SYRIAN GAS COMPANY DTGD-HOMS

ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C


INVOICING AND PAYMENTS

EXHIBIT-C, “INVOICING AND PAYMENTS”

1. CONTRACT PRICE FOR

1.1 With reference to the TYBICAL CONTRACT, it is mutually agreed between


COMPANY and CONTRACTOR that for the complete performance of the WORK,
COMPANY shall pay to CONTRACTOR the Lump Sum CONTRACT PRICE of:

 an amount / 1000000000 / S.P only one billion Syrian Pounds


 an amount of / ________ / . Foreign Currency Portion

1.2 The Lump Sum CONTRACT PRICE comprises the sum of Lump Sum Contractor’s
shown in the Pricing Sheets.

1.3 The Pricing Sheets show the breakdown of the Lump sum CONTRACT PRICE per
Activity. An Activity is in this context defined as a specific execution function for a
Plant system or item indicated on the Pricing Sheets.

1.4 The price amounts shown for each Activity are deemed to be the full amount
payable to CONTRACTOR for the complete performance of all WORK associated
with that Activity, including, but not limited to, a proportional share in all other
costs incurred by CONTRACTOR for WORK required under CONTRACT for
which no specific Activity is defined.

1.5 The CONTRACT PRICE shall be paid by COMPANY as follows :

a- Syrian Currency Portion : COMPANY will pay an amount / 1000000000 / S.P


only one billion Syrian Pounds to The CONTRACTOR against services works
inside Syrian Arab Republic territory.
b- Foreign Currency Portion is to be paid by Foreign Currency transferable.

Signature : _____________________ Date : ________________

Note: Bidders who are interested in financing the project can submit a
special financing offer which will be considered in the evaluation of
their bids.
this special offer should be put in a closed envelope in the financial
offer (third envelope).

2. PROGRESS PAYMENTS

For the calculation of the Value of Work Done ( VOWD ) at the end of each calendar
month, a percentage complete shall be mutually agreed between COMPANY and
CONTRACTOR for each Activity in accordance with the following guidelines:

1
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS

2.1 Engineering
Percentage
Description Status
Payment
- Basic Design approved. 35%
- Detail Design approved. 45%
Engineering 10%
- Manuals received and accepted
- As Built drawings received and accepted 10%
Training - Training of SGC’ staff

2.2 Procurement and Transportation of Materials and Equipment to the job site

Description Status Percentage


Payment

- FMS Received 10%


- BVSs Received 9%
- Pigging Facilities Received 6%
- DCS System Received 7%
- Telecommunication System Received 8%
Equipment received at job site - Two Years Recommended Spare Parts 2%
Received
- Spare Parts and materials Required by 3%
Company received
- 36” pipeline received 45%
- Others 10%

 BIDDER TO SPECIFY THE PRICES, SHOULD BE PAID FOR EACH ITEM

Signature: ________________________________ Date : ___________________________

2
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS

2.3 Construction Activities


2.3.1 Mobilization & Supervision at job site

2.3.1.A Mobilization

2.3.1.B Supervision at job site


Project Manager
Civil
Pipeline
Welding
Mechanical
Instrumentation/Control & Telecomm.
Electrical

2.3.2 Construction and Pre commissioning of Facilities


2.3.2A Survey
2.3.2B Fiscal Metering Station
Description Status Percentage
Payment
- Civil
- sitepreparation to final grade 20%
- concrete pours complete 15%
- structural steel complete 15%
- buildings complete 30%
- fencing 5%
- final site preparation and clean- 15%
up complete

- Mechanical
- skid/equipment installation 15%
- piping complete 40%
- instrument hook up 15%
- paint and insulation 15%
- cleaning, drying and Hydro test 15%

- Electrical
- Equipment installed 20%
- cable laid & terminated 20%
- MCC wired 25%
- grounding/lighting complete 15%
- System Tested 20%
- Control/Telecommunication
Hardware installed 30%

3
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS

Control 15%
Telecom.
- System Configured 30%
Control 10%
Telecom
- Interfacing to GCC System 10%
Control 5%
Telecom

2.3.2C Block Valves Stations


Description Status Percentage
Payment
- Civil
- site preparation to final grade 10%
BVS, SDV & Pigging area - concrete pours complete 15%
- structural steel complete 15%
- buildings complete 40%
- paving 5%
- final site preparation and 15%
clean-up complete

- Mechanical
- equipment installed 15%
- piping/valves complete 45%
- instrument hook up 15%
- paint and insulation 15%
- testing complete 10%

- Electrical
- Equipment installed 30%
- cable laid & terminated 30%
- grounding/lighting complete 20%
- System Tested 20%

- Control/Telecommunication
Hardware installed
Control 40%
Telecom. 20%
- System Configured
Control 30%
Telecom 10%

4
SYRIAN GAS COMPANY DTGD-HOMS
ARAB GAS P/L PROJECT- PHASE I EXHIBIT-C
INVOICING AND PAYMENTS

2.3.2.D Pipeline Construction


Excavation 15%
Welding 25%
X-ray 5%
Lowering and back filling 20%
Cleaning 5%
Hydro test 10%
Drying 5%
Sign board installed 5%
R.O.W. cleaned 10%

2.3.2.E Cathodic Protection


-deep wells drilled & crossing installed 20%
-testing stations installed 10%
-current monitoring stations installed 15%
-rectifiers installed 5%
-transformers installed 5%
-lightening and surge protection installed 10%
-anodes installed 5%
-panels installed 5%
-cables installed and connected 15%
-system tested 10%

2.4 Commissioning (including initial spare parts and consumable) & Start-up

- FMS commissioned, Successful 20%


start-up and introducing of
Hydrocarbon.
- BVSs commissioned successfully 20%
- Pipeline commissioned 60%

Signature: _______________________ Date: _______________________