Professional Documents
Culture Documents
MSRA - Ceiling access fixing and repairing works
MSRA - Ceiling access fixing and repairing works
Project Project
QNB FMS Doha , Qatar
Name: Location:
Service Provider Company
COMO FMS
Name:
Service Provider Contact
Shan Devasia Joseph
Person:
Service Provider Contact
55141750
Number:
Submittal Approval
Date: Date:
The purpose of this guide is to highlight safe working practices for: Working above false ceilings (in
false ceiling voids)
1. Identify the correct equipment and tools required to perform your tasks safely
2. Use all necessary personal protective equipment.
3. Cordon off work area if practical to do so and use appropriate safety signage.
4. Suitable signs and barriers will be positioned directly below works to warn of overhead
operations.
5. Tiles should not be removed whilst persons are directly beneath the area of works.
6. Push gently up on the centre of the tile, and tapping the corners gently it should lift easily
out of the grid, turn the tile through 90 degrees, and lower it through the grid square.
7. Should there be resistance to lifting, do not force it. Try another tile nearby instead.
8. When the first tile is out, store it to one side where it cannot be trodden on, knocked
over, or damaged in other ways.
9. With the first time out, look carefully over the ceiling from within the grid to establish any
difficulties with other tiles to be removed. Typically these will be trunking, conduits, ducts,
insulation, etc. Some tiles may have to be left in due to equipment being fitted close to
the grid on the inside.
10. Carry on along the run to remove other tiles. Never remove all the tiles from an area as
this will weaken the grid.
11. Stack all the removed tiles in one place.
12. Never remove grid bars from the ceiling. Do not remove or cut ceiling suspension wires.
13. When tiles are removed from an area, take them away, and store them flat, in a clean
secure place, until the job is finished.
14. If possible, do not replace tiles that will have to be removed later in the job, as this will
increase the risk of damage to the tile.
15. Never lean on the grid, place weight on other tiles or the grid, or allow cables to drag
4. Access/Egress
No access to other people shall be permitted into the work area whilst work is in progress unless it
is deemed safe. Appropriate signage and/or hoarding will be set up around the work area to
prevent access. Such signs and hoarding will be removed and area made-good on completion of
work. Alternative arrangements to be provided: Suitable signage to be fixed to show the
alternative egress or emergency escape.
5. Lighting
• Arrangements for ensuring that work place(s) are provided with adequate illumination:
- Work place survey for lighting fixtures before starts.
- Provide extra lighting source (torch light, mobile lighting) if required.
- In case of lighting emergency shutdown, battery lighting source must be arranged prior
to work start.
-
Any tools and equipment used must have maintenance records up to date and be fit for purpose.
All tools and equipment must be used as per guidelines and training.
All persons working above false ceilings must receive appropriate training
Under no circumstances shall unqualified staff carry out any carpentry work.
Materials Safety Data Sheets to be available, reviewed and updated for the above materials
monthly to be compliant with COSHH requirements.
9. Waste Management
Ensure work area is clear of any waste and hazardous materials before starting the work
Any waste accumulation from activities shall be removed and disposed of immediately in the
waste receptacles provided.
Hazardous waste must be disposed of in the appropriate receptacles and stored in the secure wet
waste room until removal from site.
This is to confirm that all operatives, involved in the execution of works described in this method
statement have, understand the method statement and will perform works in accordance as such.
Site: QNB Activity: Ceiling access Date Performed: Review Date: 1 year after or but not limited to; changes in the machine,
fixing and repairing works people, scope, location, or any incident that occurred
CONSEQUENCE
Assessed Risk Level Description of Risk Level Actions
C Insignificant Minor Moderate Major Catastrophic
P (1) (2) (3) (4) (5) Extreme or If an incident is to occur, it Stop the activity, immediate
Very Unacceptable (20-25) would be likely that a actions
Acceptable Acceptable Acceptable Acceptable Adequate permanent, debilitating injury
Unlikely
(1) (2) (3) (4) (5) or multiple deaths would
(1)
result.
Unlikely Acceptable Acceptable Adequate Adequate Tolerable
LIKELIHOOD
CFMS-IMS-HSE-F-052|Rev00|July 01 2018
CFMS-IMS-RA-SEC-001-
Doc No
20022020-01
RISK ASSESSMENT Rev No 01
Ceiling access fixing and repairing works Date
Page 1-3
Falling from Height Always a risk when Workers performing 3 4 12 -Avoid performing the work at 3 3 9 During work COMO FMS
(Use of Ladders) working above the job at risk for height if possible. execution Supervisor
ground. Ladders may injury -Permit to Work is obtained.
fail if condition is poor -Toolbox talks performed before
or improper use can work commencement. -Ladders
lead to injury, inspected and in good condition.
-Ladder training done.
-Proper PPE used.
-Over reaching is avoided.
-Avoid moving ladders when
somebody is on-board.
- 3 point contact rule in effect.
Use of step ladders Poor condition and Staff at risk for fall 3 4 12 -Ladders are checked before 3 2 6 During work COMO FMS
improper use of from height using the use. execution Supervisor
ladders can lead to ladder which can -Anti-slip mechanism in place
injury cause injury. and in good condition.
-Locks are engaged.
-Three-point gait is observed
-Leave at least 3 ladder rungs to
give space for balance.
-Person standby on the ground
to hold the ladder.
-Early warning signs to show
somebody is using ladder.
-Isolate the area.
Exposure to wood Dust can be inhaled Staff at risk from 3 3 9 Use safety mask to prevent from 2 2 4 During work COMO FMS
dust when cutting the Respiratory disease, air born particle inhaling during execution Supervisor
gypsum board for chronic conditions the cutting and plane.
celling work. due to the inhaling of
CFMS-IMS-HSE-F-052|Rev00|July 01 2018
CFMS-IMS-RA-SEC-001-
Doc No
20022020-01
RISK ASSESSMENT Rev No 01
Ceiling access fixing and repairing works Date
Page 1-3
CFMS-IMS-HSE-F-052|Rev00|July 01 2018