5 - Mechanical scope
5.1 Scope
5.2 Documentation
5.3 References
5.4 Technical requirements
5.5 Painting
5.6 Insulation
5.7 Steel structural
5.8 Pipe support
5.9 Accessibility
5.10 Spacing
5.11 Mechanical equipment installation
5.12 Piping fabrication and assembly
5.13 Installation of piping on site
5.14 Testing, commissioning and start-up
5.15 Test and inspection plan
5.16 Discrepancy
Page 1 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
5 - Mechanical Scope
5.1 Scope
Mechanical work description covers the basic requirements for the supply and
installation of equipment, piping, instrumentation and materials.
All work shall be done in accordance with piping drawings, RFQ specification and
requirement and international standards and specifications.
Page 2 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
The Scope includes, but is not limited to all mechanical works and aspects
requested and described in the (PART I & PART II) of the PROJECT which
described in EXHIBIT B (scope of work)/section 1 general scope and definitions.
In case of discrepancy arises or exists between codes, standards and documents, the
most severe shall govern.
5.1.3 Construction
CONTRACTOR shall provide all personnel, supervision, co-ordination, tools and
material as well as competent knowledge of construction for the mechanical
installation, testing and putting into operation all the works as detailed.
CONTRACTOR shall be familiar with the construction drawings of all trades and
when laying out the work with regard to structural piping and mechanical features.
CONTRACTOR shall provide for approval a construction schedule, which will take
into full consideration the availability or delivery of all equipment, materials and the
target completion date required by the COMPANY.
Page 3 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
CONTRACTOR shall arrange his own inspection team and equipment for the quality
control of the whole work. It shall be noted that although the COMPANY will
appoint its own independent inspection agent, the responsibility for meting the
appropriate quality standards will remain with the CONTRACTOR.
Page 4 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
The Deir Ali scope which include but not limited to the following:
fiscal metering station ( FMS ) near the Deir Ali area with 3MMSCMD
capacity: ref to drawing 6000-10-12
36 Inch of API 5L X70 pipeline branch with approximately length 14 km
equipped with launcher tagged 003L and receiver tagged 003R.
Three tie-in with existing gas net work facilities as following:
With the 18 inch Omar pipeline via two (2) hot taping points up stream of the
BVS 913: ref to drawing 6000-10-03
With the 24 inch Palmyra pipeline via one (1) hot tapping point upstream of
the BVS 4904: ref to drawing 6000-10-02
With Rayan existing manifold: ref to drawing 6000-10-04
5.2 Drawing
CONTRACTOR shall provide all drawings and is responsible to show all details of the work
and to ensure the drawings are correct and complete before beginning the work.
Page 5 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
5.3 References
Contract General Conditions, drawings, specifications, etc. are referenced in
Exhibit ‘G’ – Contract General Specifications and Standards.
Page 6 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
All the material to be delivered for the PROJECT shall be new /unused and
purchased from the first class manufacturer included in the approved
vendor/manufacturer list.
All main equipments shall equipped at the inlet with double block and bleed
valves
5.4.2.1 –Metering Skid
The FMS will consist of two (2) main metering trains (2X100%) one on
operation and one as standby.
Each train shall be designed for 125 MSCMH (125000 cubic meter of gas per
hour)
Each train shall typically contain but not limited to the following:
One filter separator (cartridge type).
Senior type orifice flow meter (including flow computers).
One fast acting slam shutdown valve (SSV) at the inlet of train.
One emergency shutdown valve (ESV) at the outlet of train.
Vent and blow down system.
All related piping, instrumentation, valves etc.
All required walk ways, platforms and accessibility for easy operation and
maintenance requirements
The main trains will take the gas from the main gas pipeline and deliver the
metered gas to the two (2) gas turbine generator via one header with
3MMSCMD capacity
Page 7 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
The two trains shall equip with one low flow line with 15 MCMH (15000
cubic meter of gas per hour) as maximum out put flow rate.
For the controlling philosophy and operation strategy and concepts see
the instrument and control scope
Common Five micron (5µ) filter cartridge type before inlet header
One (1) pressure reducing system (two stages pressure reduction).
All related piping, instrumentation, valves etc.
The instrument gas skid shall be easy operation and maintenance accessible
The CONTRACTOR shall design Buffer tank capable for all station
instruments operation at least 30 minuets of uninterrupted operation
5.4.2.3 Filters shall be designed according but not limited to the following
requirements:
filter shall be cartridge vertical type c/w quick opening closure
filters shall be ASME stamped and manufactured by ASME authorized
manufacturers home have ASME certificates
Filters should be designed according to the maximum design pressure,
temperature ,flow , gas compositions and site conditions
Maximum filter design pressure shall be 75 bar gauge.
Filter shall be equipped with vent to blow down system.
Filter shall be provided with double block and bleed.
Page 8 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
For this three (3) launcher and three (3) receivers the CONTRACTOR shall
comply with following:
The launcher/ receiver pig trap shall have an enough space for working
and maintenance.
This launcher and receiver shall be designed for a suitable geometric and
intelligent tools inspections.
Page 9 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
Each pigging facility shall provided with two pig signallers one when the
pipeline become above ground and the other on the pig trap it self and the
pig signal shall be transmitted via the DCS
The pig trap shall equipped with pressure and temperature indicator.
Pig launcher/receiver trap shall be ASME stamped and manufactured by
ASME authorized manufacturers home have ASME certificates
The pig launcher /receiver station design pressure shall be 75 bar gauge
The pig launcher /receiver shall be easy operation and maintenance
accessibility.
All valves on the main pipe line shall be full bore size.
