S.no. Description of work No.

of Items Length Width Height Total


1 Footing Concrete
Rectangle Footing (2200
x 2000) 25 2.2 2 0.25 27.5
Unit Remark

cum
Providing and laying in position specified grade of reinforced cement concrete of specified gr
the cost of shuttering & cenetering.
1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm Nominal Size
Volume of Concrete 1
Dry mix of about 52 to 54% extra volume(1.52 to 1.54). These extra dry
1.54
volume will get balance to 1 Cum after pouring water.
Description Quantity Unit Rate
Portland Cement 8.06 Bag 380
Aggregate (Distribute in below) 0.84 Cum 1350
Coarse Sand (Zone III) 0.42 Cum 1350
Carriage of Material
Carriage of Cement 8.06 Bag 5
Carriage of Stone Aggregate below 40mm 0.84 Cum 100
Carriage of Coarse Sand (Zone III) 0.42 Cum 100
Labour
Mason 0.17 Day 500
Beldar 2 Day 350
Bhishti 0.9 Day 280
Equipments
Hire Charges of Concrete mixer 0.25 to
0.40 Cum with Hooper 0.07 Day 500
Vibrator (Needle type 40mm) 0.07 Day 200
Sundries 14.3 Day 2
Total (A)
Add 1% Water Charges (B)
Total (A+B) = C
15% Contractor's profit (D )
Grand Total (C+D) = E
ncrete of specified grade excluding

m Nominal Size Material Ratio


1 Cum Cement 1
Sand 1.5
1.54
Aggregate 3
Rate Amount Total 5.5
380 3064.32
1350 1134.00
1350 567.00

5 40.32
100 84.00
100 42.00

500 85.00
350 700.00
280 252.00

500 35.00
200 14.00
2 28.60
l (A) 6046.24
Charges (B) 60.46
A+B) = C 6106.70
s profit (D ) 916.01
D) = E 7022.71
Code No. Description of Work Unit Rate
Providing and laying in position
specified grade of reinforced cement
1.1 concrete of specified grade excluding
the cost of shuttering & cenetering.

1:1½:3 (1 Cement: 1½ coarse sand


1.1.1 (zone-III)
: 3 graded stone aggregate 20 Cum 7022.71
mm Nominal Size
Name of WORK
Engineer Name
Tender Amount
S.no Code no. Description of work Quantity
Providing and laying in position specified
grade of reinforced cement concrete of
1 1.1
specified grade excluding the cost of
shuttering & cenetering.

1:1½:3 (1 Cement: 1½ coarse sand (zone-III) :


1.1.1
3 graded stone aggregate 20 mm Nominal Size
Unit Rate Amount

Cum 7022.71 0