List of Activities for PRIMAVERA Training

Sr No. Task Name Assigned WBS Duration Predecessors


1 Selection Land Acquisition 10
2 Purchase Land Acquisition 7 1
3 Transfer Land Acquisition 3 2
4 Possession Land Acquisition 2 3
5 Hiring of Architect Procurement of Services 10 1
6 Hiring of Contractor Procurement of Services 10 1
7 Selection & Hiring of Supplier Procurement of Services 15 6
8 Architectural Design Design 15 5
9 Structural Design Design 7 8
10 Electrical Design Design 7 8
11 Plumbing Design Design 7 8
12 Layout Design Design 5 9
13 Drawings Design 10 8,9,10,11,12
14 HR Mobilization 2 12,13
15 Machinery Mobilization 7 6
16 Layout Civil Works 1 8,9,12
17 Excavation Civil Works 7 16
18 Lean Concrete Civil Works 5 17
19 Brick Work in Foundation Civil Works 15 18FS+10 days
20 DPC Civil Works 7 19
21 Brick Work Civil Works 45 20SS+2 days
22 Lintels Civil Works 15 21SS+10 days
23 Roofing Civil Works 40 22
24 Flooring Civil Works 40 23
25 Ducting Electric Works 7 23
26 Laying of Pipes Electric Works 7 25
27 Wiring Electric Works 15 26
28 Connection Electric Works 5 27
29 Fixtures Electric Works 5 28
30 Ducting Plumbing Works 7 23
31 Laying of Pipes Plumbing Works 15 25
32 Connections Plumbing Works 15 26
33 Fixtures Plumbing Works 20 27
34 Plastering Finishings 45 28,33
35 Tiling Finishings 45 34
36 Woodwork Finishings 50 34
37 Doors & Windows Finishings 20 22
38 False Ceiling Finishings 15 34
39 White Wash and Paint Finishings 30 34FS+20 days
40 Interior Works Finishings 15 37
41 Boundary Wall & Gate Finishings 45 23SS+10 days