Customer Name
Location
Contact Person Name/ Mobile No
E- Mail ID
Date
Mechanical Installation
2 Drive room civil work completed in all aspect
3 Drive Installed in Dust-free Room
4 Ventilation for hot air moveout from drive room arrangement has made
5 Enough free space around the unit
6 Distance between back side Panel and wall/wall/another panel
7 The unit fastened on the floor
The above details are checked, and correct data filled for smooth and efficient commissioning.
In Charge of Commissioning
Note: If more than one drive is there, please making a separate photocopy of the checklist and send the same to
M/s ABB after fill-in.