14 01-Feb-24 14-Feb-24 0 14-Feb-24, Submittals Submittals GF - Sheikh's Majlis 14 01-Feb-24 14-Feb-24 0 14-Feb-24, GF - Sheikh's Majlis KFK-UNI-1010 Submission of Engineering Drawings - SM 7 01-Feb-24 07-Feb-24 0 Submission of Engineering Drawings - SM KFK-UNI-1030 Approval of Engineering Drawings - SM 7 08-Feb-24 14-Feb-24 0 Approval of Engineering Drawings - SM SF - President's Meeting R Room 14 01-Feb-24 14-Feb-24 0 14-Feb-24, SF - President's Meeting Room KFK-UNI-1020 Submission of Engineering Drawings - MR 7 01-Feb-24 07-Feb-24 0 Submission of Engineering Drawings - MR KFK-UNI-1040 Approval of Engineering Drawings - MR 7 08-Feb-24 14-Feb-24 0 Approval of Engineering Drawings - MR 63 09-Feb-24 11-Apr-24 0 11-Apr-24, Ground floor - Sheikh's Majlis Ground floor - Sheikh's Sheikh' Majlis Civil Works 4 09-Feb-24 12-Feb-24 0 12-Feb-24, Civil Works KFK-UNI-1050 Demolition of Existing Flooring 3 09-Feb-24 11-Feb-24 0 Demolition of Existing Flooring KFK-UNI-1060 Demolition of Existing Ceiling 2 09-Feb-24 10-Feb-24 1 Demolition of Existing Ceiling KFK-UNI-1090 Disposal of Debris 1 12-Feb-24 12-Feb-24 0 Disposal of Debris MEP Works 13 13-Feb-24 25-Feb-24 27 25-Feb-24, MEP Works KFK-UNI-1110 Installation of MEP 1st Fix for Ceiling 6 13-Feb-24 18-Feb-24 0 Installation of MEP 1st Fix for Ceiling KFK-UNI-1150 Installation of MEP 1st Fix for Walls 4 19-Feb-24 22-Feb-24 27 Installation of MEP 1st Fix for Walls KFK-UNI-1190 Installation of MEP 1st Fix for Flooring 3 23-Feb-24 25-Feb-24 27 Installation of MEP 1st Fix for Flooring Ceiling Finishes 23 18-Feb-24 12-Mar-24 4 12-Mar-24, Ceiling Finishes KFK-UNI-1130 MEP Clearance to proceed for Ceiling 0 18-Feb-24 0 MEP Clearance to proceed for Ceiling, KFK-UNI-1160 Ceiling Suspension for Gypsum Works 4 19-Feb-24 22-Feb-24 0 Ceiling Suspension for Gypsum Works KFK-UNI-1200 Installation of MEP 2nd Fix for Ceiling 3 23-Feb-24 25-Feb-24 0 Installation of MEP 2nd Fix for Ceiling KFK-UNI-1230 Ceiling Closing - False Ceiling Gypsum Board 4 26-Feb-24 29-Feb-24 0 Ceiling Closing - False Ceiling Gypsum Board KFK-UNI-1240 MEP Clearance for Ceiling Closing 0 26-Feb-24 0 MEP Clearance for Ceiling Closing, 26-Feb-24 KFK-UNI-1270 Installation of Gypsum Board Bulkhead for Ceiling 4 28-Feb-24 02-Mar-24 0 Installation of Gypsum Board Bulkhead for Ceiling KFK-UNI-1280 Installation of Gypsum Board Light Cove 2 01-Mar-24 02-Mar-24 0 Installation of Gypsum Board Light Cove KFK-UNI-1300 Taping, Jointing, Stucco, Primer 2 03-Mar-24 04-Mar-24 0 Taping, Jointing, Stucco, Primer KFK-UNI-1320 Installation of GRG Moulded Cornice for Ceiling 2 05-Mar-24 06-Mar-24 4 Installation of GRG Moulded Cornice for Ceiling KFK-UNI-1360 Installation of GRG Mouldings for Ceiling 2 07-Mar-24 08-Mar-24 4 Installation of GRG Mouldings for Ceiling KFK-UNI-1400 Surface preparation & Corner Treatment for GRG Works 2 09-Mar-24 10-Mar-24 4 Surface preparation & Corner Treatment for GRG Works KFK-UNI-1440 Application of 1st Coat of Paint 2 11-Mar-24 12-Mar-24 4 Application of 1st Coat of Paint Wall Finishes 19 05-Mar-24 23-Mar-24 0 23-Mar-24, Wall Finishes KFK-UNI-1330 