1.2 The Lump Sum CONTRACT PRICE comprises the sum of Lump Sum Contractor’s
shown in the Pricing Sheets.
1.3 The Pricing Sheets show the breakdown of the Lump sum CONTRACT PRICE per
Activity. An Activity is in this context defined as a specific execution function for a
Plant system or item indicated on the Pricing Sheets.
1.4 The price amounts shown for each Activity are deemed to be the full amount
payable to CONTRACTOR for the complete performance of all WORK associated
with that Activity, including, but not limited to, a proportional share in all other
costs incurred by CONTRACTOR for WORK required under CONTRACT for
which no specific Activity is defined.
Note: Bidders who are interested in financing the project can submit a
special financing offer which will be considered in the evaluation of
their bids.
this special offer should be put in a closed envelope in the financial
offer (third envelope).
2. PROGRESS PAYMENTS
For the calculation of the Value of Work Done ( VOWD ) at the end of each calendar
month, a percentage complete shall be mutually agreed between COMPANY and
CONTRACTOR for each Activity in accordance with the following guidelines:
1
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS
2.1 Engineering
Percentage
Description Status
Payment
- Basic Design approved. 35%
- Detail Design approved. 45%
Engineering 10%
- Manuals received and accepted
- As Built drawings received and accepted 10%
Training - Training of SGC’ staff
2.2 Procurement and Transportation of Materials and Equipment to the job site
2
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS
2.3.1.A Mobilization
- Mechanical
- skid/equipment installation 15%
- piping complete 40%
- instrument hook up 15%
- paint and insulation 15%
- cleaning, drying and Hydro test 15%
- Electrical
- Equipment installed 20%
- cable laid & terminated 20%
- MCC wired 25%
- grounding/lighting complete 15%
- System Tested 20%
- Control/Telecommunication
Hardware installed 30%
3
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS
Control 15%
Telecom.
- System Configured 30%
Control 10%
Telecom
- Interfacing to GCC System 10%
Control 5%
Telecom
- Mechanical
- equipment installed 15%
- piping/valves complete 45%
- instrument hook up 15%
- paint and insulation 15%
- testing complete 10%
- Electrical
- Equipment installed 30%
- cable laid & terminated 30%
- grounding/lighting complete 20%
- System Tested 20%
- Control/Telecommunication
Hardware installed
Control 40%
Telecom. 20%
- System Configured
Control 30%
Telecom 10%
4
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS
2.4 Commissioning (including initial spare parts and consumable) & Start-up