Development of Risk Sensitive Land Use Planning Practice In Greater Dhaka

Contact Package No: URP/RAJUK/S-5


Consultant: JV of NKY Architectural & Engineering Co., Turkey
Project objectives

 Review, enrich and strengthen the current planning regulation.

 Ensure that DSP (2016-2035) and DAPs are risk-sensitive

Project Methodologies

 Planning knowledge base


 Seismic Hazard Assessment and microzonation
 Geotechnical survey
 Earthquake risk assessment
 Land Subsidence Hazard
 Flood Risk Assessment

Geotechnical survey
The geotechnical surveys are designed to provide the data for following analyses:

1. Site response analysis


2. Soil bearing capacity
3. Liquefaction assessment
(Above all’s are Base on SPT, CPT, SCPT, Downhole 400 field tests & Lab tests
analysis results)

For Main Purpose Cross-validation or Correlation

Geotechnical Investigation

SPT

Field Seismic Downhole

Investigation SCPT

CPT
Geotechnical
Wash Sieve & Moisture Content
Investigation Sieve Analysis

Atterberg Limit Test

Shrinkage Limit
Laboratory Hydrometer and specific
Gravity
Investigation
Unconfined Compression Test

Direct Shear Test

Consolidation Test

Tri Axial Test


Amount of tests based on Contract

TEST NAME AMOUNT / OUTCOMES


NUMBERS
Micro tremor Test 500 Nos natural frequency, natural period
and amplification factor
Standard Penetration Test (SPT) 15000 meters Soil Layer, Physical parameter of soil
Cone penetration Test (CPT) 5000 meters information on the soil type and
stratification, shear strength in
clays , the relative density and
friction angles in sand
Seismic Cone penetration Test (SCPT) 400 Nos seismic shear wave velocity

Seismic Downhole Test 400 Nos direct measurement of seismic wave


velocity
Deliverables

MD1 GD

MD GD
GD2 GD3 GD4
5 1
+

• MD1 (Development of SEA Report for Greater Dhaka Metropolitan Development Plan) is
Submitted but not yet approved.

• MD2 (Final Consultations Report & Situational Analysis and Diagnosis Report) is approved

• MD3 (3.1 Preliminary Assessment Report, 3.2 Development of a strategic framework, 3.3
Geotechnical and Geological Survey Plan) is submitted completely but not yet approved

• MD4 (4.1 Draft analysis report of the geotechnical and geological studies conducted with
Recommendations, 4.2 Final Geotechnical and Geological Survey plan) is ongoing.

• MD5 (Final Report and completion of all obligations) is ongoing .

• GD-01 Microtremor Tests


• GD-02 SPT (Standard Penetration Tests) including Laboratory Tests
• GD-03 CPT (Cone Penetration Tests)
• GD-04.2 SCPT (Seismic Cone Penetration Tests)
• GD-04.1 Seismic Download Tests

Importance of SEA (Strategic Environmental Assessments)


a) To provide information for decision makers, the community about the environmental impacts,
policies, plans and programs at the very early stages of planning and consequently, improving
decision making process.
b) To ensure sustainable development at the stage of planning and development.
c) To develop and upgrade non-environmental organizations by designing a sustainable program.
Approaches to be Made for this Project
i) Studying 2007 SEA Report
ii) Analyzing relevant research articles, reports and books.
iii) Site Visits, Data Collections, Field Works.
iv) Meeting, Interviews with Stakeholders (i.e. consulting firm, educational institutes,
industries etc.), Online Surveys.
v) Promoting website (www.dhakaurpsea.org), social media (i.e. Facebook, Instagram,
LinkedIn, Twitter etc.), advertisements.
vi) Arrange workshops to discuss about the problems and solutions of environmental
issues, ideas to minimize it.
vii) Revise the findings.
viii) Evaluating by SEA specialists with different background.
ix) Preparing interim report.
x) Preparing draft final report.
xi) Submit the Final Report on approval.
xii) Plan Implementation.

Our Approval Procedure/ stage

PIU official’s The World Bank Stakeholder’s

Project Oversight Project working


Committee (POC) group (PWG)

Finally, Go through HOPE

• we have Updated plan,


1. We will conduct SEA validation.
• After reviewing the 44 borehole data:
1. We will submit the updated geotechnical survey plan (MD3.3).
• After getting the approval for framework (MD3.2) :
1. We will start to conduct flood hazard assessment.
2. We will start to conduct liquefaction assessment.
3. We will start to conduct seismic microzonation.