Installation of MEP 2nd Fix for Walls 3 05-Mar-24 07-Mar-24 0 Installation of MEP 2nd Fix for Walls KFK-UNI-1380 Walls Closing - GRG Mouldings for the Wall 7 08-Mar-24 14-Mar-24 0 Walls Closing - GRG Mouldings for the Wall KFK-UNI-1390 MEP Clearance for Ceiling Closing 0 08-Mar-24 0 MEP Clearance for Ceiling Closing, 08-Mar-24 KFK-UNI-1460 Surface Preparation & Corner Treatment for Paint Finish 2 15-Mar-24 16-Mar-24 0 Surface Preparation & Corner Treatment for Paint Finish KFK-UNI-1480 Application of Paint to the GRGs 2 17-Mar-24 18-Mar-24 0 Application of Paint to the GRGs KFK-UNI-1500 Application of Emulsion Paint to the Existing Walls 3 19-Mar-24 21-Mar-24 0 Application of Emulsion Paint to the Existing Walls KFK-UNI-1520 Installation of Marble Skirting for the Walls 2 22-Mar-24 23-Mar-24 0 Installation of Marble Skirting for the Walls Flooring Finishes 8 23-Mar-24 31-Mar-24 0 31-Mar-24, Flooring Finishes KFK-UNI-1540 MEP Clearance to proceed for Flooring 0 23-Mar-24 0 MEP Clearance to proceed for Flooring, KFK-UNI-1560 Installation of Dark Emperador Marble Flooring 3 24-Mar-24 26-Mar-24 0 Installation of Dark Emperador Marble Flooring KFK-UNI-1580 Instalaltion of Marble Borders for Flooring 1 27-Mar-24 27-Mar-24 0 Instalaltion of Marble Borders for Flooring KFK-UNI-1600 Installation of White Marble for Flooring 2 28-Mar-24 29-Mar-24 0 Installation of White Marble for Flooring KFK-UNI-1620 Installation of Decorative Waterjet Marble Flooring 2 30-Mar-24 31-Mar-24 0 Installation of Decorative Waterjet Marble Flooring
Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 3
Primary Baseline Remaining Work Milestone Shades Interiors LLC Khorfakan University Program of Works Majlis & Meeting Room Activity ID Activity Name Planned BL Project Start BL Project Finish Total Float February 2024 March 2024 April 2024 May 2024 Duration 0 22 29 05 12 19 26 04 11 18 25 01 08 15 22 29 06 13 Joinery Works 3 01-Apr-24 03-Apr-24 0 03-Apr-24, Joinery Works KFK-UNI-1650 Wooden Window Box Framing for the Walls 1 01-Apr-24 01-Apr-24 0 Wooden Window Box Framing for the Walls KFK-UNI-1700 Installation of Wooden Doors 2 02-Apr-24 03-Apr-24 0 Installation of Wooden Doors FF & E Works 5 04-Apr-24 08-Apr-24 0 08-Apr-24, FF & E Works KFK-UNI-1750 Installation of Calligraphy and Art Works 2 04-Apr-24 05-Apr-24 0 Installation of Calligraphy and Art Works KFK-UNI-1770 Installation of Curtains 1 06-Apr-24 06-Apr-24 0 Installation of Curtains KFK-UNI-1800 Installation of Loose Furniture 2 07-Apr-24 08-Apr-24 0 Installation of Loose Furniture Final Finishes 11 01-Apr-24 11-Apr-24 0 11-Apr-24, Final Finishes Final Paint Work 3 09-Apr-24 11-Apr-24 0 11-Apr-24, Final Paint Work KFK-UNI-1840 Final Paint Work for Ceiling and Walls 3 09-Apr-24 11-Apr-24 0 Final Paint Work for Ceiling and Walls Lights & MEP Final Fix 7 01-Apr-24 07-Apr-24 2 07-Apr-24, Lights & MEP Final Fix KFK-UNI-1660 Installation of chandelier 2 01-Apr-24 02-Apr-24 2 Installation of chandelier KFK-UNI-1690 MEP Final Fix 5 03-Apr-24 07-Apr-24 2 MEP Final Fix Testing Commisioning 2 08-Apr-24 09-Apr-24 2 09-Apr-24, Testing