Conductor Installation Check List

Name Of Line:
Section __________ to __________ Conductor Type:
Starting Date: Finishing Date:
Installation Checks
Connection plates are properly fixed to towers for stringing attachment Yes/No
Proper string and insulator type are used at respective towers as per attachment Yes/No
Installation of strings has been done as per supplier's drawings Yes/No
Split pins has been installed as per requirement with flaterning of mouth Yes/No
Materials have been installed as per installation schedule
Number of midspan joints used in section__________________________
Span No of joints Usage Details

Section Length _______________________ kms No of Spans ________________________


Required Sag Actual Sag
Section Temp (°C) Sec Phase
(daN) (daN)

Sag Measurement Taken

Total length of conductors used in section (kms) :


Post Installation Check Up
Ground clearence for conductor is maintained as per requirement Yes/No
Conductors are installed without any damage Yes/No
If any damage occured during installation, has been rectified using repair sleeves Yes/No NA
All three phases are having same sag Yes/No
Clipping of conductor have been completed Yes/No
The mid span joints and dead end joints are properly compressed according to manufacturer Yes/No
Proper jumpers are installed as per drawing and type Yes/No
Proper sag maintained to attain clearence at high voltage crossing & roads Yes/No
The stockbridge vibration dampers are properly installed according to spacer damper chart Yes/No
Remarks:

Contractor Consultant Employer


Name Name Name
Date Date Date
Signature Signature Signature