Providing and laying in position specified grade of reinforced cement concrete of specified gr
the cost of shuttering & cenetering.
1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm Nominal Size
Volume of Concrete 1
Dry mix of about 52 to 54% extra volume(1.52 to 1.54). These extra dry
1.54
volume will get balance to 1 Cum after pouring water.
Description Quantity Unit Rate
Portland Cement 8.06 Bag 380
Aggregate (Distribute in below) 0.84 Cum 1350
Coarse Sand (Zone III) 0.42 Cum 1350
Carriage of Material
Carriage of Cement 8.06 Bag 5
Carriage of Stone Aggregate below 40mm 0.84 Cum 100
Carriage of Coarse Sand (Zone III) 0.42 Cum 100
Labour
Mason 0.17 Day 500
Beldar 2 Day 350
Bhishti 0.9 Day 280
Equipments
Hire Charges of Concrete mixer 0.25 to
0.40 Cum with Hooper 0.07 Day 500
Vibrator (Needle type 40mm) 0.07 Day 200
Sundries 14.3 Day 2
Total (A)
Add 1% Water Charges (B)
Total (A+B) = C
15% Contractor's profit (D )
Grand Total (C+D) = E
ncrete of specified grade excluding
5 40.32
100 84.00
100 42.00
500 85.00
350 700.00
280 252.00
500 35.00
200 14.00
2 28.60
l (A) 6046.24
Charges (B) 60.46
A+B) = C 6106.70
s profit (D ) 916.01
D) = E 7022.71
Code No. Description of Work Unit Rate
Providing and laying in position
specified grade of reinforced cement
1.1 concrete of specified grade excluding
the cost of shuttering & cenetering.
Cum 7022.71 0