Commisioning KFK-UNI-1780 Testing & Commissioning of MEP Equipments 2 08-Apr-24 09-Apr-24 2 Testing & Commissioning of MEP Equipments 63 09-Feb-24 11-Apr-24 0 11-Apr-24, Second Floor - President's Meetin Second Floor - Presid President's Meeting Room Civil Works 4 09-Feb-24 12-Feb-24 0 12-Feb-24, Civil Works KFK-UNI-1070 Demolition of Existing Flooring 3 09-Feb-24 11-Feb-24 0 Demolition of Existing Flooring KFK-UNI-1080 Demolition of Existing Ceiling 2 09-Feb-24 10-Feb-24 1 Demolition of Existing Ceiling KFK-UNI-1100 Disposal of Debris 1 12-Feb-24 12-Feb-24 0 Disposal of Debris MEP Works 13 13-Feb-24 25-Feb-24 27 25-Feb-24, MEP Works KFK-UNI-1120 Installation of MEP 1st Fix for Ceiling 6 13-Feb-24 18-Feb-24 0 Installation of MEP 1st Fix for Ceiling KFK-UNI-1170 Installation of MEP 1st Fix for Walls 4 19-Feb-24 22-Feb-24 27 Installation of MEP 1st Fix for Walls KFK-UNI-1210 Installation of MEP 1st Fix for Flooring 3 23-Feb-24 25-Feb-24 27 Installation of MEP 1st Fix for Flooring Ceiling Finishes 24 18-Feb-24 13-Mar-24 4 13-Mar-24, Ceiling Finishes KFK-UNI-1140 MEP Clearance to proceed for Ceiling 0 18-Feb-24 0 MEP Clearance to proceed for Ceiling, KFK-UNI-1180 Ceiling Suspension for Gypsum Works 4 19-Feb-24 22-Feb-24 0 Ceiling Suspension for Gypsum Works KFK-UNI-1220 Installation of MEP 2nd Fix for Ceiling 3 23-Feb-24 25-Feb-24 0 Installation of MEP 2nd Fix for Ceiling KFK-UNI-1250 Ceiling Closing - False Ceiling Gypsum Board 4 26-Feb-24 29-Feb-24 0 Ceiling Closing - False Ceiling Gypsum Board KFK-UNI-1260 MEP Clearance for Ceiling Closing 0 26-Feb-24 0 MEP Clearance for Ceiling Closing, 26-Feb-24 KFK-UNI-1290 Installation of Gypsum Board Light Cove 3 01-Mar-24 03-Mar-24 0 Installation of Gypsum Board Light Cove KFK-UNI-1310 Taping, Jointing, Stucco, Primer 2 04-Mar-24 05-Mar-24 0 Taping, Jointing, Stucco, Primer KFK-UNI-1340 Installation of GRG Moulded Cornice for Ceiling 3 06-Mar-24 08-Mar-24 4 Installation of GRG Moulded Cornice for Ceiling KFK-UNI-1370 Installation of GRG Mouldings for Ceiling 1 09-Mar-24 09-Mar-24 4 Installation of GRG Mouldings for Ceiling KFK-UNI-1430 Surface preparation & Corner Treatment for GRG Works 2 10-Mar-24 11-Mar-24 4 Surface preparation & Corner Treatment for GRG Works KFK-UNI-1450 Application of 1st Coat of Paint 2 12-Mar-24 13-Mar-24 4 Application of 1st Coat of Paint Wall Finishes 18 06-Mar-24 23-Mar-24 0 23-Mar-24, Wall Finishes KFK-UNI-1350 Installation of MEP 2nd Fix for Walls 3 06-Mar-24 08-Mar-24 0 Installation of MEP 2nd Fix for Walls KFK-UNI-1410 Walls Closing - GRG Mouldings for the Wall 7 09-Mar-24 15-Mar-24 0 Walls Closing - GRG Mouldings for the Wall KFK-UNI-1420 MEP Clearance for Ceiling Closing 0 09-Mar-24 0 MEP Clearance for Ceiling Closing, 09-Mar-24 KFK-UNI-1470 Surface Preparation & Corner Treatment for Paint Finish 2 16-Mar-24 17-Mar-24 0 Surface Preparation & Corner Treatment for Paint Finish KFK-UNI-1490 Application of Paint to the GRGs 2 18-Mar-24 19-Mar-24 0 Application of Paint to the GRGs KFK-UNI-1510 Application of Emulsion Paint to the Existing Walls 2 20-Mar-24 21-Mar-24 0 Application