 17-Oct-23 -102 17-Oct-23
CIV4500 Excavation 10 04-Jan-23 13-Jan-23 04-Jan-23 A 13-Jan-23 13-Jan-23
A 0
A, Excavation
CIV4520 Cut of Pile 7 14-Jan-23 20-Jan-23 14-Jan-23 A 20-Jan-23 A 20-Jan-23 A, Cut0of Pile
CIV4530 Lean Concrete K-125 1 21-Jan-23 21-Jan-23 21-Jan-23 A 21-Jan-23 A 21-Jan-23 A, Lean
0 Concrete K-125
CIV4540 Pile Head Treatment 3 22-Jan-23 24-Jan-23 22-Jan-23 A 24-Jan-23 A 24-Jan-23 A, Pile
0 Head Treatment
CIV4550 Rebar Installation 18 22-Feb-23 11-Mar-23 22-Feb-23 A 11-Mar-23 A 0
11-Mar-23 A, Rebar Installation
CIV4560 Formwork Foundation 9 27-May-23 04-Jun-23 27-May-23 A 04-Jun-23 A 0 04-Jun-23 A, Formwork Foundation
CIV4570 Grounding 4 01-Jun-23 04-Jun-23 01-Jun-23 A 04-Jun-23 A 0 04-Jun-23 A, Grounding
CIV4580 Install Anchor Bolt 5 05-Jun-23 09-Jun-23 05-Jun-23 A 09-Jun-23 A 0 09-Jun-23 A, Install Anchor Bolt
CIV4590 Pouring Concrete Foundation 53 10-Jun-23 11-Jun-23 10-Jun-23 A 01-Aug-23 A -51 01-Aug-23 A, Pouring Concrete Foundation
CIV4600 Dismantling Formwork Foundation 7 12-Jun-23 18-Jun-23 02-Aug-23 A 08-Aug-23 A -51 08-Aug-23 A, Dismantling Formwork Foundation
CIV4610 Formwork Pedestal 3 19-Jun-23 21-Jun-23 09-Aug-23 A 11-Aug-23 A -51 11-Aug-23 A, Formwork Pedestal
CIV4620 Pouring Concrete Pedestal 2 22-Jun-23 23-Jun-23 12-Aug-23 A 13-Aug-23 A -51 13-Aug-23 A, Pouring Concrete Pedestal
CIV4630 Dismantling Formwork 3 24-Jun-23 26-Jun-23 04-Oct-23* 06-Oct-23 -102 06-Oct-23, Dismantling Formwork
CIV4640 Coating Foundation 4 27-Jun-23 30-Jun-23 07-Oct-23* 10-Oct-23 -102 10-Oct-23, Coating Foundation
CIV4650 Grouting Installation 3 01-Jul-23 03-Jul-23 11-Oct-23* 13-Oct-23 -102 13-Oct-23, Grouting Installation
CIV4660 Backfill Soil 4 04-Jul-23 07-Jul-23 14-Oct-23* 17-Oct-23 -102 17-Oct-23, Backfill Soil
Evap. Eff 6 Construction 303 20-Dec-22 10-Jul-23 20-Dec-22 A 18-Oct-23 -100 18-Oct-23
CIV4670 Excavation 15 20-Dec-22 03-Jan-23 20-Dec-22 A 03-Jan-23 A
03-Jan-23 0
A, Excavation
CIV4680 Cut of Pile 10 30-Dec-22 08-Jan-23 30-Dec-22 A 08-Jan-2308-Jan-23
A 0
A, Cut of Pile
CIV4690 Lean Concrete K-125 3 09-Jan-23 11-Jan-23 09-Jan-23 A 11-Jan-2311-Jan-23
A 0
A, Lean Concrete K-125
CIV4700 Pile Head Treatment 18 12-Jan-23 29-Jan-23 12-Jan-23 A 29-Jan-23 A 29-Jan-23 A, Pile
0 Head Treatment
CIV4710 Rebar Installation 18 04-Feb-23 21-Feb-23 04-Feb-23 A 21-Feb-23 A 0 A, Rebar Installation
21-Feb-23
CIV4720 Formwork Foundation 9 27-May-23 04-Jun-23 27-May-23 A 04-Jun-23 A 0 04-Jun-23 A, Formwork Foundation
CIV4730 Grounding 4 01-Jun-23 04-Jun-23 01-Jun-23 A 04-Jun-23 A 0 04-Jun-23 A, Grounding
CIV4740 Install Anchor Bolt 4 05-Jun-23 08-Jun-23 05-Jun-23 A 08-Jun-23 A 0 08-Jun-23 A, Install Anchor Bolt
CIV4750 Pouring Concrete Foundation 53 09-Jun-23 10-Jun-23 09-Jun-23 A 31-Jul-23 A -51 31-Jul-23 A, Pouring Concrete Foundation
CIV4760 Dismantling Formwork Foundation 7 11-Jun-23 17-Jun-23 01-Aug-23 A 07-Aug-23 A -51 07-Aug-23 A, Dismantling Formwork Foundation
CIV4770 Formwork Pedestal 3 18-Jun-23 20-Jun-23 08-Aug-23 A 10-Aug-23 A -51 10-Aug-23 A, Formwork Pedestal
CIV4780 Pouring Concrete Pedestal 2 21-Jun-23 22-Jun-23 11-Aug-23 A 12-Aug-23 A -51 12-Aug-23 A, Pouring Concrete Pedestal
CIV4790 Dismantling Formwork 3 23-Jun-23 25-Jun-23 13-Aug-23 A 15-Aug-23 A -51 15-Aug-23 A, Dismantling Formwork
CIV4800 Coating Foundation 8 26-Jun-23 03-Jul-23 04-Oct-23 11-Oct-23 -100 11-Oct-23, Coating Foundation
CIV4810 Grouting Installation 3 04-Jul-23 06-Jul-23 12-Oct-23* 14-Oct-23 -100 14-Oct-23, Grouting Installation
CIV4820 Backfill Soil 4 07-Jul-23 10-Jul-23 15-Oct-23* 18-Oct-23 -100 18-Oct-23, Backfill Soil