Branch connections on the main pipe line shall be barred type.
The launcher /receiver trap shall be flanged
The typically pig launching /receiving station shall contain but not limited to
the following:
Anchor block designed to overcome the reaction created by the forth of
change direction.
Pig signaller when the pipeline go through above ground
Electrical isolation joint between above and under ground
By-passed and flanged shut down valve
Motorized flanged ball valves
Vent stack and vent system.
The launcher/receiver trap with all Kickers, drain, vents lines.
Crane and inserting pigging tools
All relating piping and instruments
Accessibility and supporting
Nitrogen injection assembly
Future connection valves with blind flange and 0.5 " bleeding valvs
Page 10 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
BVS 6001.
BVS 6002.
BVS 6003.
BVS 6004.
BVS 6005.
BVS 6007.
BVS 6008.
BVS 6009.
BVS 6010.
BVS 6011.
With the required future, Telecommunication building and supply and install Line Break
Detection/Control unit and deliver to the COMPANY as complete system.
Typically this BVS,s shall include but not limited to the following:
Welded Shut down valve.
Vent stack and vent system.
All relating piping and instruments
Accessibility and supporting
Nitrogen injection assembly
Future valves with blind flange and 0.5 " bleeding valves
The block valve station by pass shall use barred tees up and down stream of
the valve.
The contractor shall procure 36” flanged gear operated full bore
double block and bleed valve to be installed down stream of the
BVS 6003
The future valves shall be sized as the following for all project locations:
All future connection valves should be equipped by blend with double
1/2''bleed valves.
Page 11 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
L-6000 with two (2) 36”# 600 future valve for intended future gas
compressor station.
BVS 6001 with one (1) 24” # 600 future valve.
BVS 6002 with one (1) 24” # 600 future valve
BVS 6003 with one (1) 36” # 600 future valve
R-003 with one (1) 36” # 600 future valve
BVS 6004 with one (1) 24” # 600 future valve
BVS 6005 with one (1) 24” # 600 future valve
S-6006 (intermediate station) with one (1) 36” # 600 future valve
BVS 6007 with one (1) 24” # 600 future valve
BVS 6008 with one (1) 24” # 600 future valve
BVS 6009 with one (1) 24” # 600 future valve
BVS 6010 with one (1) 24” # 600 future valve
BVS 6011 with two (2) 36” # 600 future valve
R- 6012 with two (2) 36” # 600 future valve for future gas compressor
station required for phase II of the project and one (1) 24” # 600 future
valve for Lebanon future requirements
5.4.5 Mechanical requirements for the tie-in connection point with block valve
station 913 at the OMAR gas pipe line
The CONTRACTOR shall designs, procure, install and commission this tie-
in with the following consideration:
Page 12 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
Page 13 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
The blow down piping up to main header should be ASTM 333 for the
low temperature piping if like this blow down create excess decreasing in
the temperature
5.5 Painting
The CONTRACTOR shall be responsible for:
The quality of workmanship, which shall be performed in accordance with
schedule V9 and all other relevant documents such as site regulations, safety rules,
referred standards and codes considering the approved vendor recommendations
and instructions.
Maintenance of the paintwork until completion of the contract.
This shall include the repair of any damage caused by third parties.
Provision of all painting, thinning and cleaning materials and tools.
Control of waste resulting from the CONTRACTOR 's painting and coating
activities, in accordance with site regulations and specific contract requirements.
Surface preparation and painting of pipe, valves, fittings and pipe supports shall be
in accordance with the requirements of AFPC Schedule ‘V 9’.
5.6 Insulation
The CONTRACTOR shall apply the insulation for the Lines containing stagnant
liquids or small bore lines with low flow rates, e.g. (automatic) drain lines ,
chemical injection lines, blind ended lines, diesel fuel lines etc., shall be lagged
and heat traced to prevent freezing, solidifying, hydrate or wax formation during
low ambient temperatures,
Page 14 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
This shall include the repair of any damage caused by third parties.
The material and thickness and installation requirement shall be accordance
schedule J
Insulation shall be installed on piping and equipment where process conditions
require heat retention.
Pipe supports shall generally comply with the requirements of AFPC Schedule Q.
The CONTRACTOR shall take into account all other requirement when design
the pipe support to avoid any conflict with other activity like heat tracing
insulation, fitting and maintenance requirement.
All big valves shall be adequately supported without any conflict with
operation and maintenance requirements
Page 15 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
5.9 Accessibility
The CONTRACTOR shall design and install all accessibility requirement for all
PROJECT location which provide the operation and maintenance accessibility
requirement for all equipments, instruments, gauges, samples, valves etc
This accessibility shall provide enough room for operation and maintenance
requirement on the skids, vessels, etc...
All pipe work shall be arranged such that all maintainable items of equipment are
accessible and capable of being removed.
Piping systems shall be designed so that all equipment, valves and instruments can
be serviced safely and conveniently, operating valves shall be accessible at grade
or floor level.
Piping shall be routed to allow access for maintenance and routine operations.
Removal or replacement of equipment shall be possible with minimum
dismantling of piping.
Piping shall not impede access or escape routes and shall not present overhead or
tripping hazards.
5.10 Spacing
The CONTRACTOR shall take into consideration the spacing between
equipments and piping spacing to insure the easy movement for operation and
maintenance requirements.
Page 16 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
5.12 Discrepancy
In case a discrepancy arises or exists between codes, standards, drawings and documents,
the most severe shall govern in the following priority:
1- RFQ tender documents
2- (AFPC) scopes and specifications
3- International industry codes and standards
Page 17 of 18
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT –B
5- Mechanical SCOPE
Page 18 of 18