of Emulsion Paint to the Existing Walls KFK-UNI-1530 Installation of Marble Skirting for the Walls 2 22-Mar-24 23-Mar-24 0 Installation of Marble Skirting for the Walls Flooring Finishes 9 23-Mar-24 01-Apr-24 0 01-Apr-24, Flooring Finishes KFK-UNI-1550 MEP Clearance to proceed for Flooring 0 23-Mar-24 0 MEP Clearance to proceed for Flooring, KFK-UNI-1570 Installation of Dark Emperador Marble Flooring 2 24-Mar-24 25-Mar-24 0 Installation of Dark Emperador Marble Flooring KFK-UNI-1590 Instalaltion of Marble Borders for Flooring 1 26-Mar-24 26-Mar-24 0 Instalaltion of Marble Borders for Flooring
Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 3
Primary Baseline Remaining Work Milestone Shades Interiors LLC Khorfakan University Program of Works Majlis & Meeting Room Activity ID Activity Name Planned BL Project Start BL Project Finish Total Float February 2024 March 2024 April 2024 May 2024 Duration 0 22 29 05 12 19 26 04 11 18 25 01 08 15 22 29 06 13 KFK-UNI-1610 Installation of Crema Marfil Polished Marble 3 27-Mar-24 29-Mar-24 0 Installation of Crema Marfil Polished Marble KFK-UNI-1630 Inspection for Grouting 1 30-Mar-24 30-Mar-24 0 Inspection for Grouting KFK-UNI-1640 Grouting for Marble Flooring 2 31-Mar-24 01-Apr-24 0 Grouting for Marble Flooring Joinery Works 5 02-Apr-24 06-Apr-24 2 06-Apr-24, Joinery Works KFK-UNI-1670 Wooden Window Box Framing for the Walls 1 02-Apr-24 02-Apr-24 0 Wooden Window Box Framing for the Walls KFK-UNI-1720 Installation of Wooden Doors 1 03-Apr-24 03-Apr-24 0 Installation of Wooden Doors KFK-UNI-1740 Installation of Sliding Door 3 04-Apr-24 06-Apr-24 2 Installation of Sliding Door FF & E Works 8 04-Apr-24 11-Apr-24 0 11-Apr-24, FF & E Works KFK-UNI-1730 Installation of Calligraphy and Art Works 2 04-Apr-24 05-Apr-24 0 Installation of Calligraphy and Art Works KFK-UNI-1760 Installation of Curtains 1 06-Apr-24 06-Apr-24 0 Installation of Curtains KFK-UNI-1790 Installation of Loose Furniture 2 07-Apr-24 08-Apr-24 0 Installation of Loose Furniture KFK-UNI-1830 Installation of Plant and Planters 2 09-Apr-24 10-Apr-24 0 Installation of Plant and Planters KFK-UNI-1850 Installation of TV Screen 1 11-Apr-24 11-Apr-24 0 Installation of TV Screen Final Finishes 10 02-Apr-24 11-Apr-24 0 11-Apr-24, Final Finishes Final Paint Work 3 09-Apr-24 11-Apr-24 0 11-Apr-24, Final Paint Work KFK-UNI-1820 Final Paint Work for Ceiling and Walls 3 09-Apr-24 11-Apr-24 0 Final Paint Work for Ceiling and Walls Lights & MEP Final Fix 3 02-Apr-24 04-Apr-24 4 04-Apr-24, Lights & MEP Final Fix KFK-UNI-1710 MEP Final Fix 3 02-Apr-24 04-Apr-24 4 MEP Final Fix Testing Commisioning 3 05-Apr-24 07-Apr-24 4 07-Apr-24, Testing Commisioning KFK-UNI-1810 Testing & Commissioning of MEP Equipments 3 05-Apr-24 07-Apr-24 4 Testing & Commissioning of MEP Equipments 4 12-Apr-24 15-Apr-24 0 15-Apr-24, Handing Over Handing Over KFK-UNI-1860 Snagging & De-Snagging 2 12-Apr-24 13-Apr-24 0 Snagging & De-Snagging KFK-UNI-1870 Close Out & Handing Over 2 14-Apr-24 15-Apr-24 0 Close Out & Handing Over
Actual Level of Effort Actual Work Critical Remaining Work Page 3 of 3